DISTURBANCE CATEGORIES AND THRESHOLDS
Section 3809.10 How Does BLM Classify Operations?
- Comment: Proposed §3809.11(a) requires casual use disturbance to be "reclaimed."
Which reclamation standards apply?
Response: We changed the requirement in final §3809.10(a) to include the word
"reclamation," which is defined under §3809.5, rather than continue to use the phrase
"you must reclaim" that appeared under proposed §3809.11(a). The definition of
"reclamation" should clarify the standards that are to be met. Wording was added to final
§3809.10(a) to clarify that if operations do not qualify as casual use, a Notice or Plan of
Operations is required, whichever applies.
- Comment: With no notification requirements, it is not clear how BLM will monitor
casual use operations.
Response: We intend to monitor casual use operations in the course of our normal
duties, but we agree with the comment and deleted the statement from proposed
§3809.11(a).
Section 3809.11 When Do I Have to Submit a Plan of Operations?
- Comment: Revise the table in proposed §3809.11 to avoid duplicating or summarizing
the definitions in 3809.5 and to eliminate ambiguity. The table is difficult to follow.
Response: The table in proposed §3809.11 has been eliminated from the final rule. The
information formerly in that table has been reorganized and edited and now appears under
final §3809.11, §3809.21 and §3809.31.
- Comment: Mining disturbance greater than casual use should require a Plan of
Operations to be consistent with the National Research Council (NRC) report.
Response: This change was adopted into the final rule to comply with NRC (1999)
report Recommendation 2.
- Comment: The current casual use/notice/plan threshold is adequate and should be
retained. The threshold protects the environment and reduces costs of exploration for
operators.
Response: Retaining the above-described threshold would be inconsistent with NRC
report Recommendation 2. Therefore, we did not adopt the comment.
- Comment: Mining or milling operations, which will cause a significant impact, even if
related to 5 acres or less, should be required to submit a plan of operations for approval.
Response: BLM has incorporated NRC (1999) report Recommendation 2 in our
proposed final regulations to require Plans of Operations for all mining and milling.
- Comment: The NRC report did not evaluate the adverse impact of Recommendation 2
on the vast majority of miners who have complied with existing regulations.
Response: We have incorporated NRC report Recommendation 2 into the proposed final
regulations and have evaluated its impact in the final EIS.
- Comment: NRC Recommendation 2 should not be supported because it would
automatically exclude from Notices some operations that would not significantly affect the
environment.
Response: Your comment is noted, but we have incorporated NRC's Recommendation 2
into the proposed final regulations
- Comment: BLM should adopt the NRC Committee's recommendations that exploration
be allowed under Notices, whereas mining would require Plans of Operations, but should
leave further details to agency guidance. The criteria for distinguishing between
"exploration" and "mining," may vary from state to state.
Response: We have incorporated NRC's Recommendation 2 into the proposed final
regulations. Guidance on implementing the regulations will follow when the regulations
become final.
- Comment: BLM should not require all mining operations to be conducted under Plans of
Operations, but should retain Notices for placer and lode mines that do not use toxic
chemicals or create acid rock drainage.
Response: We note your comment but have incorporated NRC's Recommendation 2 into
the proposed final regulations.
- Comment: It is unnecessary to require Plans of Operations for mining in light of the
proposed financial assurance requirements for Notices.
Response: We note your comment but have incorporated NRC's Recommendation 2 into
the proposed final regulations.
- Comment: Any activity requiring construction equipment or engineering design should
need a Plan of Operations in light of the NRC report. Mechanized drilling equipment, off-highway vehicles, and bulldozers should also require a Plan of Operations.
Response: We note your comment but have incorporated NRC's Recommendation 2 into
the proposed final regulations.
- Comment: Lowering the threshold for Notices or Plans of Operations seems to conflict
with the 1970 Mining and Mineral Policy Act and the 1980 National Materials and
Minerals Policy Research and Development Acts.
Response: We and the public operate under many conflicting laws. We believe we have
balanced the mandate of FLPMA to prevent unnecessary or undue degradation of the
public lands with the above-mentioned mineral policy acts that promote development of
the Nation's mineral resources.
- Comment: Some bulk sampling may cross the line from exploration to mining. Bulk
sampling to remove less than 100 tons of material cannot be compared to bulk sampling
that requires 10,000 tons for testing, which is the known range in size of such activities.
While a bulk sample proposal under a Notice deserves scrutiny, the final determinations
should be made on a case-by-case basis.
Response: BLM recognizes that bulk sampling is not easy to define. Bulk samples vary
in many ways, including size and weight, as acknowledged in the NRC (1999) report. We
have chosen a threshold at the upper limit of the NRC discussion on bulk sampling: 1,000
tons or more would trigger the requirement for a Plan of Operations. (See final
§3809.11(b)). We believe that this limit implements NRC report Recommendation 2 in a
way that does not unduly constrain exploration (see NRC report Recommendation 3) yet
provides a clear cutoff that can be verified by BLM field people.
