U.S. DEPARTMENT OF THE INTERIOR  BUREAU OF LAND MANAGEMENT  
ePlanning DOI-BLM-ID-I030-2012-0005-CX (Spar Canyon 230 kV powerline Right of Way Assisgnment)  
> NEPA Register > DOI-BLM-ID-I030-2012-0005-CX
NEPA Project Summary 
NEPA #:  DOI-BLM-ID-I030-2012-0005-CX Status:  Completed
Project Name:  Spar Canyon 230 kV powerline Right of Way Assisgnment Decision Date:  02/16/2012
EIS OEPC #:  FONSI Date: 
Applicant:  Salmon River Electrice Cooperative Inc    
Case File Number/:
Project Number 
IDI-15966    
Start Date:     
End Date:     
 
Project Description:
Approve assignment of an existing, 20 mile long by 100 feet wide power line ROW. Assignment of the ROW will be from the current ROW holder, Thompson Creek Mining Company to the new holder, Salmon River Electric Cooperative, Inc.
Project Location:
The powerline starts at the Spar Canyon switchyard approximately 17 miles S/SE of Challis, Idaho and runs west through Spar Canyon to the South Butte switchyard approximately 25 miles S/SW of Challis, Idaho
 
Project Lead:  Vanek, Timothy R    
Phone Number:  (208) 879-6218    
Email Address:     
Office(s):  Challis FO Lead Office:  Challis FO
Counties:  Custer    
 
Program(s):  Lands and Realty Subprogram(s):  None
Cooperating Agencies:     
 

Documents: