Project: PGE Powerline Rights-of-Way Authorizations

Project Status: Planning in Progress
Office Location: none
Resource Area: Tillamook
NEPA #: DOI-BLM-OR-S060-2010-014-CX  Categorical Exclusion / Decision Record
Document Publish Date: 5/17/2010
Summary: BLM proposes to authorize three existing powerlines that were recently discovered. The powerlines belong to Portland General Electric, and are located in T2N R2W sec 15, T2N R3W sec 3 and T3N R3W sec 33 in Washington and Multnomah Counties. There will be no additional ground disturbance above that which has already occurred.
Public Review Start Date : 5/17/2010
Public Review End Date : 6/01/2010
Contact: Bob McDonald
Contact Email: robert_mcdonald@blm.gov
Contact Phone: 503-815-1110
Program Areas: Lands/Realty