Right of way grant renewal for Pend Oreille County PUD No. 1

Spokane

Documents in Project

Decision Record OR-135-2010-0011-CX Project Under Implementation
The Pend Oreille County PUD has been approved to renew the right-of way for the existing 7.2kV Cook's Mountain powerline. The line provides power to a communication site on private land. The original right-of-way grant was issued in 1986 but the powerline was first constructed in 1956. The right-of-way is approximately 1200 feet long and 40 feet wide. No new rights will be issued or new ground disturbance approved as a result of this administrative action. The term of the grant will be 30 years.
Spokane District Office
(509) 536-1200
BLM_OR_SP_Mail@blm.gov
Resource Area: Border
Program Areas: Lands/Realty
Download: CX_WAOR-38511.pdf
Document Publish Date
06/25/2010