NEPA Project Details
Project: Millpond Maintenance Facility | |
| Project Status: Planning in Progress | |
| Office Location: Roseburg | |
| Resource Area: Swiftwater | |
| NEPA #: OR-104-07-01 Decision Record | |
| Document Publish Date: 2/19/2008 | |
| Summary: The Millpond Maintenance Building will be built at Site #2 which is currently the overflow parking lot that services the Millpond Recreation Site and a small stand (0.2 acres) of young conifers 7-15 inches diameter breast height. On-the-ground implementation of Action Alternative 2 is contingent upon funding and available staffing. Construction of the facility will occur within the existing boundary of the Millpond Recreation Site which is located on the east side of road 26-3-1.0 in Section 21; T25S, R02W; Willamette Meridian. This project is within the Riparian Reserve Land Use Allocation and within the North Umpqua Special Recreation Management Area. The Project Design Features that will be implemented as part of the Action Alternative are described on pages 10-13 of the Millpond Maintenance Facility EA, as modified by this Decision Document. These project design features will be developed into contract stipulations and will be implemented as part of the construction contract. This decision is subject to administrative remedy under 43 CFR § 5003.2 and 5003.3. | |
| Public Protest/Appeal Start Date : 2/19/2008 | |
| Public Protest/Appeal End Date : 3/04/2008 | |
| Contact: Roseburg District Office | |
| Contact Phone: (541) 440-4930 | |
| Program Areas: Recreation | |
| NEPA #: OR-104-07-01 Finding of No Significant Impact | |
| Document Publish Date: 2/19/2008 | |
| Summary: The Swiftwater Field Office, Roseburg District, Bureau of Land Management has a need to replace the existing Rock Creek Maintenance Facility currently located on the east side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21 due to safety and security concerns. The facility will be constructed at site #2 which is on the east side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21, W.M.. The project area lies within the Riparian Reserve of Rock Creek and within the North Umpqua Special Recreation Management Area. It also lies within the existing boundary of the Millpond Recreation Site and approximately 0.25 mile south of the existing Rock Creek Maintenance Facility. | |
| Contact: Roseburg District Office | |
| Contact Phone: (541) 440-4930 | |
| Program Areas: Recreation | |
| NEPA #: OR-104-07-01 Environmental Assessment | |
| Document Publish Date: 6/26/2007 | |
| Summary: This Environmental Assessment analyzes the environmental impacts associated with the Swiftwater Field Office's proposal for the construction of a new maintenance facility. The Swiftwater Field Office, Roseburg District, Bureau of Land Management has a need to replace the existing Rock Creek Maintenance Facility currently located on the east side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21 due to safety and security concerns. There are two proposed locations for the new facility. One location (Site #1) is on the west side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21, W.M. and the other location (Site #2) is on the east side of BLM Road 26-3-1.0, T. 25 S., R. 02 W., Section 21, W.M.. | |
| Public Review Start Date : N/A - Historic | |
| Public Review End Date : N/A - Historic | |
| Contact: Roseburg District Office | |
| Contact Phone: (541) 440-4930 | |
| Program Areas: Recreation | |