Project: Mule Creek Bridge Replacement

Project Status: Planning Completed
Office Location: Medford
Resource Area: Glendale
NEPA #: DOI-BLM-OR-M080-2010-0009-CX  Categorical Exclusion / Decision Record
Document Publish Date: 7/28/2010
Summary: The Glendale Resource Area proposes to remove the existing 50 year old Mule Creek wooden bridge and replace it with a safe, long term bridge structure. The existing concrete bridge abutments will be used to support the new bridge. All the existing wooden railings, deck planking, and laminated support beams would be removed. A crane would be used to remove the heavy pieces. No machinery or equipment would be allowed to work in the stream.
Public Review Start Date : 7/29/2010
Public Review End Date : 8/13/2010
Contact: Martin Lew
Contact Phone: (541) 471-6504
Program Areas: Transportation/Travel/Access