Environmental Assessment,Finding of No Significant Impact DOI-BLM-OR-B050-2010-0017-EA Planning Completed
The Proposed Action is to construct approximately 0.7-mile of buried pipeline and install a 10-foot diameter bottomless (or two 1,500-gallon aluminum) water trough(s) within South Pasture of Juniper Ridge Allotment.
Burns District Office
(541) 573-4400
n/a
Resource Area: Three Rivers
Program Areas: Range/Wild Horses
Download: JRidgeALL.pdf
Document Publish Date
06/28/2010
Decision Record DOI-BLM-OR-B050-2010-0017-EA Planning Completed
The proposed decision is to authorize implementation of the Proposed Action (Alternative B). The Proposed Action will construct approximately 0.7-mile of buried pipeline and install a 10-foot diameter bottomless (or two 1,500-gallon aluminum) water trough(s) within the South Pasture of Juniper Ridge Allotment.
Burns District Office
(541) 573-4400
n/a
Resource Area: Three Rivers
Program Areas: Range/Wild Horses
Download: JRidgeProposedDRJune29.pdf
Document Publish Date
Protest:
06/29/2010
07/01/2010 - 08/14/2010

Historic Burns Planning Documents / Current Burns Planning Documents