<< back to the Ruby Pipeline Project homepage Ruby Pipeline ProjectRights-of-Way Notices to Proceed (NTP)NOTE: If you need help in using the data or information here, please contact Mark Mackiewicz at 435-636-3616 or by email at blmruby@blm.gov. The mile post marker maps that correspond to the NTPs are available at the Ruby Pipeline LLC Alignment Sheet website at www.rubypipeline.com/alignment_sheets.shtm. The mile post marker maps may also be accessed by going to the Ruby Pipeline LLC website and selecting "USGS Topographics Maps" in the left column. You will need the "Alignment Sheets Referenced" numbers to find the map that corresponds to the mile post marker number. The mile post markers are identified with triangular numbered flags on the maps. To view the rights-of-way NTP document, click the NTP number in the left column below. NTP Number | Date Signed (mm/dd/yr) | Released | 57 | 12/9/2011 | 1. BLM Salt Lake Field Office, UT (In Spread: 3)
Milepost (MP): R190.6 Build New Road from County Road 8560 N to Mainline Valve (MLV) 14 Quadrangle Sheet Referenced: 33
2. BLM Elko District, NV (In Spreads: 4 and 5)
MP: 311 Build New Road from E-26 to MLV 21 Quadrangle Sheet Referenced: 53
MP: 364.25 Build Above-Ground Cathodic Protection Site at MLV 24 Quadrangle Sheet Referenced: 63
MP: 365.7 Build New Road from E-51A to MLV 24 Quadrangle Sheet Referenced: 63
MP: 385.3R Build New Road from Midas Tuscarora Road to MLV 25 Quadrangle Sheet Referenced: 66
3. BLM Winnemucca District, NV (In Spread: 5)
MP: 402R Build New Road from H-3A to MLV 26 Quadrangle Sheet Referenced: 68
MP: 456.9 Build New Road from Old Denio Road to MLV 29 Quadrangle Sheet Referenced: 79
MP: 493.2 Build New Road from Leonard Creek Road to MLV 31 Quadrangle Sheet Referenced: 85
MP: 509.7 Build Above-Ground Cathodic Protection Site (revised location) at MLV 32 Quadrangle Sheet Referenced: 88
MP: 509.7 Build New Road from Pearl Camp Road to MLV 32 Quadrangle Sheet Referenced: 88
MP: 528.13 Build New Road from H-50A to MLV 33 Quadrangle Sheet Referenced: 91
4. BLM Surprise Field Office, CA (In Spread: 6)
MP: 547.84 Build Above-Ground Cathodic Protection Site to MLV 34 Quadrangle Sheet Referenced: 94
MP: 547.9 Build New Road from W-4A to MLV 34 Quadrangle Sheet Referenced: 94
MP: 564 Build New Road from County Road 34 to MLV 35 Quadrangle Sheet Referenced: 97
MP: 581.4 Build New Road from W-15 to MLV 36 Quadrangle Sheet Referenced: 97
5. BLM Lakeview Resource Area, OR (In Spread: 6)
MP: 595.8 Build New Road from Big Valley Road to MLV 37 Quadrangle Sheet Referenced: 102
6. Fremont-Winema National Forests, OR (In Spread: 7)
MP: 643.06 Build New Road from Forest Service Road 4017 (L-19) to MLV 40 Quadrangle Sheet Referenced: 110
7. BLM Klamath Falls Resource Area, OR (In Spread: 7)
MP: 659.24 Build Above-Ground Cathodic Protection Site to MLV 41 Quadrangle Sheet Referenced: 112A
MP: 659 Build New Road from K-3B to MLV 41 Quadrangle Sheet Referenced: 112A | 56 | 3/9/2011 | BLM Lakeview Resource Area, BLM Klamath Falls Resource Area, and Bureau of Reclamation, OR (In Spreads: 6 and 7) Mileposts (MP): MP 588.5 to 589.7 (BLM Lakeview) MP 597.4 to 601.2 (BLM Lakeview) MP 653.0 to 658.5 (BLM Klamath Falls Resource Area) • Access Roads K-3F and K-8. MP 664.4 • Access Road K-10E (BLM Klamath Falls Resource Area and Reclamation) Alignment Sheets Referenced: 300A-242; 300A-245 through 300A-247; 300A-268 through 300A-270
Quadrangle Sheets Referenced: 101-103; 111-112A | 55 | 4/15/2011 | BLM Surprise Field Office, CA (In Spread: 5)
Access Roads: MP 533.0 to 538.0: W-1 (east of W-2), H-50B
This NTP does not authorize the use of roads on BLM managed lands that may be authorized for use on the Sheldon Wildlife Refuge or that have not been previously authorized for use.
This NTP only applies to access routes and lands under the jurisdiction of the Surprise Field Office.
