Middle Applegate Watershed Pilot Joe Project

Medford

Documents in Project

Scoping Letter DOI-BLM-OR-M060-2011-0016-EA Planning Completed
The Medford District Bureau of Land Management (BLM), Ashland Resource Area, is proposing ecological restoration projects, one of which results in the removal of timber under the Pilot Joe Timber Sale. Additional projects may include noncommercial thinning in young stands, and biomass and timber removal under stewardship authorities. These are the initial projects under the Middle Applegate Pilot Project, and are located in the Middle Applegate Watershed in the vicinity between Cantrall-Buckley Park and Thompson Creek. While collaboration and public information events about the Pilot have been ongoing since October 2010, this Notice opens the formal scoping period under the National Environmental Policy Act (NEPA). The initial projects will be analyzed under the Pilot Joe Environmental Assessment.
Stephanie Kelleher
541-618-2205
skellehe@blm.gov
Resource Area: Ashland
Program Areas: Timber/Silviculture
Download: Pilot_Joe_Scoping_Letter_signed_4.8.2011.pdf
Document Publish Date
Comment:
04/08/2011
04/08/2011 - 05/06/2011
Scoping Letter DOI-BLM-OR-M060-2011-0016-EA Planning Completed
The Environmental Assessment (EA) for the Pilot Joe Demonstration Project will be available for public review starting at the end of this month, June, 2011. This letter is to inform you that if you would like a paper copy of the EA sent to you via hard copy mail, you will need to request it. This letter is also meant to identify the level of interest the public has for an additional public meeting during the EA comment period.
Stephanie Kelleher
541-618-2205
skellehe@blm.gov
Resource Area: Ashland
Program Areas: Timber/Silviculture
Download: PilotJoe_PreEA_ltr_signed_6.13.11.pdf
Document Publish Date
06/13/2011
Environmental Assessment DOI-BLM-OR-M060-2011-0016-EA Planning Completed
The Environmental Assessment (EA) for the Pilot Joe Demonstration Project is now available for public review.
Stephanie Kelleher
541-618-2205
skellehe@blm.gov
Resource Area: Ashland
Program Areas: Timber/Silviculture
Download: pilotjoeea.pdf
Document Publish Date
Comment:
06/24/2011
06/27/2011 - 07/27/2011
Finding of No Significant Impact DOI-BLM-OR-M060-2011-0016-EA Planning Completed
The Medford District Bureau of Land Management, Ashland Resource Area (BLM) analyzed forest management activities, fuels reduction and maintenance, and transportation maintenance, including road decommissioning, on approximately 889 acres of BLM-administered lands in the Pilot Joe Demonstration Project Environmental Assessment (EA). I have determined that Alternative 2, the selected alternative, with the associated project design features from the Pilot Joe Demonstration Project, is not a major Federal action that would significantly affect the quality of the human environment, individually or cumulatively with other actions in the general area.
Stephanie Kelleher
541-618-2205
skellehe@blm.gov
Resource Area: Ashland
Program Areas: Timber/Silviculture
Download: PilotJoe_FONSI.pdf
Document Publish Date
08/17/2011
Decision Record DOI-BLM-OR-M060-2011-0016-EA Planning Completed
This document describes my decision, and reasons for my decision, regarding the selection of a course of action to be implemented for the Pilot Joe Demonstration Project.
Stephanie Kelleher
541-618-2205
skellehe@blm.gov
Resource Area: Ashland
Program Areas: Timber/Silviculture
Download: PilotJoe_DR.pdf
Document Publish Date
Protest:
08/17/2011
08/18/2011 - 09/02/2011