U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Oregon / Washington

NEPA Project Details

Return to NEPA Documents

Project: Neal Hot Springs Proposed Right of Way OR-66537

Project Status: Planning Completed
Office Location: Vale
Resource Area: Malheur
NEPA #: DOI-BLM-OR-V040-2011-008-EA  Decision Record
Document Publish Date: 6/02/2011
Summary: The Malheur Resource Area, Vale District BLM, has completed the Decision Record and Finding of No Significant Impact (FONSI) for the Environmental Assessment (DOI-BLM-OR-V040-2011-008-EA) identifying the alternative actions for the proposed construction of exploratory geothermal well pads and access roads approximately two miles west of Bully Creek Reservoir near Vale, Oregon. The proposed action will be implemented in accordance with and subject to the guiding land use plan - the Southeastern Oregon Resource Management Plan and Final EIS.
Public Protest/Appeal Start Date : 6/02/2011
Public Protest/Appeal End Date : 7/06/2011
Contact: Vale District Office
Contact Phone: (541) 473-3144
Program Areas: Lands/Realty
NEPA #: DOI-BLM-OR-V040-2011-008-EA  Finding of No Significant Impact
Document Publish Date: 6/02/2011
Summary: The Malheur Resource Area, Vale District BLM, has completed the Decision Record and Finding of No Significant Impact (FONSI) for the Environmental Assessment (DOI-BLM-OR-V040-2011-008-EA) identifying the alternative actions for the proposed construction of exploratory geothermal well pads and access roads approximately two miles west of Bully Creek Reservoir near Vale, Oregon. The proposed action will be implemented in accordance with and subject to the guiding land use plan - the Southeastern Oregon Resource Management Plan and Final EIS.
Contact: Vale District Office
Contact Phone: (541) 473-3144
Program Areas: Lands/Realty
NEPA #: DOI-BLM-OR-V040-2011-008-EA  Environmental Assessment
Document Publish Date: 6/02/2011
Summary: The Malheur Resource Area, Vale District BLM, has completed the Decision Record and Finding of No Significant Impact (FONSI) for the Environmental Assessment (DOI-BLM-OR-V040-2011-008-EA) identifying the alternative actions for the proposed construction of exploratory geothermal well pads and access roads approximately two miles west of Bully Creek Reservoir near Vale, Oregon. The proposed action will be implemented in accordance with and subject to the guiding land use plan - the Southeastern Oregon Resource Management Plan and Final EIS.
Public Review Start Date : 6/02/2011
Public Review End Date : 7/06/2011
Contact: Vale District Office
Contact Phone: (541) 473-3144
Program Areas: Lands/Realty
NEPA #: DOI-BLM-OR-V040-2011-008-EA  Environmental Assessment
Document Publish Date: 5/06/2011
Summary: Vale District BLM has completed for public review, an Environmental Assessment (DOI-BLM-OR-V040-2011-008-EA) and unsigned Finding of No Significant Impact (FONSI) identifying the alternative actions for the proposed construction of exploratory geothermal well pads and access roads approximately two miles west of Bully Creek Reservoir near Vale, Oregon. The proposed action will be implemented in accordance with and subject to the guiding land use plan - the Southeastern Oregon Resource Management Plan and Final EIS. If you wish to review and comment on the US Geothermal ROW, Neal Hot Springs Environmental Assessment DOI-BLM-OR-V040-2011-008, please do so in writing and address your comments to the Malheur Field Manager, Vale District BLM, 100 Oregon St., Vale, OR 97918. To be considered, your comments must be received in this office by May 23, 2011. A copy of the document is available at the front desk of the Vale Bureau of Land Management Office, at the above address.
Public Review Start Date : 5/06/2011
Public Review End Date : 5/23/2011
Contact: Vale District Office
Contact Phone: (541) 473-3144
Program Areas: Lands/Realty