Alignment Sheets Referenced: 300A-219 to 300A-221
Quadrangle Sheets Referenced: 92, 93, 93A | 54 | 3/01/2011 | BLM Lakeview Resource Area and the Bureau of Reclamation, OR (In Spreads: 6 and 7)
Mileposts (MP): MP 594.90 to 596.05 (BLM) and MP 662.40 to 664.60 (Reclamation)
Alignment Sheets Referenced: 300A-244, 300A-245, and 300A-272
Quadrangle Sheets Referenced: 102, 113, and 113A | 53 | 2/24/2011 | BLM Klamath Falls Resource Area, OR (In Spread: 7)
Mileposts (MP): MP 658.5 to 662.4 And Project Modification No. 160: Centerline from 657.70 to 659.20 Project Modification No. 170: Centerline from 659.50 to 662.75
Alignment Sheets Referenced: 300A-270 through 300A-272
Quadrangle Sheets Referenced: 112A-113 | 52 | 4/14/2011 | BLM Surprise Field Office, CA (In Spread: 5)
Access Roads: MP 541.0 to 546.0 : W-1 (west of W-2), W-2, W-3, W-3B
This NTP does not authorize the use of roads on BLM managed lands that may be authorized for use on the Sheldon Wildlife Refuge or that have not been previously authorized for use.
This NTP only applies to access routes and lands under the jurisdiction of the Surprise Field Office.
Alignment Sheets Referenced: 300A-221 to 300A-223
Quadrangle Sheets Referenced: 92, 93, 93A, 94, 94A | 51 | 2/18/2011 | BLM Lakeview Resource Area (BLM-LRA), Fremont-Winema National Forests (F-W NFs), and BLM Klamath Falls Resource Area (BLM-KFRA), OR (In Spreads: 6 and 7) Mileposts (MP): MP 592.0 to 592.3 (BLM - LRA) MP 645.5 to 645.9 (F-W NF) MP 649.3 to 649.5 (F-W NF) MP 651.5 to 653.0 (BLM - KFRA) And Project Modification No. 160: Centerline from MP 645.5 to 645.9 Centerline from MP 649.3 to 649.5 Centerline from MP 651.0 to 656.2 (see KFRA Stipulation) Alignment Sheets Referenced: 300A-242 to 300A-245, 300A-265 to 300A-268
Quadrangle Sheets Referenced: 101-102, 110-111 | 50 | 2/07/2011 | BLM Lakeview Resource Area (In Spread: 6)
Mileposts (MP): MP 590.9 to 592.0 MP 592.3 to 592.7 MP 593.1 to 594.9 MP 596.4 to 597.4 And Project Modification: 160 Centerline from 589.9 to 593.1 Centerline from 594.0 to 595.5 Centerline from 596.4 to 600.3
Alignment Sheets Referenced: 300A-242 to 300A-245
Quadrangle Sheets Referenced: 101 and 102 | 49 | 1/31/2011 | BLM Klamath Falls Resource Area and Bureau of Reclamation (In Spread: 7)
Mileposts (MP): MP 664.60 to MP 664.80 – Reclamation Land MP 664.80 to MP 665.15 – BLM Land MP 665.15 to MP 665.20 – Private Easement of Reclamation Land And Access Road: MPs 664.6 to 665.20: K10G - Private Land, BLM Land, and Reclamation Land
Alignment Sheets Referenced: 300A-272 and 300A-273
Quadrangle Sheets Referenced: 113 | 48 | 1/13/2011 | Lakeview District Office and Fremont-Winema National Forests (In Spread: 6)
Mileposts (MPs): MPs 601.2-605.0 And Access Roads: MPs 601.2-605.0: L-3A, CT-1, CT-1A, CT-1B, CT-2, CT-2A, CT-3A And Project Modifications: No. 136: Don Robinson Staging Area and Existing Well Water Source No. 139: Reverse Lay Spread 6 Centerline No. 154: Deep Creek Staging Area No. 160: Rock Stacks Centerline
Alignment Sheets Referenced: 300A-247 and 300A-248
Quadrangle Sheets Referenced: 103 and 104 | 47 | 6/6/2011 (Reissue 2)
2/26/2011 (Reissue 1)
2/4/2011 (original) | Surprise Field Office and Sheldon Wildlife Refuge, NV (In Spreads 5 and 6)
Mileposts (MPs): MPs 531.4 to 549.9 And Access Roads: MP 531.4 to 549.9 : H-46A; W-2A, W-3A, W-4, W-4A
H46B is not under the jurisdiction of the Surprise Field Office.
This NTP does not authorize the use of roads on BLM managed lands that are authorized for use on the Sheldon Wildlife Refuge, e.g., H-52, H-50, or that have not been previously authorized for use. And Project Modification No. 124: H-10WS Access Road
Alignment Sheets Referenced: 300A-218 to 300A-225
Quadrangle Sheets Referenced: 91-94 | 46a | 6/6/2011 (Reissue 3)
3/8/2011 (Reissue 2)
2/26/2011 (Reissue 1)
2/2/2011 (Original) | Winnemucca District Office NV (In Spread: 5)
Mileposts (MPs): MPs 509. 9 to 518.0 And Access Roads: MP 509.9 to 518.0: H-43, H-45, H-45A, and H-48.
