U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Oregon / Washington

NEPA Project Details

Return to NEPA Documents

Project: Tucker Hill Quarry Plan of Operations Amendment

Project Status: Planning Completed
Office Location: Lakeview
Resource Area: Lakeview RA
NEPA #: DOI-BLM-OR-L050-2012-0009-EA  FONSI/Decision Record
Document Publish Date: 2/04/2013
Summary: The BLM has completed an analysis of a proposal to amend a Plan of Operations (PoO) to expand the existing perlite quarry at Tucker Hill. The quarry is located about 39 miles northwest of Lakeview in central Lake County, Oregon. The BLM originally approved a PoO based upon an analysis of about 23 acres of surface disturbance in an EIS completed in 1996. The BLM is now issuing a decision to adopt the PoO amendment and allow expansion of the current operation by 47 acres based upon a new analysis contained in an EA.
Public Protest/Appeal Start Date : 2/01/2013
Public Protest/Appeal End Date : 3/04/2013
Contact: Lakeview Resource Area
Contact Phone: (541) 947-2177
Program Areas: Minerals
NEPA #: DOI-BLM-OR-L050-2012-0009-EA  Environmental Assessment / FONSI
Document Publish Date: 12/06/2012
Summary: The Bureau of Land Management has analyzed a proposal and one alternative to authorize the expansion of the existing perlite quarry at Tucker Hill. The BLM initially approved a mining Plan of Operations (PoO) for the quarry, based upon an analysis of about 23 acres of surface disturbance described in an Environmental Impact Statement completed in 1996. The current operation consists of mining perlite from the quarry, crushing the ore on-site, and then transporting the ore to a plant in Lakeview for further processing and shipping. The EA contains an analysis of the effects of approving an amendment to the PoO which would authorize expanding the existing perlite quarry to include an additional estimated 47 acres of surface disturbance over a 15-year period of time. The quarry is located about 39 miles northwest of Lakeview in central Lake County, Oregon.
Public Review Start Date : 12/12/2012
Public Review End Date : 1/10/2013
Contact: Lakeview Resource Area
Contact Phone: (541) 947-2177
Program Areas: Minerals
NEPA #: OR-010-2008-01  Decision Record
Document Publish Date: 2/21/2008
Summary: Decision Record for Tucker Hill Mining Plan of Operations Amendment
Public Protest/Appeal Start Date : 2/22/2008
Public Protest/Appeal End Date : 3/24/2008
Contact: Lakeview Resource Area
Contact Phone: (541) 947-2177
Program Areas: Minerals
NEPA #: EA#OR-010-2008-01  Environmental Assessment
Document Publish Date: 1/15/2008
Summary: The EA analyzes a proposed amendment to the existing plan of operations which would authorize the use of a new site for the disposal of waste rock from the quarry.
Public Review Start Date : 1/23/2008
Public Review End Date : 2/21/2008
Contact: Lakeview Resource Area
Contact Phone: (541) 947-2177
Program Areas: Minerals
NEPA #: CX #OR-010-2006-10  Categorical Exclusion
Document Publish Date: 1/25/2006
Summary: This document represents BLM's 2006 approval of, and categorical exclusion documentation for, a proposed amendment to the Plan of Operations for the Tucker Hill Perlite Mine. Specifically, the amendment addressed minor modifications and maintenance of the haul road accessing the mine.
Public Review Start Date : N/A - Historic
Public Review End Date : N/A - Historic
Contact: Lakeview Resource Area
Contact Phone: (541) 947-2177
Program Areas: Minerals
NEPA #: none  Documentation of NEPA Adequacy
Document Publish Date: 10/19/2001
Summary: The document represents BLM's approval of, and determination of NEPA adequacy for, a 2001 amendment to the Plan of Operations for the Tucker Hill Perlite Mine. The amendment covered proposed changes to the quarry operations and blasting schedules.
Public Protest/Appeal Start Date : N/A - Historic
Public Protest/Appeal End Date : N/A - Historic
Contact: Lakeview Resource Area
Contact Phone: (541) 947-2177
Program Areas: Minerals
NEPA #: none  Documentation of NEPA Adequacy
Document Publish Date: 1/07/1999
Summary: This document represents the approval and plan conformance review for an amendment to the Plan of Operations for the Tucker Hill Perlite Mine. Specifically, this amendment authorized the use of a portable crusher at the mine site beginning in 1999.
Public Protest/Appeal Start Date : N/A - Historic
Public Protest/Appeal End Date : N/A - Historic
Contact: Lakeview Resource Area
Contact Phone: (541) 947-2177
Program Areas: Minerals