- Comment: BLM should use caution in deciding whether to exclude bulk sampling from
Notice-level operations. The NRC report (page 96) refers to activity that involves the
"excavation of considerable amounts of overburden and waste rock" to get to layers
where the bulk samples will be taken. Sampling of that nature gets to be so extensive as to
require a Plan of Operations. Other activities that might nominally qualify as bulk
sampling, such as ones that do not first remove large amounts of overburden, can properly
be treated as exploration subject to the Notice-level program. Such sampling involves far
less disturbance than the activities listed by NRC, and, in any event, the land from which
the bulk samples are taken must still be reclaimed. For these reasons, in case of bulk
sampling, BLM should focus not on the amount of earth sampled, but rather the sampling
method.
Response: BLM recognizes that bulk sampling is not easy to define. Bulk samples vary
in many ways, including size and weight, as the NRC (1999) report acknowledged. The
report discussion on sampling clearly states that NRC believes not all sampling programs
would require a Plan of Operations, but that Plans of Operations would generally be
required. In considering the NRC discussion, BLM does not believe that drilling should
be considered a bulk sampling method because NRC characterized bulk samples as
excavations from shallow open pits or small underground openings. We have chosen a
threshold at the upper limit of the NRC discussion on bulk sampling, that is, bulk samples
of 1,000 tons or more will trigger the requirement for a Plan of Operations. (See final
§3809.11(b)). We believe this limit implements NRC report Recommendation 2 in a way
that does not unduly constrain exploration (see NRC report Recommendation 3) yet
provides a clear "cutoff" that can be verified by BLM field personnel.
- Comment: BLM should revise the language that now appears in final §3809.11(c)(3) to
state that an area of critical environmental concern (ACEC) triggers this provision only
when the establishing of the ACEC considered and evaluated existing mineral rights and
mineral potential.
Response: ACECs are designated through BLM's land use planning process and are
subject to public comment before designation. This process allows the public to comment
and BLM to consider and evaluate mineral potential and valid existing rights. The
requirement for a Plan of Operations in ACECs would result in a more formal review and
approval of mining or exploration, which would help assure better planning and protection
of the resources for which the ACEC was established.
- Comment: Most mining claims held by small miners are either within areas closed to off-road vehicles or within areas proposed to be closed to off-road vehicles. As such, almost
all small miners will be required to prepare Plans of Operations for any level operation on
their claims.
Response: The requirement is restricted to areas designated as "closed" to off-road
vehicle use. It does not apply to proposed closures. This requirement remains unchanged
from previous §3809 regulations in effect since 1981.
- Comment: BLM should include riparian areas under proposed 3809.11(j), as in the
Northwest Forest Plan.
Response: Using the new performance standards, including the protection of riparian
areas and wetlands found in final §3809.420(b)(3), we believe that riparian areas will be
adequately protected.
- Comment: We oppose requiring a Plan of Operations for operations affecting proposed
threatened and endangered species or designated critical habitat because of the uncertainty
and delays to the permitting process and the additional workload required.
Response: We believe that the requirement to submit a Plan of Operations for surface
disturbance greater than casual use on any known lands or waters known to contain
federally listed threatened and endangered species or their proposed or designated habitat
is the best way to protect these species. Under §3809.11(c)(6) BLM can develop land use
plans or endangered species recovery plans which might then allow Notices to be filed.
- Comment: Delete the phrase "unique, irreplaceable, or outstanding historical, cultural,
recreational, or natural resource values" from proposed §3809.11(j)(6), since this phrase
may be too subjective and any public lands could meet these criteria. Some commenters
believe that defining "special status areas" by those criteria would establish ad hoc
designations of ACECs as to mining without following the procedures of 43 CFR 1610.7-2. Delete the term "activity plans."
Response: We have deleted these phrases from the final rule for several reasons. First,
we modified the definition of unnecessary or undue degradation in final §3809.5 to include
conditions, activities, or practices that result in substantial irreparable and unmitigatable
harm to significant scientific, cultural, or environmental resources of the public lands.
Second, we retained language specific to threatened or endangered species in recognition
of the consultation requirements of the Endangered Species Act. We believe that these
modifications have the same net effect as the language in proposed §3809.11(j)(6).
- Comment: The term "special status areas" (used in final §3809.11(c)) is very broad, and
would effectively remove many areas from exploration. The term expands BLM authority
to create such areas.
Response: The term is not meant to impart any distinctive meaning on its own; it is
simply a general reference to the types of lands listed in that section. The listed lands
have already been established under separate laws and are not affected by the regulations.
- Comment: Proposed 3809.11(j)(6) is too narrow an approach under BLM's
responsibility to prevent unnecessary or undue degradation, and to protect affected
resources BLM must retain authority to require Plans of Operations.
Response: We have deleted §3809.11(j)(6) from the final rule for several reasons. (See
§3809.11 for what would require a Plan of Operations.) First, we modified the definition
of unnecessary or undue degradation in final §3809.5 to include conditions, activities, or
practices that result in substantial irreparable and unmitigatable harm to significant
scientific, cultural, or environmental resources of the public lands that cannot be
effectively mitigated. Second, we retained language specific to threatened or endangered
species in recognition of the consultation requirements of the Endangered Species Act.