Alignment Sheets Referenced: 300A-209 and 300A-212
Quadrangle Sheets Referenced: 88 and 89 | 46 | 6/6/2011 (Reissue 3)
3/8/2011 (Reissue 2)
2/26/2011 (Reissue 1)
2/2/2011 (Original) | Winnemucca District Office and Sheldon Wildlife Refuge, NV (In Spread: 5)
Mileposts (MPs): MPs 518.0 to 531.4 (includes Project Modification Nos. 123 and 169) And Access Roads: MP 518.0 to 531.4: H-46A, H-47, H-49, H-50, H-50A, H-51 Access Roads: H-46, H-46B And Project Modification No. 123: H-9WS Access Road Project Modification No. 123: Kundrna Ranch Staging Area Project Modification No. 169: Summit Lake TCP Centerline Route
Alignment Sheets Referenced: 300A-213 and 300A-218
Quadrangle Sheets Referenced: 88 and 89 | 45 | 12/09/2010 | Fremont-Winema National Forests, OR (In Spread: 6)
Mileposts (MPs): 611.5 to 611.8 And Access Road: MPs 611.5 to 611.8: L12b
Alignment Sheets Referenced: 300A-251
Quadrangle Sheets Referenced: 105 | 44 | 12/02/2010 | Elko District Office, NV (In Spread: 4)
Access Road: Project Modification No. 03-003-WW: Well 5 Access Road
Alignment Sheets Referenced: NA, off Right-of-Way, See attached map in NTP
Quadrangle Sheets Referenced: NA, off Right-of Way, See attached map in NTP | 43 | 11/23/2010 | Winnemucca District Office, NV (In Spread: 5)
Mileposts (MPs): MPs 490.0 to 498.0 And Access Road: MP 490.0 to 498.0: H-37A
Alignment Sheets Referenced: 300A-201 and 300A-202
Quadrangle Sheets Referenced: 85 and 86 | 42 | 3/17/2011 (Reissue 1)
11/23/2010 (Original) | Elko District Office, NV (In Spread: 4)
Mileposts (MPs): 372.5 to 377.5 And Access Roads: MP 372.5 to 377.5: E-54A, E-54B
Alignment Sheets Referenced: 300A-153 to 300A-155
Quadrangle Sheets Referenced: 64 and 65 | 41 | 11/23/2010 | Winnemucca District Office, NV (In Spread: 5)
Mileposts (MPs): MPs 498.0 to 509.9 And Access Roads: MP 498.0 to 509.9: H-38, H-38A, H-39, H-41, H-42 And Project Modification No. 122: Access Road H-8WS Project Modification No. 124A: BLM Proposed Drill Well MP 509.8
Alignment Sheets Referenced: 300A-204 to 300A-209
Quadrangle Sheets Referenced: 86, 86A, 88 | 40 | 11/17/2010 | Elko District Office, NV (In Spread: 3)
Access Roads: MP 254.0 to 258.0 E-6 E-7
Alignment Sheets Referenced: 300A-105 and 300A-106
Quadrangle Sheets Referenced: 43, 43A, 44, and 45 | 39 | 11/16/2010 | Winnemucca District Office, NV (In Spread: 5)
MP 487.90 Project Modification No. 168: Leonard Creek Pipe Storage and Staging Yard
Alignment Sheets Referenced: 300A-200
Quadrangle Sheets Referenced: 84 | 38 | 12/21/2010 | BLM, Klamath Falls, Resource Area and US Bureau of Reclamation, Klamath Basin Area Office, OR (In Spread: 7)
Mile Posts (MPs): 665.2 to 666.3
Alignment Sheets Referenced: 300A-1273
Quadrangle Sheets Referenced: 113, 113A | 37 | 3/16/2011 (Reissue 5)
11/23/2010 (Original) | Elko District Office, NV (In Spread: 4)
Mile Posts (MPs): 355.5 to 372.5 And Access Roads: MP 355.5 to 372.5: E-49C, E-49D, E-49E, E-49F, E-50A, E-50B, E-50C, E-50D, E-50E, E-51, E-51A, E-51B, E-51C, E-52A, E-52B, E-52C, E-52D
Access Road E-52 – Ruby is requesting the portion of the road north of the ROW; the portion of the road south of the ROW will not be used. And Variance No. 109: 26-Ranch Proposed Drill Well MP 360.6 Water Source Variance No. 110: China Springs Staging Area MP 364.4 Variance No. 111: Barrick Proposed Drill Well MP 368.3 Water Source Variance No. 111: Barrick Proposed Drill Well MP 368.3 Staging Area
Alignment Sheets Referenced: 300A-146 to 300A-153
Quadrangle Sheets Referenced: 62-64 | 36 | 11/19/2010 | Salt Lake Field Office, UT (In Spread: 3)
Access Roads: MP s 216 to 227: B-50B: Pigeon Mountain Loop County Road B-50D: Rabbit Springs County Road B-59: Unnamed County Road B-60: South Winter Cabin County Road
