Project: Ontario to Quartz Transmission Line Project | |
| Project Status: Project Under Implementation | |
| Office Location: Vale | |
| Resource Area: Baker City | |
| NEPA #: OR-030-07-002 Environmental Assessment | |
| Document Publish Date: 8/06/2007 | |
| Summary: Idaho Power Company (IPC) proposes to amend right-of-way (ROW) OR-01469 to authorize roadwork on an existing road and three new short service roads along existing 138-kV transmission lines from Huntington to Quartz. The Proposed Action will improve access to five structures and allow for future operation and maintenance activities on the new service roads. | |
| Public Review Start Date : N/A - Historic | |
| Public Review End Date : N/A - Historic | |
| Contact: Vale District Office | |
| Contact Phone: (541) 473-3144 | |
| Program Areas: Transportation/Travel/Access | |