We believe that these modifications have the same net effect as the language in proposed
§3809.11(j)(6).
- Comment: Proposed §3809.11(e) is too vague on when a Notice or Plan of Operations
would be required for group recreational mining. Recreational and mineral collecting
groups should not be singled out and have to submit a Notice or a Plan of Operations. It
is an unreasonable requirement and, in some cases, mineral-collecting groups could not
afford the financial guarantees, which they feel are unnecessary for those who use only
hand tools. BLM should not recognize such activities under the mining laws.
Response: We have deleted §3809.11(e) from the final rule. Provisions for when a
Notice or Plan of Operations would need to be submitted that would affect recreational
and mineral collecting groups can be found in the final rule, §3809.31(a). The changes in
§3809.31(a) provide more clarification as to when a Notice or Plan of Operations would
be required.
- Comment: Proposed §3809.11(f) will eliminate flexibility when requiring Plans of
Operations for uses described in that section.
Response: We deleted proposed §3809.11(f) but in order not to be inconsistent with
NRC Recommendation 2, we retained in the final rules the provision requiring a Plan of
Operations for mining and milling operations.
§3809.11 "Forest Service" Alternative
- Comment: BLM received a variety of comments on the Forest Service alternative in the
proposed regulation. They are as follows: The Forest Service alternative would provide a
consistent approach to federal agency administration of the Mining Law. The surface
resources on BLM public lands deserve the same level of protection as do the national
forest lands. Adoption of the Forest Service alternative would be less confusing in those
mineralized areas that occur on both BLM lands and in national forests. The Forest
Service alternative compares favorably to proposed §3809.11 (Alternative 1) because of a
perception that the Forest Service alternative would provide greater protection to non-special status areas, that is, those areas not listed in proposed §3809.11(j). BLM did not
provide a meaningful basis for reasoned comment on this issue. The Forest Service
alternative has an advantage because it places the burden of deciding whether a Notice or
Plan is needed on the government as opposed to the operator. The significant disturbance
standard of the Forest Service alternative would be too vague, too open to varying
interpretations, create uncertainty as to which operations it would apply, and create
significant potential for disagreement between the operator and BLM over whether a
planned operation would create significant disturbance. The significant disturbance
standard of the Forest Service alternative goes beyond FLPMA's statutory directive to
prevent unnecessary or undue degradation. Adoption of the Forest Service alternative
would eliminate the use of Notices for small exploration operations. If so, business would
be adversely affected. Eliminating Notices for placer mining in Alaska would create a
hardship for small miners, who couldn't meet the requirements for filing a proposed Plan
of Operations. The Forest Service alternative would consume more of BLM's already
thinly spread resources, potentially causing administrative delays and increase costs due to
NEPA compliance requirements.
Response: Congress has required BLM not be inconsistent with the NRC (1999) report.
This report recommends that exploration disturbing less than 5 acres be allowed under
Notice-level activity.
Section 3809.21 When Do I Have to Submit a Notice?
- Comment: Small operators count on the 5-acre exclusion for rapid yet responsible
evaluation of many projects to make its discovery. Such operators may not have the
finances for lengthy permit procedures and time delays, as do major mining companies.
Without the 5 acre threshold, future exploration would be conducted almost exclusively by
the largest of the mining companies.
Response: The 5-acre threshold for submitting a Notice has been retained for exploration
activities of 5 acres or less.
- Comment: Define "unreclaimed" as used in proposed §3809.11(b) and proposed
§3809.11(c). BLM should not regard the Notice threshold as "unreclaimed surface
disturbance of 5 acres or less."
Response: We have changed the term "unreclaimed surface disturbance of 5 acres or
less" in §3809.21(a)(1) to clarify the requirement. By specifying "public lands on which
reclamation has not been completed," we expressly intend to use the term "reclamation" as
defined in final §3809.5. This means that reclamation must meet performance standards in
final §3809.420, and BLM must accept such reclamation before releasing a financial
guarantee. Once reclamation has been completed to these standards, we believe that such
lands may be treated as if never disturbed when considered in a Notice submittal.
- Comment: Clarify under proposed §3809.11(b) how an operator is responsible to
reclaim the previous disturbance by another operator.
Response: As with proposed §3809.11(b) and (c), and the final rule, the operator is
liable for prior reclamation obligations in a project area if conditions described under final
§ 3809.116 are met. Operators who believe that BLM should not hold them responsible
for past reclamation obligations should contact BLM before causing more surface
disturbance. BLM could then advise them as to whether it is taking any action against
previous operators or mining claimants at the disturbed site.
- Comment: Revise proposed §3809.11(b) to retain the existing requirement for BLM to
act within 15 calendar days. Extending the review period to 15 business days would delay
exploration. Operators need flexibility and speed for Notice-level exploration projects, and
that timing of exploration activities is often critical. Streamline the processing of Notices
as much as possible and avoid delays. Streamlining the process would be consistent with
the NRC report.
Response: We changed the final rule to use calendar days rather than business days in
response to public comments and the NRC (1999) report recommendations to minimize
impacts on exploration and small operators.
