Cote Grade Quarry

Burns

Documents in Project

Decision Record,Categorical Exclusion DOI-BLM-OR-B050-2011-0030-CX Planning in Progress
Perform Exploratory Drilling on both sides of the Cote Grade and within 400 feet of the cliff area. The purpose of the drilling is to determine if an appropriate quantity and quality of material are available for development of a Quarry to meet road design criteria.
Burns District Office
(541) 573-4400
n/a
Resource Area: Three Rivers
Program Areas: Minerals
Download: CoteGradeQuarry.pdf
Document Publish Date
Comment:
05/17/2011
05/17/2011 - 06/18/2011
Environmental Assessment,Finding of No Significant Impact DOI-BLM-OR-B050-2011-0013-EA Planning in Progress
The proposal is to drill, blast, crush, stockpile, and haul up to 250,000 cubic yards (cy) of material over a period of time that would include material needed for longer-term maintenance. The material would be used to widen the road surface of Double O Road from up to 20 feet to 28 feet and overlaying up to 6 to 8 inches of material source on an existing 32-mile stretch of Double O Road. The project would also provide material for the Moon Reservoir Road as well as other roads. During the timing of the Double O Road project, the crest of the road at Cote Grade may be lowered and realigned to the east to improve road safety.
Burns District Office
541-573-4400
n/a
Resource Area: Three Rivers
Program Areas: Minerals, Lands/Realty
Download: CoteGradeQuarry_EA_Feb2013.pdf
Document Publish Date
Comment:
02/27/2013
02/27/2013 - 03/29/2013

Historic Burns Planning Documents / Current Burns Planning Documents