Alignment Sheets Referenced: NA, See Attached Maps in NTP
Quadrangle Sheets Referenced: NA, See Attached Maps in NTP | 35 | 11/12/2010 | Kemmerer Field Office, WY (In Spread: 1A)
Mile Posts (MPs): 18.16 to 19.59 And Access Roads: MP 18.16 to 19.59: Remainder of LW-21 not previously approved, LW-23, LW-24
Alignment Sheets Referenced: 300A-8 and 300A-9
Quadrangle Sheets Referenced: 5 | 34 | 11/04/2010 | Winnemucca District Office, NV (In Spread: 5) Mile Posts (MPs): MP 479.0 to 490.0 And Access Roads: MP 479.0 to 487.0: H-34A, H-34B, H-36
Alignment Sheets Referenced: 300A-197 through 300 A-201
Quadrangle Sheets Referenced: 82 to 85 | 33 | 2/28/2011 (Reissued) 11/4/2010 (Original) | Elko District Office, NV (In Spread: 4) Mile Posts (MPs): MP 328.8 to 330.4; MP 351.0 to 355.5 and Access Roads: MP 327.5 to 328.8 and 330.4 to 339.0: Access Roads E-33, E-34, E-35 MP 351.0 to 355.5: E-48, E-48A, E-49A, E-49B
26-Ranch Proposed Drill Well MP 351.93 Water Source and Staging Area
Alignment Sheets Referenced: 300A-135; 300A-144 through 300A-146
Quadrangle Sheets Referenced: 56-58A; 61-62 | 32 | 2/26/2011 (Reissued)
11/12/2010 (Original) | Surprise Field Office, CA (In Spread: 6)
Mile Posts (MPs): 577.0 to 588.3 And Access Roads: MP 577.0 to 588.3: W-14B, W-15, W-15A
Project Modification 166: Barrel Springs Centerline
Alignment Sheets Referenced: 300A-237 through 300A-241
Quadrangle Sheets Referenced: 99 to 101 | 31 | 11/12/2010 | Lakeview Resource Area, OR (In Spread: 6)
Mile Posts (MPs): MP 588.3 to 588.5 (Twelve Mile Creek)
Alignment Sheets Referenced: 300A-241
Quadrangle Sheets Referenced: 101 | 30a | 11/04/2010 | Winnemucca District Office, NV (In Spread: 5)
Mile Posts (MPs): 450.50 to 451.25 and 452.35 to 458.50
Alignment Sheets Referenced: 300A-185 through 300A-188
Quadrangle Sheets Referenced: 78 and 79 | 30 | 10/28/2010 | Winnemucca District Office, NV (In Spread: 5)
Mile Posts (MPs): 450.5 to 479.0
MPs 450.50 to 451.25 and 452.35 to 458.50 ARE NOT APPROVED UNDER THIS NTP
MPs 465.0 to465.5: BLM REQUIRES THAT BOTH TRIBAL MONITORS AND FAR WESTERN ARCHAEOLOGICAL MONITORS BE PRESENT DURING ALL GROUND DISTURBING ACTIVITIES.
And Access Roads:
MP 450.5 to 479.0: H-29, H-30A (BLM REQUIRES THAT BOTH TRIBAL MONITORS AND FAR WESTERN ARCHAEOLOGICAL MONITORS BE PRESENT DURING ALL GROUND DISTURBING ACTIVITIES), H-31, H-32, H-35
And the Following Pipe Yards and Related Access Roads: Sod House Pipe Storage Yard Midas Road Pipe Storage Yard
Alignment Sheets Referenced: 300A-185 through 300A-197
Quadrangle Sheets Referenced: 78-82 | 29 | 3/16/2011 (Reissue 2)
10/26/2010 (Original) | Elko District Office, NV (In Spreads: 3 and 4)
Access Roads: (Related to MPs)
MP 230.0 to 239.0: Access Roads E-1, E-1A, E-2 (See Elko Stipulations) MP 239.0 to 267.0: Access Roads E-4 (See Elko Stipulations), E-5, E-8 (See Elko Stipulations), E-9A (See Elko Stipulations), E-9B (See Elko Stipulations) MP 276.0 to 289.0: Access Roads E-14, E-14A (See Elko Stipulations), E-14B MP 319.0 to 328.8: Access Roads E-29, E-31, E-36 (See Elko Stipulations) MP 330.4 to 339.0: Access Road E-39 MP 339.5 to 351.0: Access Roads E-42A, E-44, E-45A (See Elko Stipulations), E-45B (See Elko Stipulations)
(Unrelated to MPS)
225/226 Pipeyard Access Road (also labeled as E-40 [This road requires a Level 3 Variance prior to any improvements])
Alignment Sheets Referenced: 300A-95 through 111; 300A-116 to 119.1; 300A-132; 300A-133; 300A-135; 300A-140 through 143
Quadrangle Sheets Referenced: 40-45, 47-49, 55-57, 58, 58A, 59-60 | 28 | 10/11/2010 | Kemmerer Field Office, WY
The Williams Tie-In, a 36-inch diameter natural gas pipeline on federal lands described as follows: 6th Principle Meridian, Lincoln County, WY Township 21 North, Range 114 West, Section 27, Lot 2, and Section 28, NE¼NE¼.