- Comment: Clarify what is meant by "business days" since government business days do
not coincide with industry business days.
Response: We changed the final rule to use calendar days rather than business days in
response to public comments and the NRC report recommendations to minimize impacts
on exploration and small operators.
- Comment: In the proposed rule the 15-business-day review period given BLM to review
Notices is too short to ensure adequate investigation by the agency. We suggest 30 days.
Response: We did not implement this suggestion. Instead, we changed the final rule to
use calendar days rather than business days in response to public comments and the NRC
report recommendations to minimize impacts on exploration and small operators.
Section 3809.31 Special Situations That Affect Submittals Before Conducting Operations
- Comment: Suction dredges with intake diameter of 8 to 4 inches or less should be
considered casual use and not require a Notice or a Plan of Operations. It is not clear how
BLM determined the 4" intake threshold. BLM should adopt state requirements,
including intake size and not be more stringent than the State. It appears that the
proposed rule requires a Notice or Plan of Operations for any dredging activity, regardless
of how insignificant. Replace the 4" nozzle threshold with language that identifies surface-disturbing activities as the threshold for Notice level use. High-value fish and wildlife
habitats could be harmed by a 4" suction dredge intake. Require standards for suction
dredging concerning cumulative impacts and stream status. BLM should consider a
broader range of values that could be affected when assessing whether to regulate portable
suction dredges under 4 inches in diameter. Suction dredge operators should, at a
minimum, be required to obtain an individual National Pollution Discharge Elimination
System (NPDES) permit. Avoid the contradiction that small suction dredges are not
considered casual use yet do not follow requirements for Notices or Plans of Operations.
BLM should define small dredges as recreational or casual use and not require bonding or
Notices unless the operators have a record of causing problems or noncompliance. The
National Research Council does not wish small-scale dredging operations, those that use a
nozzle size of 8 inches or less, to be categorized as a mining operation. Very small
industrial mineral mines or placer operations (other than the small dredges discussed
above) that use only simple sorting methods should not automatically be required to
submit Plans of Operations. Such determinations should be made on a case-by-case basis.
The language in proposed §3809.11(h) would conflict with Recommendation 2 of the
NRC report. Suction-dredging is properly managed under state or local authority. If the
proposed rule is finalized, the proposed alternative that would allow an operator to use
any suction dredge if it was regulated by the state and the state and BLM have an
agreement to that effect should be adopted as the least burdensome alternative.
Response: We deleted the reference in proposed §3809.11(h) to an "intake diameter of 4
inches or less." We retained language that relies on state regulation. When the state
requires an authorization for the use of suction dredges and BLM and the state have an
agreement under final §3809.200 addressing suction dredging, we will not require a
Notice or Plan of Operations unless otherwise required by this section. In addition, we
added clarifying language and cross-references under final §3809.31(b)(1) and
§3809.31(b)(2). Given the NRC report discussion that endorses the way BLM regulates
suction dredging, we believe that the NRC did not intend in its Recommendation 2 to
require Plans of Operations for suction dredging. The rule will allow most suction
dredging to be regulated by state regulatory agencies as long as they have a permitting
program that is the subject of an agreement with BLM under final §3809.200. Therefore,
we find that final §3809.31(b) is not inconsistent with Recommendation 2 of the NRC
report.
- Comment: Since suction dredging takes place in rivers and streams and not on the land,
it should be under state authority and regulation, not BLM regulation.
Response: We generally agree that it is appropriate for states to regulate activities within
navigable waters. Even in such cases, BLM believes it has the authority to protect the
public lands above high water mark where there may be adjacent, related operations. But
in many cases, there has been no such determination of navigability for rivers and streams
on public lands. In these instances, BLM has clear authority to regulate the operations.
We believe we have provided for proper state regulation of suction dredging in final
§3809.31(b).
Operations Conducted Under Notices
- Comment: Clarify in §3809.300(a) that all Notices will expire after 2 years and then the
final rules will apply.
Response: The final rule has been modified to clarify the intent of the section.
- Comment: Use a tax identification number instead of a social security number in the
operator information required under proposed §3809.301(b)(1).
Response: We agree and have made that change in the proposed final regulations, as well
as under final §3809.401(b)(1).
- Comment: Notice content requirements should not include the dates that operations will
begin and when reclamation will be completed, since these are never exactly known.
Response: We agree and have changed final §3809.301(b)(2)(iv) accordingly by asking
for the expected dates that operations will begin and reclamation will be completed. We
have also specified "calendar" days under final §3809.301(d) for clarity.
- Comment: Add a requirement to §3809.301(b), §3809.312, and §3809.313 for an
operator to advertise planned operations in a local newspaper, not beginning operations
until 30 days after publication. This time would allow the public to file written objections.
Response: We did not adopt this comment since we believe that this suggestion would
conflict with NRC report Recommendation 3 dealing with expeditious handling of
exploration.
- Comment: Add to §3809.311 language that allows any person with an adversely affected
interest to file written objections to a Notice within 30 days of advertising planned
operations.
