Artist rendering

Shoreline Stabilization Project

In northern Palm Beach County on Florida’s urbanized Treasure Coast lies the 120-acre Jupiter Inlet Lighthouse Outstanding Natural Area (ONA). The ONA was designated by Congress in 2008 for the preservation, protection and enhancement of seven key resources and values found on the site; these include the remarkable biodiversity and rich history of the site. The site is the only unit of the National Conservation Lands east of the Mississippi River, and the only unit managed by the BLM’s Eastern States. 

On March 24, 2025, the Bureau of Land Management broke ground on a critical infrastructure project to protect and enhance the iconic Jupiter Inlet Lighthouse and unique, significant resources of surrounding public lands. The community, local elected officials, and special guests joined BLM officials in celebrating the $16 million effort to stabilize the shoreline and incorporate resilient recreation features at the ONA. 

With an investment of $8.3 million from the Great American Outdoors Act and $7,000,000 in support from the Florida Inland Navigation District, the project will add engineered and living shoreline components to reduce erosion and sediments entering the Intracoastal Waterway. 

 

Two women in hard hats and safety vests observe a shoreline project by a clear blue waterway with buildings in the background.
Shayne Banks, SSDO District Manager (left) and Kathleen Henderson, Dickenson Infrastructure (right) check-in on the site preparations prior to driving the sheet piles for the lower retaining wall. Kathleen, as Quality Control Manager, also checks environmental protections, such as the turbidity curtain, are correctly maintained.

 

Project Description 

Covering about 5 acres, the project includes construction of a retaining wall, installation of in-water wave breaks, pilings, artificial reef structures, and an addition of shoreline access points. The planting of upland and tidal vegetation, including mangroves, will enhance and protect the area’s terrestrial and marine habitats. 

 

Project Timeline

ONA project timeline graphic

 

Benefits

The ONA Shoreline Stabilization Project significantly enhances public safety by preventing erosion and protecting coastal infrastructure. Improved shoreline stability will ensure safety for boaters and shoreline users at the ONA and within the adjacent intracoastal waterway, reducing hazards to navigation. Additionally, the project enhances recreational opportunities by preserving the natural landscape, allowing for continued enjoyment of outdoor activities such as fishing, kayaking, and wildlife observation in a safer environment.

graphic of workflow
The Challenge

The ONA is losing approximately 7 feet of shoreline each year due to severe erosion, threatening the historic lighthouse structure and surrounding natural habitats.

 

Image shows sand and soil eroding onto shoreline
Erosion of the shoreline evident prior to construction mobilization.
 
Ongoing erosion poses significant threats to:
  • The historic Jupiter Inlet Lighthouse
  • Critical natural habitats within the 120-acre ONA
  • Safe navigation on the Intracoastal Waterway
  • Public safety along the shoreline

Without intervention, continued erosion will result in potential structural damage to the lighthouse, loss of protected natural areas, and disruption to maritime activities in this historically and ecologically significant area.

The Solution

The BLM and its state and local partners are taking action to protect and enhance the shoreline at the ONA for all to enjoy now and into the future.

 

A yellow excavator on a construction site near turquoise waters, with workers and a barrier in the background under a blue sky.
A long-reach backhoe removes overhanding sediment from the shoreline ready for installation of the lower portion of the retaining wall.
 
Project Scope:
  • Stabilize approximately 5 acres or 1 mile of eroding shoreline
  • Timeline: January 6, 2025 to October 2026
  • Total Budget: $16 million
Funding Sources:
  • Great American Outdoors Act (GAOA): $8.3 million
  • Florida Inland Navigation District (FIND): $7 million
  • Additional sources: $0.7 million
Implementation Methods:
  • Engineered structures: Rip-rap wave breaks, retaining walls, terraced seawalls
  • Living shoreline techniques: Native vegetation planting, mangrove restoration
  • Creation of salt marsh habitat and artificial reef structures
  • ADA-compliant recreational amenities
Public Safety & Navigation Benefits

 

Eroded sandy beach with palm trees, exposed roots, and scattered debris, under a cloudy sky with construction cranes in the background.
Erosion of the shoreline evident prior to construction mobilization.

