Project: Millpond Maintenance Facility

Project Status: Planning in Progress
Office Location: Roseburg
Resource Area: Swiftwater
NEPA #: OR-104-07-01  Decision Record
Document Publish Date: 2/19/2008
Summary: The Millpond Maintenance Building will be built at Site #2 which is currently the overflow parking lot that services the Millpond Recreation Site and a small stand (0.2 acres) of young conifers 7-15 inches diameter breast height. On-the-ground implementation of Action Alternative 2 is contingent upon funding and available staffing. Construction of the facility will occur within the existing boundary of the Millpond Recreation Site which is located on the east side of road 26-3-1.0 in Section 21; T25S, R02W; Willamette Meridian. This project is within the Riparian Reserve Land Use Allocation and within the North Umpqua Special Recreation Management Area. The Project Design Features that will be implemented as part of the Action Alternative are described on pages 10-13 of the Millpond Maintenance Facility EA, as modified by this Decision Document. These project design features will be developed into contract stipulations and will be implemented as part of the construction contract. This decision is subject to administrative remedy under 43 CFR 5003.2 and 5003.3.
Public Protest/Appeal Start Date : 2/19/2008
Public Protest/Appeal End Date : 3/04/2008
Contact: Roseburg District Office
Contact Phone: (541) 440-4930
Program Areas: Recreation
NEPA #: OR-104-07-01  Finding of No Significant Impact
Document Publish Date: 2/19/2008
Summary: The Swiftwater Field Office, Roseburg District, Bureau of Land Management has a need to replace the existing Rock Creek Maintenance Facility currently located on the east side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21 due to safety and security concerns. The facility will be constructed at site #2 which is on the east side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21, W.M.. The project area lies within the Riparian Reserve of Rock Creek and within the North Umpqua Special Recreation Management Area. It also lies within the existing boundary of the Millpond Recreation Site and approximately 0.25 mile south of the existing Rock Creek Maintenance Facility.
Contact: Roseburg District Office
Contact Phone: (541) 440-4930
Program Areas: Recreation
NEPA #: OR-104-07-01  Environmental Assessment
Document Publish Date: 6/26/2007
Summary: This Environmental Assessment analyzes the environmental impacts associated with the Swiftwater Field Office's proposal for the construction of a new maintenance facility. The Swiftwater Field Office, Roseburg District, Bureau of Land Management has a need to replace the existing Rock Creek Maintenance Facility currently located on the east side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21 due to safety and security concerns. There are two proposed locations for the new facility. One location (Site #1) is on the west side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21, W.M. and the other location (Site #2) is on the east side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21, W.M..
Public Review Start Date : N/A - Historic
Public Review End Date : N/A - Historic
Contact: Roseburg District Office
Contact Phone: (541) 440-4930
Program Areas: Recreation