Neal Hot Springs Proposed Right of Way OR-66537

Vale

Documents in Project

Environmental Assessment DOI-BLM-OR-V040-2011-008-EA Planning Completed
Vale District BLM has completed for public review, an Environmental Assessment (DOI-BLM-OR-V040-2011-008-EA) and unsigned Finding of No Significant Impact (FONSI) identifying the alternative actions for the proposed construction of exploratory geothermal well pads and access roads approximately two miles west of Bully Creek Reservoir near Vale, Oregon. The proposed action will be implemented in accordance with and subject to the guiding land use plan - the Southeastern Oregon Resource Management Plan and Final EIS. If you wish to review and comment on the US Geothermal ROW, Neal Hot Springs Environmental Assessment DOI-BLM-OR-V040-2011-008, please do so in writing and address your comments to the Malheur Field Manager, Vale District BLM, 100 Oregon St., Vale, OR 97918. To be considered, your comments must be received in this office by May 23, 2011. A copy of the document is available at the front desk of the Vale Bureau of Land Management Office, at the above address.
Vale District Office
(541) 473-3144
n/a
Resource Area: Malheur
Program Areas: Lands/Realty
Download: 20110506_USGEO_EA.pdf
Document Publish Date
Comment:
05/06/2011
05/06/2011 - 05/23/2011
Environmental Assessment DOI-BLM-OR-V040-2011-008-EA Planning Completed
The Malheur Resource Area, Vale District BLM, has completed the Decision Record and Finding of No Significant Impact (FONSI) for the Environmental Assessment (DOI-BLM-OR-V040-2011-008-EA) identifying the alternative actions for the proposed construction of exploratory geothermal well pads and access roads approximately two miles west of Bully Creek Reservoir near Vale, Oregon. The proposed action will be implemented in accordance with and subject to the guiding land use plan - the Southeastern Oregon Resource Management Plan and Final EIS.
Vale District Office
(541) 473-3144
n/a
Resource Area: Malheur
Program Areas: Lands/Realty
Download: 20110602_FINAL_EA-USGEO.pdf
Document Publish Date
Comment:
06/02/2011
06/02/2011 - 07/06/2011
Finding of No Significant Impact DOI-BLM-OR-V040-2011-008-EA Planning Completed
The Malheur Resource Area, Vale District BLM, has completed the Decision Record and Finding of No Significant Impact (FONSI) for the Environmental Assessment (DOI-BLM-OR-V040-2011-008-EA) identifying the alternative actions for the proposed construction of exploratory geothermal well pads and access roads approximately two miles west of Bully Creek Reservoir near Vale, Oregon. The proposed action will be implemented in accordance with and subject to the guiding land use plan - the Southeastern Oregon Resource Management Plan and Final EIS.
Vale District Office
(541) 473-3144
n/a
Resource Area: Malheur
Program Areas: Lands/Realty
Download: USGeothermal_FONSI_20110602.pdf
Document Publish Date
06/02/2011
Decision Record DOI-BLM-OR-V040-2011-008-EA Planning Completed
The Malheur Resource Area, Vale District BLM, has completed the Decision Record and Finding of No Significant Impact (FONSI) for the Environmental Assessment (DOI-BLM-OR-V040-2011-008-EA) identifying the alternative actions for the proposed construction of exploratory geothermal well pads and access roads approximately two miles west of Bully Creek Reservoir near Vale, Oregon. The proposed action will be implemented in accordance with and subject to the guiding land use plan - the Southeastern Oregon Resource Management Plan and Final EIS.
Vale District Office
(541) 473-3144
n/a
Resource Area: Malheur
Program Areas: Lands/Realty
Download: USGeothermal_DecisionRecord_20110602.pdf
Document Publish Date
Protest:
06/02/2011
06/02/2011 - 07/06/2011

Historic Vale Planning Documents / Current Vale Planning Documents