The right-of-way area granted herein is 50 feet wide, 984 feet long, and contains 1.13 acres, more or less.
A temporary use area encompassing 1.4683 acres is included, as well as the use of temporary access roads LW-1C, LW-1D, and LW-1E, approximately 2,953 feet long and 30 feet wide, encompassing 2.03 acres, more or less.
Alignment Sheets Referenced: 300A-1
Quadrangle Sheets Referenced: 1 | 27a | 10/26/2010 | Fremont-Winema National Forests, OR (In Spreads: 6 and 7)
This NTP specifically grants widening up to 30 feet as necessary for the following Access Roads:
(Related to MPs) MP 611.0 to 611.5: L-12B Ruby has withdrawn the request for the use and widening this road as of 10/25/2010, USE AND WIDENING OF THIS ROAD RESCINDED IN NTP 27A) MP 631.0 to 632.0: L-15E MP 635.0 to 635.8: L-15B (USE AND WIDENING NOT GRANTED PER NTP 27) MP 639.0 to 639.5: L-15F MP 645.9 to 649.3: CT-43, L-19C, L-19D, L-22, K-1A, K-1B, K-1C, K-1D, K-1E, MP 649.5 to 651.0: K-2, K-3A
(Unrelated to MPs) L-9A (NO WIDENING PERMITTED PER NTP 27), L-18 (SEE FOREST SERVICE STIPULATION NTP 27), L-20 (SEE FOREST SERVICE STIPULATION NTP 27)
Alignment Sheets Referenced: 300A-247, 300A-248, 300A-251, 300A-261, 300A-262, 300A-264 through 300A-267; 300A-273
Quadrangle Sheets Referenced: 104, 105, 109, 110, 111, 113A | 27 | 10/14/2010 | Fremont-Winema National Forests, OR (In Spreads: 6 and 7)
Mile Posts (MPs): MP 611.0 to 611.5 MP 627.8 to 629.7 MP 631.0 to 632.0 | MP 635.0 to 635.8 MP 639.0 to 639.5 MP 645.9 to 649.3 | MP 649.5 to 651.0 MP 666.3 to 666.8 |
and Access Roads: (Related to MPs) MP 611.0 to 611.5: L-12B MP 631.0 to 632.0: L-15E MP 635.0 to 635.8: L-15B (NOT GRANTED THIS NTP-SEE OTHER STIPULATIONS NEXT PAGE) MP 639.0 to 639.5: L-15F MP 645.9 to 649.3: CT-43, L-19C, L-19D, L-22, K-1A, K-1B, K-1C, K-1D, K-1E, MP 649.5 to 651.0: K-2, K-3A
(Unrelated to MPs) L-9A (NO WIDENING PERMITTED PER FOREST SERVICE), L-18 (SEE FOREST SERVICE STIPULATION NEXT PAGE), L-20 (SEE FOREST SERVICE STIPULATION NEXT PAGE) Alignment Sheets Referenced: 300A-247, 300A-248, 300A-251, 300A-261, 300A-262, 300A-264 through 300A-267; 300A-273 Quadrangle Sheets Referenced: 104, 105, 109, 110, 111, 113A | 26 | 10/12/2010 | Salt Lake Field Office, UT (In Spread: 3)
Mile Posts (MPs): MP 220.8 to MP 222.1 MP 227.5 to MP 230.0 and Access Road: MP 227.5 to 230.0 - B-63
Alignment Sheets Referenced: 300A-91, 300A-92, 300A-94, and 300A- 95
Quadrangle Sheets Referenced: 38-40 | 25a | 10/21/2010 | Elko District Office, NV (In Spread: 5)
This NTP specifically grants widening up to 30 feet as necessary for the following Access Roads:
(Related to MPs) MP 330.4 to 339.0: E-37, E-38, E-40, E-41, E-42 MP 339.5 to 343.1: E-43 MP 343.1 to 346.0: E-45 (USE AND WIDENING NOT APPROVED IN NTP 25), E-46
(Unrelated to MPS)
E-3A, E-9, and E-10 (USE AND WIDENING OF ALL THREE ROADS NOT APPROVED IN NTP 25) E-12, E-48B, E-48C, E-48D, E-48E (NOT APPROVED BY FERC), E-48F (NOT APPROVED BY FERC).
