Project: Botkin Road and Klickitat Tie Road Fish Log Salvage

Project Status: Planning Completed
Office Location: none
Resource Area: Marys Peak
NEPA #: DOI-BLM-OR-S050-2009-0005-CX  Categorical Exclusion
Document Publish Date: 2/12/2009
Summary: Document will allow removal of approximately 50 pieces of fallen timber across or adjacent to the existing road network for the purposes of aquatic habitat restoration near Philomath, Oregon.
Public Review Start Date : 2/17/2009
Public Review End Date : 3/03/2009
Contact: Salem District Office
Contact Phone: (503) 315-5949
Program Areas: Other