NEPA Project Details
Project: Entiat Valley 115kV Transmission Program | |
| Project Status: Planning Completed | |
| Office Location: Spokane | |
| Resource Area: Wenatchee | |
| NEPA #: OR-134-08-EA-019 FONSI/Decision Record | |
| Document Publish Date: 9/10/2008 | |
| Summary: Decision Notice and Decision Record Finding of No Significant Impact This Finding of No Significant Impact (FONSI) and combined Decision Notice and Decision Record is for the portions of the proposed action described in the Entiat Valley 115 kV Transmission Program Environmental Assessment (EA). | |
| Public Protest/Appeal Start Date : 9/10/2008 | |
| Public Protest/Appeal End Date : 10/10/2008 | |
| Contact: Spokane District Office | |
| Contact Email: BLM_OR_SP_Mail@blm.gov | |
| Contact Phone: (509) 536-1200 | |
| Program Areas: Lands/Realty | |
| NEPA #: OR-134-08-EA-019 Environmental Assessment | |
| Document Publish Date: 6/27/2008 | |
| Summary: The Public Utility District No. 1 of Chelan County, Washington (District) has applied to the U.S. Department of Agriculture (USDA) Forest Service and U.S. Department of the Interior (USDI) Bureau of Land Management (BLM), respectively, for a special use permit and a right-of-way (ROW) grant to build a new 115 kilovolt (kV) electric transmission line in the Entiat, Washington area that would cross lands managed by these agencies. | |
| Public Review Start Date : 6/19/2008 | |
| Public Review End Date : 7/18/2008 | |
| Contact: Spokane District Office | |
| Contact Email: BLM_OR_SP_Mail@blm.gov | |
| Contact Phone: (509) 536-1200 | |
| Program Areas: Lands/Realty | |
Website Updates