U.S. DEPARTMENT OF THE INTERIOR  BUREAU OF LAND MANAGEMENT  
ePlanning DOI-BLM-ID-T030-2012-0013-CX Help
   Video Tutorial
> NEPA Register > DOI-BLM-ID-T030-2012-0013-CX
NEPA Project Summary 
NEPA #:  DOI-BLM-ID-T030-2012-0013-CX Status:  Completed
Project Name:  Celluar Inc. Lease Amendment - Notch Butte Decision Date: 
EIS OEPC #:  FONSI Date: 
Applicant:  Cellular Inc.    
Case File Number/:
Project Number 
IDI-10111    
Start Date:     
End Date:     
 
Project Description:
Cellular Inc. would like to connect to Syringa Networks hand hole (refer to ROW IDI-37078) that is located on the southwest side of the compound on the north side of the access gate and install a buried 4 inch conduit running from the hand hole to WWC’s equipment shelter. The distance between the hand hole to the shelter is approx. 10 ft. long, one ft. wide and approx. 3 ft. deep. In order to dig the trench, WWC will rake the gravel that is currently covering the ground back enable them to roll back the weed barrier and dig the dirt for the placement of the conduit. Once the conduit is in the trench the dirt would be replaced, the weed barrier would be put in place and the gravel raked back into place.
Project Location:
T. 6 S., R. 17 E., Sec. 22
 
Project Lead:  Kovar, Debra A    
Phone Number:  (208) 677-6670    
Email Address:     
Office(s):  Shoshone FO Lead Office:  Shoshone FO
Counties:  Lincoln    
 
Program(s):  Special Interest(s): 
Cooperating Agencies:     
 


USA.Gov | No Fear Act | DOI | Disclaimer | About BLM | Notices | Get Adobe Reader® Privacy Policy | FOIA | Kids Policy | Contact Us | Accessibility | Site Map | Home This page was created by the Bureau of Land Management