U.S. DEPARTMENT OF THE INTERIOR  BUREAU OF LAND MANAGEMENT  
ePlanning DOI-BLM-ID-C020-2012-0010-CX Help
   Video Tutorial
> NEPA Register > DOI-BLM-ID-C020-2012-0010-CX
NEPA Project Summary 
NEPA #:  DOI-BLM-ID-C020-2012-0010-CX Status:  Completed
Project Name:  Lucile Recreation Site Turn Lane Decision Date:  01/24/2012
EIS OEPC #:  FONSI Date: 
Applicant:     
Case File Number/:
Project Number 
   
Start Date:     
End Date:     
 
Project Description:
BLM is proposing to install a turn lane at the entrance of the Lucile Recreation Site located on US Highway 95. The Idaho Transportation Department required the installation of the turnlane on the highway as part of the stipulations/mitigation for constructing the Lucile Recreation Site, and the BLM has secured funding for the project. The turn lane would be constructed under a contract within the existing 200 foot right of way (IDI-4449) held by the Idaho Transportation Department as a Federal Aid Highway. Upon completion of the this project, entering and exiting the recreation site will be much safer. Installation of the turn lane is planned for completion in the spring of 2012.
Project Location:
US Highway 95, along the Salmon River upstream from Lucile, Idaho. Boise Meridian, T.25N., R.01E, Sec. 11
 
Project Lead:  O'Neill, Joseph F    
Phone Number:  (208) 962-3683    
Email Address:     
Office(s):  Cottonwood FO Lead Office:  Cottonwood FO
Counties:  Idaho    
 
Program(s):  Land and Realty Special Interest(s): 
Cooperating Agencies:     
 