Response: We did not adopt this suggestion because we believe that it would conflict
with NRC report Recommendation 3 on expeditious handling of exploration .
- Comment: Operators should not have to provide a reclamation cost estimate under
proposed 3809.301(b)(4) because BLM would review and modify a reclamation plan in
most cases.
Response: We do not agree with this comment and have not adopted the suggested
change. The burden should be on operators, who are the proponent of the activities
requiring reclamation, to give their best estimate of reclamation costs.
- Comment: BLM should review Notices for completeness in time frames ranging from 5
calendar days to 20 business days.
Response: We have rejected this suggestion because we believe the 15 calendar day
review period should include a completeness review. If BLM staff determines that a
Notice is incomplete in less time, we will notify the operator as soon as possible.
- Comment: Clarify the standards BLM will use to see if a Notice is complete under
3809.311(a).
Response: The standards for completeness are listed in final §3809.301.
- Comment: The State Game and Fish Department would like to review proposals,
regardless of acreage, where there is concern about fish and wildlife resources, or limited,
high-value wildlife habitats such as riparian zones and wetland habitats.
Response: During the Notice-review process BLM will make every effort to coordinate
with state regulators. This coordination will likely happen through state/federal
agreements, such as described under final §3809.200.
Section 3809.312 When May I Begin Operations After Filing a Complete Notice?
- Comment: BLM should be required to inform the operator when a Notice is complete
and operations can begin.
Response: This comment has not been incorporated in the final rule. The Notice system
is designed to allow an operator to begin operating if not notified by BLM of its concerns
about compliance with this rule.
- Comment: New §3809.312(e) should be added that would notify operators that they
may be subject to more requirements imposed by state regulation and that operators must
be in compliance with such requirements before beginning operations.
Response: The comment was not adopted. This requirement is already covered under
§3809.5, under the definition of unnecessary or undue degradation. See also final
§3809.3. In addition, state law applies by its own terms.
- Comment: The 15-business-day time frame proposed for Notice review would not be
realistic since an operator would be required to provide a financial guarantee before
beginning operations.
Response: In practice, an operator would need to obtain a financial guarantee before or
soon after filing a complete Notice in order to begin operations 15 days later.
- Comment: Notice-level operations should not be required to furnish financial guarantees,
as required under proposed 3809.312(c), if no cyanide or leaching is proposed.
Response: The requirement for a financial assurance beyond casual use has been left in
the final rules so as not to be inconsistent with NRC report Recommendation 1.
- Comment: BLM would be able to extend the 15-business-day review period for a Notice
indefinitely under proposed 3809.313 due to the ambiguous, proposed language of that
section.
Response: Under §3809.313(a), the final rule allows BLM to extend the review period
by 15 more calendar days. Specific time frames were not included in §3809.313(b), (c),
and (d), because it could take longer to resolve BLM concerns.
Section 3809.330 May I Modify My Notice?
- Comment: Proposed § 3809.330 does not define how an incomplete Notice modification
affects the existing Notice.
Response: Final §3809.330(b) states that modified Notices will be handled under the
procedures of final §3809.311, which addresses incomplete Notices. You may not
proceed with the modified Notice until it is complete and BLM has reviewed it.
Section 3809.331 Under What Conditions Must I Modify My Notice?
- Comment: It is unclear how §3809.331(a)(1) would apply to private lands.
Response: §3809.331(a)(1) applies to modifications of Notices involving public lands. It
has nothing to do with private lands.
- Comment: 24000.50: It is unclear how much time BLM would give an operator to
comply with §3809.331(a)(1) if BLM requires modification of a Notice.
Response: The length of time that BLM requires to modify a Notice will depend on site-specific conditions. The time requirements will be spelled out in an appealable decision
letter sent to the operator from the BLM.
- Comment: BLM should revise proposed 3809.331(a)(1) to require documentation of
unnecessary or undue degradation that BLM had found.
Response: Normal case processing in BLM includes documenting our findings in case
files. This documentation ensures a good written record upon which the local BLM
manager can base decisions and findings. These findings and decisions on unnecessary or
undue degradation would be included in an appealable decision letter sent by BLM to the
operator and requiring modification of the Notice.
Section 3809.332 How Long Does My Notice Remain in Effect?
- Comment: Two years is a reasonable period for a Notice to be effective, but the
responsibility for operators to reclaim operations should be independent of the validity of
the affected mining claims.
Response: The 2-year period addressed in final rule §3809.332 makes no mention of the
validity of the affected mining claims. Operators continue to be responsible for
reclamation of their disturbances after expiration of a Notice or abandonment of a mining
claim.
- Comment: Notices should expire in 4 to 5 years.
Response: Operators may file extensions under final §3809.333 to keep their Notices
and our records current. Additional extensions are allowed.
- Comment: BLM has not shown that an inability to clear expired Notice records has
resulted in unnecessary or undue degradation and that it would be inappropriate to clear
records since reclamation may not be completed for a considerable time in the future at a
project area.
