U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Oregon / Washington

NEPA Project Details

RSS Icon

Clary and Meehan ROW

Medford

Documents in Project

Environmental Assessment OR117-08-04 Planning Completed
The Clary and Meehan EA is available for public review and comment. This EA analyzed a ROW request across BLM land in T37S, R5W, Section 20 to access their property.
Medford District Office
(541) 618-2200
n/a
Resource Area: Grants Pass
Program Areas: Lands/Realty, Transportation/Travel/Access
Download: claryea.pdf
Document Publish Date
Comment:
03/01/2010
03/03/2010 - 04/02/2010
Finding of No Significant Impact OR117-08-07 Planning Completed
In March 2010, an environmental assessment (EA) for the Clary Meehan Right-of-Way (ROW) Project was completed and distributed for review and comment. A decision has been made to authorize the ROW and Road Construction to access private lands.
Medford District Office
(541) 618-2200
n/a
Resource Area: Grants Pass
Program Areas: Transportation/Travel/Access
Download: claryfonsi.pdf
Document Publish Date
11/24/2010
Decision Record OR117-08-07 Planning Completed
This is an authorization to construct approximately 140 feet of road and a ROW of perpetual access for private lands.
Medford District Office
(541) 618-2200
n/a
Resource Area: Grants Pass
Program Areas: Transportation/Travel/Access
Download: claydr.pdf
Document Publish Date
Protest:
11/24/2010
11/24/2010 - 12/09/2010

Historic Medford Planning Documents / Current Medford Planning Documents