U.S. DEPARTMENT OF THE INTERIORBUREAU OF LAND MANAGEMENT
|
||||
Average Application for Permit to Drill (APD) Approval Timeframes: FY2005 - FY2012This chart illustrates the average number of days to process an APD, broken out as follows:
As an example, in FY2012, this process took an average of 228 days. This includes industry taking an average of 151 days to submit a complete APD and the BLM taking an average of 77 days to process the APD.
|
||||