Response: This provision remains in the final rule because it will help BLM clear its
records of Notices where no activity has occurred or Notices that have remained inactive
for long periods since operations began. Reclamation obligations will continue for the
operator until completed, regardless of the disposition of the Notice.
Section 3809.333 May I Extend My Notice, and, if so, How?
- Comment: Clarify that Notices would be extended only if there is an acceptable financial
guarantee as provided under §3809.503.
Response: We have incorporated a reference to §3809.503 to this subsection of the final
rule.
- Comment: The 2-year time frame for Notice extension is adequate. The 2-year time
frame for Notice extension is too short. Notice extensions should not be required if
operations do not change.
Response: Operators may file extensions under final §3809.333 to keep their Notices and
our records current. Additional extensions are allowed..
- Comment: Clarify that the only reason a Notice extension might not ensue is in the
instance of noncompliance, and in such a case BLM would notify the operator.
Response: We anticipate that only operators in good standing with the regulations will be
able to extend Notices. BLM will inform operators of the reasons for the noncompliance
and steps needed to correct it.
- Comment: Add language to §3809.330(a) and to §3809.333 to require public
notification for Notice modifications and extensions.
Response: We believe that adding such public notification requirements would be
inconsistent with NRC report Recommendation 3.
Section 3809.334 What if I Temporarily Stop Conducting Operations Under a Notice?
- Comment: BLM should provide written documentation of any finding under proposed
3809.334(b) that temporary cessation of operations will likely cause unnecessary or undue
degradation.
Response: BLM's findings, on a case-by-case basis, will be spelled out in an appealable
decision letter sent to the operator from BLM.
- Comment: §3809.334 inadequately addresses unnecessary or undue degradation caused
by improper storage and containment of hazardous materials and remediation of
contaminated soils.
Response: We believe that the performance standards applicable under §3809.320 as well
as the continued requirement to prevent unnecessary or undue degradation adequately
address these concerns.
- Comment: Define "period of time" as used in §3809.334(a) and "extended period of
non-operation" as used in §3809.334(b)(2).
Response: Regardless of the "period of time" that passes, at all times an operator must
meet the requirements of §3809.334(a). BLM will take actions needed to ensure the
prevention of unnecessary or undue degradation. BLM will determine the term of an
"extended period of non-operation" on a case-by-case basis after considering the
sensitivity of the resources in the project area.
Section 3809.335 What Happens When My Notice Expires?
- Comment: A third option should be added to §3809.335(a) to allow an operator to give
written Notice to BLM of the intent to extend the Notice per §3809.333. If an operator
misses the extension deadline but intends to operate, he/she should not be forced to
reclaim.
Response: Operators who face this situation would not be in compliance with §3809.333,
which requires they notify BLM in writing on or before the expiration date of their desire
to conduct operations for 2 additional years. We wrote §3809.333 in this way in order to
avoid long periods of time after a Notice expires for reclamation to be completed, and to
prevent unnecessary or undue degradation from occurring. If a Notice expires,
§3809.335(a) ensures that reclamation is promptly completed. If an operator
inadvertently misses a Notice-extension deadline, he/she must immediately submit a new
Notice and provide adequate financial guarantee as required under §3809.301, then follow
§3809.312. Quick submittal of a new Notice will ensure the prevention of unnecessary or
undue degradation and continuity of operations.
Section 3809.336 What if I Abandon My Notice-Level Operations?
- Comment: Since exploration is typically intermittent, Notice-level operations may appear
to be "abandoned" at some time during the 2-year Notice term.
Response: We have included in §3809.336 criteria to inform the public of indicators of
abandonment. BLM will strive to contact operators where it is not clear whether
operations have been abandoned. Our major concerns are the prevention of unnecessary
or undue degradation and that operators maintain public lands within the project area,
including structures, in a safe and clean condition.
- Comment: Revise §3809.336(a) to require BLM to provide an appealable determination
that the project area has been abandoned.
Response: Any written decision that BLM sends to an operator may be appealed as
outlined under §3809.800.
PLANS OF OPERATIONS
Existing/Pending Plans of Operations
- Comment: 3809.400(b) "BLM made an EA...available to the public...": Does this include
EAs that are on file at a BLM office and therefore "available" as public information, or are
the regs referring to public notification in a more formal sense (i.e. interested parties
receiving notification by mail or internet)? Also, does the EA need to be FONSI'd, final or
preliminary? These issues should be clarified so that the new regs can be implemented
more consistently. The proposed rule should delete the unfair NEPA document
publication requirement trigger to grandfather proposed Plan of Operations.
Response: §3809.400(b) was attempting to clarify the dates when the final rules would
become effective where Plans are pending awaiting the completion of an environmental
assessment (EA) or EIS. The final §3809.400(b) has been revised and no longer refers to
pending EAs or EISs in determining effective dates of the final rules on pending plans. If
the Plan of Operations were submitted before the effective date of the final regulations,
then it falls under the old plan content and performance standard requirements.
- Comment: All existing Notices or Plans of Operations should be grandfathered if they
put the new regulations in place unless the mining materially changes from what was
proposed and approved in the Notice or Plan.