Alignment Sheets Referenced: 300A-135 through 300A-142
Quadrangle Sheets Referenced: 57-60 | 25 | 3/16/2011 (Reissue)
10/14/2010 (Original) | Elko District Office, NV (In Spread: 5)
Mile Posts (MPs): MP 327.5 to 328.8; MP 330.4 to 346.0
And Access Roads: (Related to MPs) MP 330.4 to 339.0: E-37, E-38, E-40, E-41, E-42 MP 339.5 to 343.1: E-43 MP 343.1 to 346.0: E-45 (NOT APPROVED THIS NTP), E-46
(Unrelated to MPS)
E-3A, E-9, and E-10 (ALL THREE ROADS NOT APPROVED THIS NTP) E-12, E-48B, E-48C, E-48D, E-48E, E-48F
Alignment Sheets Referenced: 300A-135 through 300A-142
Quadrangle Sheets Referenced: 57-60 | 24a | 10/21/2010 | Winnemucca District Office, NV (In Spread: 5)
This NTP specifically grants road widening up to 30 feet for the following Access Roads:
MP 428.3 to 450.5 – H-22, H-22A, H-23, H-24, H-24A, H-25, H-26, H-26A, H-26B
Alignment Sheets Referenced: 300A-176 through 300A-185
Quadrangle Sheets Referenced: 74 and 75 | 24 | 10/13/2010 | Winnemucca District Office, NV (In Spread: 5)
Mile Posts (MPs): 428.3 to 450.5 and Access Roads: MP 428.3 to 450.5 – H-22, H-22A, H-23, H-24, H-24A, H-25, H-26, H-26A, H-26B
Alignment Sheets Referenced: 300A-176 through 300A-185
Quadrangle Sheets Referenced: 74 and 75 | 23a | 10/21/2010 | Surprise Field Office, CA (In Spread: 6)
This NTP specifically grants widening up to 30 feet as necessary for the following Access Roads:
MP 567.5 to 577.0 – W-9, W-14, and W-14A
Alignment Sheets Referenced: 300A-233 through 300A-237
Quadrangle Sheets Referenced: 97 through 99 | 23 | 10/12/2010 | Surprise Field Office, CA (In Spread: 6)
Mile Posts (MPs): 567.5 to 577.0 and Access Roads: MP 567.5 to 577.0 – W-9, W-14, and W-14A
Alignment Sheets Referenced: 300A-233 through 300A-237
Quadrangle Sheets Referenced: 97 through 99 | 22 | 10/01/2010 | Kemmerer Field Office, WY (In Spread: 1A)
Mile Posts (MPs): 6.39 to 18.16 19.59 to 48.04 SKIP: MP 18.16 TO 19.59 (NOT Authorized under this NTP) and Access Roads: All access roads, EXCEPT LW-23 and LW-24 (NOT Authorized under this NTP), with the following requirement:
The following access roads require cultural resources reconnaissance and/or full cultural resource monitoring prior to any maintenance or upgrading activity: LW-11, LW-13, LW-14A, LW-6B, LW-17, LW-20, LW-21B, LW-22, LW-23, LW-24, LW-26, LW-31, U-1WS, Staging Areas - Sections 16 and 18, T18N, R117W, U-10, U-20, U-24, U-25, U-26, U-U-27, U-28, Staging area - Section 16, T19N, R120W, U-31
Alignment Sheets Referenced: 300A-4 through 21
Quadrangle Sheets Referenced: 2 through 9 | 21 | 10/12/2010 | Salt Lake Field Office, UT (In: Spreads: 2, 1B, and 3)
Mile Posts (MP): 60.3 to 60.7 152.5 to 154.0 165.7 to 174.8 176.8 to 178.8 214.0 to 215.0
And the following Access Roads: MP 60.3 to MP 60.7: Access Roads R18, R19, R20, R21
MP 152.5 to MP 154.0: Access Roads B-26, B-26A, B-26B, B-28, B-28B, B-29, B-29A, B-29B
MP 165.7 to MP 174.8: Access Roads B-27A (NOT AUTHORIZED THIS NTP), B-27C (NOT AUTHORIZED THIS NTP), B-33 (NOT AUTHORIZED THIS NTP), B-34, B-36, B-36A, B-37
MP 176.8 to MP 178.8: Access Roads B-39A, B-39B MP 214.0 to MP 215.0: Access Roads B-46A, B-47, B-50A, B-50D, B-63
Alignment Sheets Referenced: 300A-26; 300A-64; 300A-69 through 74; 300A-89
Quadrangle Sheets Referenced: 12, 26, 28, 29, 30, 31, 37 | 20a | 2/28/2011 (Reissued)
10/27/2010 (Original) | Elko District Office, NV (In Spread: 5) This NTP specifically grants use and widening up to 30 feet as necessary for the following Access Roads:
(Related to MPs) MP 380.5 to 386.8: E-57 (E-57 is a DO NOT USE ROAD and is not approved under this NTP), E-57A (See Elko District Stipulations), E-57B, E-57C (See Elko District Stipulations).
