Finding of No Significant Impact DOI-BLM-OR-S050-2010-0004-EA Planning Completed
The Bureau of Land Management, Marys Peak Resource Area, has prepared an environmental assessment on a proposal to implement three projects within the Rickreall Creek 5th field watershed: density management on approximately 1,340 acres of mid and late seral forest stands, legacy tree release, and large woody debris enhancement. The proposed projects are located in Polk County, Oregon. Contact: Stefanie Larew (503) 375-5601
Stefanie Larew
503-375-5601
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: Rickreall_FONSI_final.pdf
Document Publish Date
05/01/2012
Decision Record DOI-BLM-OR-S050-2010-0004-EA Planning Completed
The Bureau of Land Management, Marys Peak Resource Area, has made a decision to implement Project 3 of the Rickreall Creek Watershed Enhancement EA -- Large Woody Debris Enhancement. The project involves placing trees on up to six miles of three stream segments to enhance structural habitat diversity for aquatic and riparian dependent species. Contact: Scott Snedaker (503) 315-5928
Stefanie Larew
503-375-5601
n/a
Resource Area: Marys Peak
Program Areas: Riparian/Aquatic/Fisheries
Download: Rickreall_Creek_LWD_DR_final.pdf
Document Publish Date
Protest:
05/02/2012
05/02/2012 - 05/17/2012
Decision Record DOI-BLM-OR-S050-2010-0004-EA Planning Completed
The BLM has made a decision to implement the Robb Mill Loader Timber Sale, the first sale of six analyzed in the Rickreall Creek Watershed Enhancement EA. The project entails density management on approximately 183 acres of a 53 year old stand in the Adaptive Management Area and Riparian Reserves. Approximately 0.36 miles of temporary road will be constructed.
Stefanie Larew
503-375-5601
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: RobbMillDR.pdf
Document Publish Date
Protest:
04/24/2013
04/24/2013 - 05/08/2013
Environmental Assessment,Finding of No Significant Impact DOI-BLM-OR-S050-2010-0004 Planning Completed
The Marys Peak Resource Area has completed an environmental assessment on a proposal to perform three projects: mid and late-seral enhancement, legacy tree release, and large woody debris enhancement within the Rickreall Creek fifth field watershed in Polk County, Oregon.
Stefanie Larew
503-375-5601
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: RickreallEA13.pdf
Document Publish Date
03/07/2012
Decision Record DOI-BLM-OR-S050-2010-0004 Planning Completed
The BLM has made a decision to implement the C-9 Timber Sale. This project was described and analyzed in the 2012 Rickreall Creek Watershed Enhancement Environmental Assessment. It consists of 125 acres of density management on BLM-managed lands in the Adaptive Management Area and Riparian Reserves land use allocations in Polk County, Oregon.
Stefanie Larew
503-375-5601
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: C-9DR.pdf
Document Publish Date
Protest:
04/23/2014
04/23/2014 - 05/07/2014
Decision Record DOI-BLM-OR-S050-2010-0004 Planning Completed
The BLM has made a decision to implement the Rick-Line Timber Sale. This project was described and analyzed in the 2012 Rickreall Creek Watershed Enhancement Environmental Assessment. It consists of density management on 315 acres of BLM-managed lands in Polk County, Oregon.
Stefanie Larew
503-375-5601
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: Rick-LineDR.pdf
Document Publish Date
Protest:
04/23/2014
04/23/2014 - 05/07/2014
Determination of NEPA Adequacy DOI-BLM-OR-S050-2010-0004 Planning Completed
The BLM analyzed the Waymire Timber Sale in the Rickreall Creek Watershed Enhancement Environmental Assessment in 2012. Due to considerations with red tree voles and Northern Spotted Owl critical habitat, the BLM will not be pursuing the Waymire Timber Sale further at this time.
Rich Hatfield
(503) 375-5682
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: WaymireTS.pdf
Document Publish Date
04/23/2014
Decision Record DOI-BLM-OR-S050-2010-0004-EA Planning Completed
The BLM has made a decision to implement the Gilmore Timber Sale. This project was described and analyzed in the 2012 Rickreall Creek Watershed Enhancement EA. It consists of density management on approximately 179 acres of BLM-managed lands in Polk County, Oregon. Other actions include road construction, renovation, and post-harvest fuel reduction treatments.
Stefanie Larew
503-375-5601
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: GilmoreDR.pdf
Document Publish Date
Protest:
08/20/2014
08/20/2014 - 09/04/2014