Response: The final rules provide that all existing approved Plans of Operations, and
Plans of Operations pending on the effective date, would be grandfathered from the Plan
content requirements and the performance standards. All other portions of the regulations
such as bonding and enforcement would still apply. Material changes (modifications)
would be subject to the new regulations where practical as described in §3809.433.
- Comment: 3809.400. Please define what you consider to be a modification This should
be listed in the definitions. No cut-off date should exist since the operator is committing
capital. Under set assumptions, it's defined by the performance standards, and this would
deter anyone in this project, or the new rules could force his financial position into a
riskier state. In other words, he could not be able to fill it.
Response: A modification, as used in section 3809.432, is a change in a Plan of
Operations that requires some level of review by BLM because it exceeds what was
described in the approved Plan of Operations. We have added this definition to the
Glossary of the final EIS.
- Comment: For this rulemaking, the regulations in effect when a Plan of Operations is
submitted must govern. If BLM proceeds with this rulemaking, the final rule must clarify
that the new rules do not apply to any pending Plan of Operations and that the date of
submission of the Plan determines which rules will apply. The agency can, however, draw
some line, in a final rule, on the completeness or competence of the Plan pending at the
time of the final rule in order to prevent BLM from being required to exempt from the
new rules incomplete or obviously inadequate Plan s submitted solely for the purpose of
preventing application of the rule changes. At the same time, a fully developed Plan (that
covers all necessary facilities and addresses the major permitting statutes and issues) is
itself a significant investment of technical expertise, time and money. It is not prepared
and submitted to beat a deadline; it is submitted in a good faith effort to comply with
existing regulations. The operator may expect that there will be changes in the Plan
between submission and approval, based on agency review, public comment, or the
actions of other environmental permitting entities. At the same time, however, BLM
cannot reasonably expect the operator to design the initial Plan , or Plan modification, to
meet the conditions of rules that are not yet in effect, or in the alternative, completely
reconstruct a proposed Plan because new rules have been subsequently finalized.
Response: The final regulations provide for the effective date of the final regulations to
determine which performance standards and Plan content requirements apply to a Plan of
Operations. But BLM would require for a Plan to be grandfathered, that it be
substantially complete before the effective date of the regulations. This means that the
Plan if grandfathered under the old regulations must have reasonably met the content
requirements of the old regulations by the date the new regulations go into effect.
- Comment: Section 3809.400(b) must be amended to state clearly that if an operator files
a Plan of Operations before the effective date of the new regulations, then none of the new
regulations apply. Making filing the cutoff point for applications is appropriate. First, a
Plan of Operations typically entails the expenditure of substantial sums of money, time and
effort. Requiring a new Plan of Operations to be developed under any promulgated new
regulatory regime merely because BLM has not approved the Plan of Operations is an
inappropriate and unnecessary burden on the claimant. Second, it is only fair to the
operator that the Plan of Operations be reviewed, evaluated and implemented under the
rules in place at the time of the filing, rather than requiring the operator to refile the Plan .
Third, this test is easier for BLM to administer because it requires BLM to look no further
than the filing date to determine what criteria apply as opposed to the proposed rule,
which has different levels of applicability depending on whether BLM has made an
environmental assessment or draft environmental impact statement available to the public
before the effective date of the regulations. If a particular District Office has the adequate
staff to push a project through the schedule and publish an EA or EIS before
implementation of the revised rules. BLM's proposal is arbitrary in that an entity issued an
EA or Draft EIS the day before the regulations are effective would be able to operate
under its proposal whereas a similar project which missed the deadline by a few days
would be required to conform to the new requirements. An operator should not be
penalized due to delays largely or solely within BLM's control, whether warranted or not.
The grandfather or exemption threshold should respect the claimant-operator's
"considerable time and resources towards developing the Plan ".
Response: BLM has changed the final rules to provide for a substantially complete Plan
to be processed under the regulations that were in effect when it was submitted to BLM.
BLM agrees this would be more fair to the operator and easier to administer. But existing
or pending Plans of Operations would still be subject to the administrative provisions of
the new regulations such as financial assurance for reclamation, or enforcement.
- Comment: The approach of not grandfathering pending Plans filed before the effective
filing date is inconsistent with Section 3809.332, which uses the effective date of the final
rule as the date upon which an existing Notice will begin its 2-year term under the
proposed final regulations.
Response: The reason for this difference in the proposed final regulations is that Notices
are typically for activities of smaller scale and shorter duration than are Plans of
Operations. Therefore, the consequences of grandfathering existing Notices is not as
great as it is for Plans. With the changes to the proposed final regulations, pending Plans
of Operations would also be grandfathered in addition to notices.
- Comment: Unless the Department of the Interior has a request from the mining industry,
.400(d) should be deleted. It is unlikely that an owner/operator would voluntarily submit
to the more costly and more time-consuming provisions of the proposed revisions of the
existing 3809 regulations.
Response: Section 3809.400(d) is a voluntary provision and has been retained. An
operator may want certification that their operations are in compliance with the new
regulations, even where not required, for insurance or marketing purposes.
