NEPA Project Details
Project: Summer Lake Dike Maintenance | |
| Project Status: Planning Completed | |
| Office Location: Lakeview | |
| Resource Area: Lakeview RA | |
| NEPA #: DOI-BLM-OR-L050-2011-00009-EA FONSI/Decision Record | |
| Document Publish Date: 12/07/2011 | |
| Summary: The document includes the final decision and Finding of No Significant Impact authorizing the Oregon Department of Fish and Wildlife to repair/maintain about 150 feet of an existing irrigation dike located on BLM-administered lands within the Diablo Mountain WSA. The dike system delivers irrigation water to the Summer Lake Wildlife Refuge managed by the Oregon Department of Fish and Wildlife. | |
| Public Protest/Appeal Start Date : 12/09/2011 | |
| Public Protest/Appeal End Date : 1/09/2012 | |
| Contact: Lakeview Resource Area | |
| Contact Phone: (541) 947-2177 | |
| Program Areas: Wildlife | |
| NEPA #: DOI-BLM-OR-L050-2011-0009-EA Environmental Assessment / FONSI | |
| Document Publish Date: 9/16/2011 | |
| Summary: The EA and FONSI address a proposal to authorize the Oregon Department of Fish and Wildlife to repair a 150-foot long section of an existing dike system that controls and diverts water to the southern half of the Summer Lake Wildlife Area. This dike section was damaged in 2010 by high water flows. Most of this dike falls within the Diablo Mountain Wilderness Study Area on lands administered by the BLM. | |
| Public Review Start Date : 9/21/2011 | |
| Public Review End Date : 10/20/2011 | |
| Contact: Lakeview Resource Area | |
| Contact Phone: (541) 947-2177 | |
| Program Areas: Wildlife | |
Website Updates