Project: Bottleneck LSR Enhancement

Project Status: Planning in Progress
Office Location: none
Resource Area: Marys Peak
NEPA #: OR-080-07-16  Environmental Assessment / FONSI
Document Publish Date: 3/04/2009
Summary: Project 1 would thin approximately 161 acres of dense, mid-seral (68 years old) conifer forest, release existing wolf trees (large trees with full live crowns), and create snags and coarse woody debris (CWD). Project 2 would enhance a 24 acre late-seral (103 years old) stand, and a 4 acre deciduous swamp, both occurring adjacent to the mid-seral forest of Project 1.
Public Review Start Date : 3/04/2009
Public Review End Date : 4/02/2009
Contact: Salem District Office
Contact Phone: (503) 315-5949
Program Areas: Range/Wild Horses