U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Oregon / Washington

NEPA Project Details

RSS Icon

Lower Mill Creek Enhancement

Salem

Documents in Project

Decision Record,Categorical Exclusion DOI-BLM-OR-S050-2010-0003-CX Planning Completed
The proposed action on Project 1 - Mill Creek Stewardship is density management on one forest stand approximately 36-years-old and 22 acres in area. The proposed action on Project 2 - Panther Creek Timber Sale is density management on two forest stands approximately 39-54 years-old and 39 acres in area. No road construction will be necessary on either project.
Stephanie Larew
(541) 375-5601
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: lomilcr_en_cx.pdf
Document Publish Date
Comment:
06/01/2010
06/02/2010 - 06/17/2010
Decision Record DOI-BLM-OR-S050-2010-0003-CX Planning Completed
The Bureau of Land Management, Marys Peak Resource Area, has made a decision to implement Project 2 of the Lower Mill Creek Enhancement CX. The project entails density management on approximately on two forest stands approximately 41-56 years old and 39 acres in area. No road construction will occur. The project is located in T. 7 S., R. 6 W., Section 9, within the Mill Creek 5th field watershed in Polk County, Oregon. Contact: Andy Frazier (503) 315-5979
Stefanie Larew
503-375-5601
n/a
Resource Area: Marys Peak
Program Areas: Timber/Silviculture
Download: PantherCk_DR_final.pdf
Document Publish Date
Protest:
05/30/2012
05/31/2012 - 06/14/2012

Historic Salem Planning Documents / Current Salem Planning Documents