Project: Rickard Creek Decision Rationale

Project Status: Planning Completed
Office Location: none
Resource Area: Marys Peak
NEPA #: OR080-07-13  Decision Rationale
Document Publish Date: 5/27/2009
Summary: The proposed action is to perform regeneration harvest on approximately 87 acres, commercial thinning on approximately six acres of General Forest Management Area (GFMA), and density management on approximately 21 acres of Riparian Reserves (RR) land use allocations (LUAs). Road construction totaling approximately 2,990 feet will occur. Following harvest all of the new construction will be decommissioned.
Public Protest/Appeal Start Date : 5/27/2009
Public Protest/Appeal End Date : 6/11/2009
Contact: Salem District Office
Contact Phone: (503) 315-5949
Program Areas: Timber/Silviculture