NEPA Project Details
Project: Mule Creek Bridge Replacement | |
| Project Status: Planning Completed | |
| Office Location: Medford | |
| Resource Area: Glendale | |
| NEPA #: DOI-BLM-OR-M080-2010-0009-CX Categorical Exclusion / Decision Record | |
| Document Publish Date: 7/28/2010 | |
| Summary: The Glendale Resource Area proposes to remove the existing 50 year old Mule Creek wooden bridge and replace it with a safe, long term bridge structure. The existing concrete bridge abutments will be used to support the new bridge. All the existing wooden railings, deck planking, and laminated support beams would be removed. A crane would be used to remove the heavy pieces. No machinery or equipment would be allowed to work in the stream. | |
| Public Review Start Date : 7/29/2010 | |
| Public Review End Date : 8/13/2010 | |
| Contact: Martin Lew | |
| Contact Phone: (541) 471-6504 | |
| Program Areas: Transportation/Travel/Access | |