 

  • Eliminates falling vegetation and collapsing sand
  • Stops vegetation debris in the waterway creating hazards to boating
  • Reduces sediment entering the intracoastal waterway, and therefore reduces a portion of the required routine dredging to maintain navigability
  • Adds navigational aids to support use of the Intracoastal waterway.
Recreational Enhancements
New Public Access Features:
  • New approximately 700-foot public boardwalk along the Loxahatchee River
  • Construction of approximately 800-foot terraced wall with 9 stairways for improved shoreline access
  • Enhanced snorkeling and marine education areas
  • New dock facility for ferries and water taxis
Accessibility Improvements:
  • ADA-compliant dock and access improvements
  • Improved access points to the Loxahatchee River & Indian River Lagoon
  • Dedicated boat access spots with access to the ONAs trail system
  • Safer recreational areas for visitors of all abilities
  • Enhanced educational opportunities about coastal ecosystems

Note: Boat beaching spots will be reduced during construction.

Economic Benefits
Tourism and Heritage Protection:
  • Safeguarding the Jupiter Inlet Lighthouse, a major tourist attraction
  • Preservation of a historic site that generates approximately $14.7 million annually for Palm Beach County
  • Protection of a site that draws over 150,000 visitors per year
Economic Development and Navigation:
  • Protection of the Intracoastal Waterway's navigability for commercial and recreational vessels
  • Job creation through Great American Outdoors Act funding
  • Reduced long-term maintenance costs for waterway dredging
  • Support for local maritime businesses and recreation industries
Environmental Considerations
Habitat Creation and Enhancement:
  • Planting of 10,000 new mangroves
  • Creation of 2-acre salt marsh habitat
  • Installation of artificial reef structures
  • Protection of habitats for sensitive and endangered species
Erosion Control and Water Quality:
  • Significant reduction in shoreline erosion rate
  • Decrease in sediment flow into the Intracoastal Waterway
  • Improved water quality in the Loxahatchee River
  • Protection of the 120-acre ONA
Construction Information
A worker in a safety vest observes a yellow skid steer clearing vegetation in a lush, tropical area with palm trees.
Roller-chopper clears vegetation to allow for installation of the gopher tortoise exclusion fencing.
 
Project Timeline:
  • Start date: January 6, 2025
  • Completion: August 2026
  • Phased approach to minimize disruption to visitors and wildlife
Visitor Impact During Construction:
  • Wildlife protection measures in place, including gopher tortoise relocation
  • Temporary trail rerouting of approximately 500-foot segment
  • Intermittent closures of certain areas
  • Limited boat anchorage accessibility during construction phases
  • Informational signage and updates available on-site

 

 

Status & Milestones

Notice to Proceed issued to Dickerson Infrastructure this month, and Contract administration (scheduling, submittals, engineering reviews continue behind the scenes) begins behind the scenes.

Construction equipment and contractor will mobilize to the ONA, setting up temporary offices on-site. Vegetation salvage of herbaceous species for care at The Nature Conservancy Blowing Rocks Preserve is underway. The effort will save approximately 200 individual plants of a range of species to be returned to the site upon completion of the projects.

Gopher Tortoise exclusion fencing installed and tortoise relocations out of the construction zone underway this month. Turbidity curtain installation also to be completed this coming month to protect the Intracoastal waterway from any sediment generated by the project.

Clearing, Grubbing, other site preparations for the retaining wall area is completed.

Sheet Pile is arriving throughout May and into June. Installation of the sheet pile should start before the end of the month.

 

A flatbed truck loaded with stacked metal sheets parked under a large tree in a sunny outdoor setting with a walking path nearby.
Sheet pile for the Shoreline Stabilization project’s lower retaining wall arrives on-site.

 

The sheet pile retaining wall is approximately half-way complete.

Construction site along a shoreline, featuring heavy machinery, a sand barrier, and a calm waterway lined with orange booms.

Touch up work has started on the sheet piles to ensure a complete corrosion resistant finish, and the final product has a clean uniform color.

First helical anchor performance test and the start of helical installation begins.

A group of workers in safety helmets and vests collaborates on-site, focusing on equipment amidst a green background.
Helical anchor performance test

Begining formwork for concrete cap pouring.

Construction workers prepare a concrete form along a beachside, with heavy machinery and a waterway in the background under sunny skies.
Working on rebar before concrete is poured.

Turbidity curtain installation is complete to protect the Loxahatchee River from sediments generated by the installation of additional wave breaks along the site’s southern shoreline.

Sheet pile installation is completed.

Construction site with heavy machinery near a waterfront, showcasing excavators, workers, and a clear blue sky.
The last sheet pile is installed.

Bid option 2 breakwater installation completed. This area of work included the filling+leveling of a large grass event lawn, and the installation of two limestone breakwaters, putting this project area at 95% completion. The breakwater work is being completed by BDI Marine & Site Contractors, professionals are ensuring every limestone rock is placed down to have 3 points of contact and be aesthetically pleasing. 

