Environmental Assessment EA # OR-104-07-09 Planning Completed
On April 26, 2007, Barnes & Associates, Inc., in behalf of a private land owner, submitted a request to the Bureau of Land Management (BLM) for a road-use agreement (as described in Chapter 2) to provide access for the removal of timber from lands in private, non-industrial ownership that were not covered under an existing agreement. The request included provisions for a three-year unilateral road-use permit and construction of approximately 40 feet of new road in Section 31 of T. 24 S., R. 03 W. Willamette Meridian. On September 12, 2007, ownership transferred from the private, non-industrial landowner to Roseburg Resources Company. Roseburg Resources Company requested the BLM continue to process the unilateral permit. This environmental assessment (EA) analyzes the environmental consequences of both the proposed action alternative and the No Action alternative, to explain the environmental effects of each in the decision-making process.
Roseburg District Office
(541) 440-4930
n/a
Resource Area: Swiftwater
Program Areas: Other
Download: roneaccessea.pdf
Document Publish Date
Comment:
03/17/2008
03/11/2008 - 03/25/2008
Decision Record EA# OR-104-07-09 Planning Completed
The Rone Access will be a 40 foot road, constructed in Section 31 of T. 24 S., R. 03 W. Willamette Meridian, taking off of the 24-3-30.0 road. Construction of the temporary road will occur on Bureau of Land Management administered lands and will be permitted for the period of three years. This project is on a ridge top within the General Forest Management Area Land Use Allocation. The Project Design Features that will be implemented as part of the Action Alternative are described on pages 4-6 of the Rone Access EA, as modified by this Decision Document. These project design features will be developed into contract stipulations and will be implemented as part of the construction contract. This decision is subject to administrative remedy under 43 CFR 5003.2 and 5003.3.
Roseburg District Office
(541) 440-4930
n/a
Resource Area: Swiftwater
Program Areas: Other
Download: RoneAccessDR.pdf
Document Publish Date
Protest:
05/14/2008
05/13/2008 - 05/28/2008
Finding of No Significant Impact EA# OR-104-07-09 Planning Completed
The Rone Access project will construct a 40 foot road in Section 31 of T. 24 S., R. 03 W. Willamette Meridian, beginning at the 24-3-30.0 road. This project is within the General Forest Management Area Land Use Allocation and will cross BLM administered land to access Roseburg Resources Company lands.
Roseburg District Office
(541) 440-4930
n/a
Resource Area: Swiftwater
Program Areas: Other
Download: RoneAccessFONSI.pdf
Document Publish Date
05/14/2008

Historic Roseburg Planning Documents / Current Roseburg Planning Documents