Alignment Sheets Referenced: 300A-156 through 159
Quadrangle Sheets Referenced: 65 and 66 | 20 | 3/16/2011 (Reissue 2)
10/06/2010 (Original) | Elko District Office, NV (In Spreads: 3, 4, and 6)
Mile Posts (MP): | 230.0 to 270.0 | 324.0 to 327.5 | | 275.0 to 276.0 | 380.5 to 384.0 | | 284.3 to 289.0 | 384.0 to 386.8 | | 316.0 to 319.0 | |
And the following Access Roads: MP 316.0 to MP 319.0: Access Roads E-28, E-28A MP 324.0 to MP 327.5: Access Roads E-33, E-35
Alignment Sheets Referenced: 300A-95 through 112; 300A-114; 300A-117 to 119.1; 300A-130 through 131; 300A-133 through 135; 300A-156 through 159Quadrangle Sheets Referenced: 40, 41, 46, 49, 55, 56, 57, 65, 66 | 19a | 11/17/2010 | BLM Lakeview Resource Area and Fremont-Winema National Forests, OR (In Spread 6) L-3 (NOT Approved in NTP 19, NOT Approved this NTP) CT-3 L-4 L-5 L-8
Alignment Sheets Referenced: 300A-244, 300A-248, 300A-250
Quadrangle Sheets Referenced: 102, 103, 104 | 19 | 9/30/2010 | Lakeview Resource Area, OR and Fremont Winema National Forest, OR (In Spread: 6)
Access Roads: CT-3, L-4, L-5, and L-8 at Mile Posts (MPs): 605.5-611.0 (previously granted in NTP No. 1) Alignment Sheets Referenced: 300A-248 through 300A-251
Quadrangle Sheets Referenced: 102 through 105 | 18b | 11/02/2010 | BLM Surprise Field Office, NV (In: Spread 6)
W-8 W-10A
Alignment Sheets Referenced: 300A-229, 300A-231
Quadrangle Sheets Referenced: 95, 97 | 18a | 9/30/2010 | Surprise Field Office, CA (In Spread: 6)
Mile Posts (MPs): 552.0 to 553.0
Alignment Sheet Referenced: 300A-226 and 300A-227
Quadrangle Sheets Referenced: 95 | 18 | 9/30/2010 | Surprise Field Office, CA (In Spread: 6)
Mile Posts (MPs): 549.9 to 552.0 557.0 to 558.0 561.5 to 562.0 and Access Roads: W-5, W-8, W-10, W-10A
Alignment Sheets Referenced: 300A-225 through 300A-226; 300A-228 through 300A-230
Quadrangle Sheets Referenced: 94, 95 and 97 | 17 | 10/01/2010 | Winnemucca District Office, NV (In Spread: 5) Mile Posts (MPs): 415.0 to 416.3 424.0 to 425.0 and Access Road: H-15
Alignment Sheets Referenced: 300A-170 through 300A-171, and 300A-174
Quadrangle Sheets Referenced: 71 and 73 | 16 | 9/17/2010 | Winnemucca District Office, NV (In Spread: 5)
Mile Posts (MPs): 425.0 to 428.3 and Access Roads: MP 425.0 to MP 428.3 – H-16 and H-16A
Alignment Sheets Referenced: 300A-174 through 300A-176
Quadrangle Sheets Referenced: 73 and 74 | 15 | 9/27/2010 | Elko District Office, NV (In Spread: 4)
Mile Posts (MPs): 323 to 324 and Access Roads: MP 323 to MP 324 – E-29A and E-31
Alignment Sheets Referenced: 300A-133
Quadrangle Sheets Referenced: 56 | 14 | 9/16/2010 | Kemmerer Field Office, WY (In Spread: 1)
Mile Posts (MPs): 6.39 to 6.40 and Access Roads: MPs 6.39 to 6.40 LW-1, LW-1B, LW-4, LW-3, LW-6, LW-10, LW-11, LW-5, LW-6A ONLY to where it intersects with LW-13 in Section 34, T20N, R114W, LW-7, LW-8, LW-9, and LW-10A.
Alignment Sheets Referenced: 300A-3
Quadrangle Sheets Referenced: 2 | 13 | 9/13/2010 | BLM Salt Lake Field Office, UT (In Spreads: 1A and 3)
Mile Posts (MPs): 51.8 to 54.0 180.0 to 181.50 199.0 to 207.0 and all access roads between the MPs identified above as referenced in Appendix O of the Plan of Development, and those identified roads leading into the MPs listed above.
Alignment Sheets Referenced: 300A-23 and 300A-24 300A-75 300A-83.1, 300A-84.1, 300A-85.1, and 300A-86.1
Quadrangle Sheets Referenced: 9 and 10, 31 and 35 | 12 | 9/10/2010 | BLM Winnemucca District Office, NV (In Spread: 5)
Mile Posts (MPs): 396.7 to 415.0 and all access roads between the MPs identified above as referenced in Appendix O of the Plan of Development, and those identified roads leading into the MPs listed above.
Alignment Sheets Referenced: 300A-164 through 300A-171
Quadrangle Sheets Referenced: 68-71 | 11b | 11/04/2010 | BLM Elko District Office, NV (In Spread 4)
Access Roads: E-20 and E-25
Alignment Sheets Referenced: 300A-124 and 300A-127 to 300A-129
Quadrangle Sheets Referenced: 51 and 53 | 11a | 2/28/2011 (Reissued)
9/21/2010 (Original) | BLM Elko District Office, NV (In Spread: 4)
Access Road Nos. E-21 and E-23
Alignment Sheets Referenced: 300A-124 and 300A-125
Quadrangle Sheets Referenced: 51 and 52 | 11 | 3/16/2011 (Reissue 2)
9/10/2010 (Original) | BLM Elko District Office, NV (In Spreads: 3, 4, and 5)
Mile Posts (MPs): 289.0 to 316.0 377.5 to 380.5 386.8 to 396.7 and all access roads between the MPs identified above as referenced in Appendix O of the Plan of Development and those identified roads leading into the MPs listed above. EXCEPT: Access Road Nos. E-21 and E-23.
