U.S. DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Oregon / Washington

NEPA Project Details

Return to NEPA Documents

Project: Alvord Desert Pipeline Well and Trough

Project Status: Planning Completed
Office Location: none
Resource Area: Andrews
NEPA #: DOI-BLM-OR-B060-2010-0030-CX  Categorical Exclusion
Document Publish Date: 5/07/2010
Summary: A 30' bottomless water trough to replace several small portable troughs located next to an existing reservoir would be constructed. In the past, water was pumped from the well into the reservoir. However, the reservoir's holding capacity was unreliable, so temporary troughs were utilized this past year. In addition a solar tower to power the water pump for the well would be installed. Water would be pumped from an existing well at the site into the trough. A small trench about 15 feet long would be dug in order to place a water pipe from the well to the trough.
Public Review Start Date : 5/10/2010
Public Review End Date : 5/25/2010
Contact: Burns District Office
Contact Phone: (541) 573-4400
Program Areas: Range/Wild Horses