U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Oregon / Washington

NEPA Project Details

RSS Icon

Alternative Access to Unit 5 of Treetop Flyer Commercial Thinning

Roseburg

Documents in Project

Finding of No Significant Impact DOI-BLM-OR-R050-2009-0008-EA Planning in Progress
The road construction proposed in Alternative Two of the Alternative Access to Unit 5 of Treetop Flyer Commercial Thinning EA is intended to provide suitable access for thinning of an entire mid-seral forest stand. The effects of the thinning were analyzed in the South Umpqua River Watershed Harvest Plan EA (OR105-08-02), which was planned and designed to conform with the management objectives and direction of the 1995 Roseburg District Record of Decision and Resource Management Plan (1995 ROD/RMP).
Roseburg District Office
(541) 440-4930
n/a
Resource Area: South River
Program Areas: Timber/Silviculture
Download: AltAcTTFlyrFNSI.pdf
Document Publish Date
12/15/2009
Environmental Assessment DOI-BLM-OR-R050-2009-0008-EA Planning in Progress
The proposed action is construction of a permanent all-weather road (No. 30-3-15.3) from the junction of Roads Nos. 30-3-15.2, 30-3-15.1 and 30-3-22.0 to the ridgeline above. Upon reaching the ridgeline, the road would follow the ridge through a ten-year-old plantation, before passing through a thin strip of young timber and ending at a landing area in a clearing.
Roseburg District Office
(541) 440-4930
n/a
Resource Area: South River
Program Areas: Timber/Silviculture
Download: AltAcTTFlyerCT.pdf
Document Publish Date
Comment:
12/15/2009
12/15/2009 - 01/14/2010

Historic Roseburg Planning Documents / Current Roseburg Planning Documents