Alignment Sheets Referenced: 300A-119.1 through 300A-130 300A-155 through 300A-156 300A-159 through 300A-163
Quadrangle Sheets Referenced: 50-55, 65, 66-68 | 10 | 9/08/2010 | BLM Surprise Field Office, CA (In Spread: 6)
Access Road No. W-9, south of Access Road 10A at Mile Posts 561.5 to 562.0
Quadrangle Sheet Referenced: 97 | 9a | 9/01/2010 | BLM Alturas Field Office, CA (In Spread: 7)
Road Nos.: M-1/M-1A M-11 M-12 M-13
Quadrangle Sheets Referenced: 112A, 113A, and 115 | 9 | 8/27/2010 | Modoc National Forest, California (In Spread: 7)
Road Nos.:
| M-1/M-1A | M-4 | M-7 | M-12 | | M-2 | M-5 | M-9 | M-13 | | M-3 | M-6 | M-11 | |
Quadrangle Sheets Referenced: 112A, 113A, and 115 | 8 | 8/23/2010 | Klamath Falls Resource Area and Fremont-Winema National Forest, Oregon (In Spread: 7)
Road Nos. (land jurisdiction): L19 (BLM and Fremont-Winema), K1 (Fremont-Winema), and K3 (also known as Willow Valley Road; BLM and Fremont-Winema)
Quadrangle Sheets Referenced: 110, 111,111A, 112, 112A, and 113 | 7 | 8/17/2010 | Elko District Office, NV (In Spread: 5)
Water Well located at MP 381.2
Alignment Sheet Referenced: 300A-157.1 | 6 | 8/13/2010 | Elko District Office, NV (In Spread: 4)
Water Well located at MP 300.4
Alignment Sheet Referenced: 300A-124 | 5 | 8/04/2010 | Winnemucca District, NV (In Spread: 5)
Desert Valley Compressor Station in Humboldt County, T41N, R33E, Section 9.
Quadrangle Sheet Referenced: 82 | 4 | 8/05/2010 | Salt Lake City Field Office, UT (In Spread: 3)
Wildcat Hills Compressor Station, Box Elder County, T12N, R10W, Sections 16/21.
Quadrangle Sheet Referenced: 29 | 3 | 8/04/2010 | Fremont-Winema National Forest (In Spread: 7)
Mile Post (MP) Range: 635.8 to 645.5
Alignment Sheets Referenced: 300A-261 to 300A-265 | 2 | 2/28/2011 (Reissued)
8/3/2010 (Original) | Salt Lake Field Office, UT (In Spreads: 1A, 2A, 1B, and 3)
Mile Post: 47.0 to 227.5
Alignment Sheets Referenced: 300A-21 to 300A-94
Elko District Office, NV (In Spreads: 3 and 4)
MP Ranges: 270.0-275.0 276.0-284.3 289.0-298.0 301.0-303.0 319.0-323.0 346.0-350.0 Wieland Flat Compressor Station in Elko County, T39N, R55E, Section 29.
Alignment Sheets Referenced: 300A-111 to 300A-114 300A-114 to 300A-117 300A-119.1 to 300A-123.1 300A-124 and 300A-125 300A-131 to 300A-133 300A-142 to 300A-144 Quadrangle Sheet Referenced: No. 35 Kemmerer Field Office, WY (In Spread: 1A)
Roberson Creek Compressor Station in Lincoln County, T20N, R115W, Section 24
Quadrangle Sheet Referenced: No. 2 | 1 | 7/30/2010 | Kemmerer Field Office, Kemmerer, WY (In Spread: 1A)
Mile Post (MP) 0.00 to 6.39 LW-11 to Opal Terminus at King Compressor Station. MP 11.62 to 17.9 MP 21.0 to MP 28.0 MP 29.9 to MP 48.04 King Meter Station, T21N, R114W, S28 Roberson Creek Compressor Station, T20N, R115W, S24
Alignment Sheets Referenced: 300A-1 to 300A-3, 300A-6 to 300A-9, 300A-11 to 300A-21 Winnemucca District Office, NV (In Spread: 5)
MP 416.3 to 424.0
Alignment Sheets Referenced: 300A-171 to 300A-174
Surprise Field Office, CA (In Spread: 6) MP 553.0 to 557.0 MP 558.0 to 561.5 MP 562.0 to 567.5
Alignment Sheets Referenced: 300A-227 to 300A-233
Lakeview Field Office, OR (In Spread: 6)
MP 604.0 to 611.0
Alignment Sheets Referenced: 300A-248 to 300A-251
Klamath Falls Resource Area, OR (In Spread: 7)
MP 666.8 to MP 675.0
Alignment Sheets Referenced: 300A-273 to 300A-276, 301A-1 |
 |
| |
|
|