Project: Long Tom Landscape Plan

Project Status: Planning Completed
Office Location: none
Resource Area: Siuslaw
NEPA #: DOI-BLM-OR-E050-2009-0006-EA  FONSI/Decision Record
Document Publish Date: 7/25/2011
Summary: Decision Record and FONSI for Long Tom Landscape Plan
Public Protest/Appeal Start Date : 7/27/2011
Public Protest/Appeal End Date : 8/11/2011
Contact: Sharmila Premdas
Contact Phone: 541-683-6794
Program Areas: Timber/Silviculture
NEPA #: DOI-BLM-OR-E050-2009-0006-EA  Environmental Assessment
Document Publish Date: 7/25/2011
Summary: Final EA for Long Tom Landscape Plan
Public Review Start Date : N/A - Historic
Public Review End Date : N/A - Historic
Contact: Sharmila Premdas
Contact Phone: 541-683-6794
Program Areas: Timber/Silviculture
NEPA #: DOI-BLM-OR-E050-2009-0006-EA  Finding of No Significant Impact
Document Publish Date: 3/16/2011
Summary: Preliminary FONSI for Long Tom Landscape Plan
Contact: Sharmila Premdas
Contact Phone: 541-683-6794
Program Areas: Timber/Silviculture
NEPA #: DOI-BLM-OR-E050-2009-0006-EA  Environmental Assessment
Document Publish Date: 3/16/2011
Summary: Environmental Assessment for Long Tom Landscape Plan
Public Review Start Date : 3/16/2011
Public Review End Date : 4/15/2011
Contact: Sharmila Premdas
Contact Phone: 541-683-6794
Program Areas: Timber/Silviculture