. .

U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Oregon / Washington

NEPA Project Details

RSS Icon

Sessler Federal Land Policy and Management Act Water Right-of-Way Categorical Exclusion

Medford District

Documents in Project

Decision Record CE#OR118-08-015 Planning Completed
The proposed action is the issuance of right-of-way grant to Robert (Bob) Sessler (applicant)applicant), under the provisions at 43 CFR Part 2800, and Title V of P.L. 94-579; 90 Stat 2743. The requested period of use is for a term of 20 years. The proposed action includes the use and maintenance of an existing water facility consisting of a small in-stream rock "dam" (diversion point) lined with plastic sheeting and an above ground 1 inch ABS pipe water line. The dam and the water line are on BLM managed land. The water right-of-way would be 5 ft by approximately 350 feet (0.04 acres) across BLM land it enters the applicant's private land. The system has been in place for many years and is used for domestic and irrigation use.
Michelle Calvert
(541) 471-6505
n/a
Resource Area: Glendale
Program Areas: Lands/Realty
Download: SesslerROWCE.pdf
Document Publish Date
Protest:
08/06/2008
08/11/2008 - 09/11/2008

Historic Medford Planning Documents / Current Medford Planning Documents