Two workers on a beach are adjusting a black net in shallow water, with a wooden pier and construction equipment in the background.
Geo Netting that goes in the middle of limestone breakwaters to secure the bedding stone

Last helical anchor of over 200 installed. Performance tests were completed every 9 anchors to ensure the wall is held in place.

Construction site view showing sandy terrain with equipment and a waterway lined with palm trees in the background.
View of helical anchors looking north.

Concrete cap pouring

Remove formwork from concrete caps after curing via a drip hose for 7 days. This marks the final step in the sheet pile wall, allowing the construction of the gravity block wall to commence.

Construction site along a waterfront, featuring wooden frameworks, an excavator, and a yellow containment barrier in the water.
Curing process using drip hose done for 7 days after the pour.
Two workers in safety vests and helmets conduct material testing on a construction site, using equipment on the tailgate of a pickup truck.
The aeration test is one of many tests completed every 50 yards to ensure the quality of the concrete.

Begin construction of the gravity block wall, the upper of the two retaining walls being installed on site.

Stacked concrete barrier blocks form a retaining wall next to a mound of sand, under a cloudy sky near a waterfront.
Cross section of block gravity wall. To the left is the sheet pile terrace and the right side will be filled in to meet the natural elevation of the property.
Sunrise showing the construction of the shoreline stabilization project
Sunrise over the shoreline taken on 12/04/2025

Instillation of the gravity block wall was completed.

Wildlife protected but not disturbed! Gopher tortoise near his burrow next to the construction site.

Gopher tortoise with a cattle egret in a grassy area with fencing
Gopher tortoise with a cattle egret on the property. 

While the concrete was curing, backfill was compacted and tested. The backfill competent for the lower retaining wall was complete.

Begin installing stair piles that will allow for movement from the shoreline to the upper portion of the property.

Construction equipment surrounding a rock wall
Pilings being installed on the middle terrace.
Steep looking stairs leading down to the shoreline
Stairs leading down to the shoreline

The first tree is planted on the shoreline! A mature Sabal palmetto, commonly referred to as a Cabbage Palm was installed on the upper retaining wall. This is the first of several hundred more plants to be installed along the 800’ construction site, plantings will mimic the ecosystems found on site. 

Workers loading a cabbage palm onto construction equipment
With the help of members of the American Conservation Crew, cabbage palms are being salvaged & prepared to transplant to other areas of the property. 

First limestone breakwater work began in the Indian river lagoon portion of the waterway. This chain of breakwater will run along the property to the retaining wall, protecting a large portion of the property, creating habitat and snorkeling interest.

rocks piled along a sandy shoreline with construction equipment in the background
Breakwater being installed near Cato’s bridge

 

3-month Look Ahead

Contract begins. Most work occurring behind the scenes with engineering reviews of submittals, materials ordering and scheduling. On site environmental protections will be implemented as construction equipment is mobilized to the ONA. Clearing and grubbing of the construction zone for the retaining wall portion of the project will occur resulting in minor reroutes of site trails and public use area restrictions. Earthwork will begin to prepare for retaining wall construction.

Earthwork continues as materials start to arrive on-site. Sheet-pile is the first to be delivered with the Blocks for the retaining wall starting to arrive in late June. Installation of Sheet-pile is likely to begin towards the end of May.

With the sheet pile retaining wall nearly full installed, attention is now on backfilling behind the sheet pile, installing helical anchors to hold the sheets in place, and touching up the sheet pile with corrosion resistance coverings and the final color. Work will begin on the in-water components along the Loxahatchee River starting at the west end of the project with additional wave breaks being added to the existing shoreline stabilization work.

Two construction workers in hard hats and blue uniforms are using a large wrench on a metal pipe in a sandy excavation site.
The workers are completing installation of one of the nearly 100 helical anchors that hold the sheet pile in place.
Construction workers place barriers along a sandy shoreline, while a digger overhead is ready to scoop materials by the blue water.
Construction crew installing drainage material behind the sheet pile to allow water to continue to move though the soil and not build up behind the retaining wall.

Work will continue on installing stairway access through the next three months. Following the install of all stair pilings, carpentry work for the steps will begin on the seven staircases that span the stabilization project. A barge will be mobilized to help install breakwaters. Final grading of the retaining walls will be completed, allow planting of the shoreline to commence. Work will begin on the 900’ of boardwalk going around the property. 

Three manatees are seen swimming near a concrete wall in clear blue water
Manatees swimming within the turbidity curtain taken on 01/05/2026