GENERAL PROJECT SCHEDULE |
Dates |
Process Milestones |
Public Participation Components |
-Winter 2006/2007 |
-Notice of Intent (NOI) |
-Publication of the Notice of Intent formally initiates the revision process and begins the scoping process.
|
-Winter 2007 |
-Scoping |
-Public meetings will be held throughout the planning areas.
|
-Spring/Summer 2007 |
-Additional Scoping for the Travel Management Planning Process |
-Working groups of some form will be utilized throughout the planning areas along with public workshops.
|
-Fall 2007 |
-Alternative Formulation
|
|
-Winter 2007/2008 |
-Alternatives Assessment (Analyze Alternatives)
|
|
-Summer 2008 |
-Draft RMP/EIS |
-Notice of Availability announces the publication of the Draft RMP/EIS and starts the 90-day public comments period.
|
-Winter/Spring 2009 |
-Proposed RMP/Final EIS |
-Notice of Availability announces the publication of the Proposed RMP/Final EIS and starts the 30-day protest period and 60-day Governor’s Consistency Review.
|
-Summer 2009 |
-Record of Decision: Notice of Availability announces the approval of the RMP. |
|