- Comment: 400(a) This entire section is not consistent with the NRC study findings and
Recommendations, especially Recommendations 9,11,15 and 16.
Response: BLM does not see any inconsistency in the final regulations with the NRC
study. NRC did not even address how existing or pending Plans of Operations should
transition with any changes in the regulations. But the final rules do provide for
exemption from the new performance standards and Plan content requirements for existing
and pending Plans of Operations. This is certainly consistent with the NRC comments at
various places in the report that procedures be fair and reasonable to operators and protect
the interests of the mining company in continuing to conduct operations.
- Comment: Under this proposal, an environmental assessment or draft EIS could be
substantially complete based on the current content requirements, at significant
expenditure of time and money, and without public review, would need to be completely
redone to reflect the new content requirements and performance standards.
Response: The extent to which individual Plans would have to be redone under the
proposed final regulations is highly site specific. BLM has changed the proposed final
regulations to grandfather existing and pending Plans of Operations submitted to BLM
before the effective date of the final regulations from the performance standards and Plan
content requirements. This change would prevent the situation of having to redo
significant expenditures on an EA or draft EIS.
- Comment: Proposed 3809.400(a) provides that all of the proposed final regulations,
except the performance standards in proposed 3809.420, would apply to Plans of
Operations approved before the effective date of the regulations. Operations under such
approved Plans of Operations should continue pursuant to the current regulations.
Otherwise, for example, such operations would be subject to whatever new definitions of
"unnecessary or undue degradation" that may be adopted (see Proposed 3809.1).
Response: Part of the "terms and conditions" in the final regulations under which
approved Plans of Operations would continue to operate, include the definition of
unnecessary or undue degradation that was in effect when the Plan of Operations was
approved. Plans of Operations that are grandfathered from the new performance
standards would not be subject to the new definition of unnecessary or undue degradation.
- Comment: Under the proposed rule 3809.400(b) , a proposed Plan of Operations or
proposed modification to a facility submitted before the final rule takes effect would be
subject to the revised 3809 program requirements unless BLM had released an
environmental assessment (EA) or draft EIS on the proposed Plan before the rule's
effective date. This approach is simply unfair given BLM's usual Plan approval process.
Operators typically wait between eighteen months and two years for BLM to make public
a draft EIS or EA. If an operator has expended significant funds determining whether a
planned operation (or modification) is feasible under the current rules and preparing a Plan
accordingly, it should not be compelled to go back to the drawing board two years later
simply because BLM has taken an inordinate amount of time to review the Plan . Indeed,
even if a revised Plan were later put together and resubmitted to BLM, the operator
would have to wait another three to five years for BLM approval. There can be no doubt
that operators spend considerable sums preparing Plans of Operations, including Plans to
modify facilities. As we explained in our comments on BLM's Paperwork Reduction Act
submission to the Office of Management and Budget, under the existing regulations it
takes an average of 2,748 person hours to prepare a Plan of Operations. Those hours
involve the services of scores of professionals and thus require enormous expenditures.
For example, Newmont Gold typically spends between $150,000 and $200,000 preparing
a medium-sized Plan of Operations under the existing regulations. There is simply no
justification for making operators restart the process and reincur such large expenses.
Response: BLM has been persuaded by these and other arguments on the cutoff date for
exempting pending operations from portions of the regulations. The final regulations
provide for operations that have submitted a proposed Plan of Operations to BLM by the
effective date of the new regulations to operate under the Plan content and performance
standards of the old regulations.
- Comment: Keeping in mind BLM's preference for a process-based test, Newmont Gold
suggests that BLM grandfather all proposed Plans of Operations and proposed
modifications pending with BLM on the date the rule becomes final. This will not amount
to very many Plans. According to the draft EIS, about 200 Plans of Operations are
submitted each year. Assuming BLM's conclusion of 18 months from Plan submittal to a
final EIS, a draft EIS should take at most 12 months. Thus, if BLM lives up to assertions,
at most 200 Plans without draft EISs might be pending when the rule is finalized. This
amount compares with about 1000 Plan-level operations now on the public lands.
Grandfathering these 200 Plans would not, we submit, result in any undue impacts to the
public lands-particularly since there has never been any showing by BLM that the current
regulations are inadequate to protect the public lands. And to ensure that operators do
not take unfair advantage of such a rule, BLM could specify that applications that are
incomplete on their face would not be grandfathered.
Response: BLM has been persuaded by these and other arguments about the cutoff date
for exempting pending operations from portions of the regulations. The final regulations
allow operations that have submitted a substantially complete proposed Plan of Operations
to BLM by the effective date of the new regulations to operate under the Plan content and
performance standards of the old regulations.
- Comment: Section 3809.400. Proposed rules should not apply to existing or pending
Plans of Operations or modifications to such Plans. The proposed rules should not apply
to existing or pending Plans of Operations or modifications to such Plans. Mining
companies object to any retroactive application of the proposed rules. If it proceeds to
finalize the proposed rulemaking despite the extensive opposition, BLM must clearly
specify that where an operator has filed a Plan of Operations before the effective date of
the regulations, the operation and Plan are subject to the existing subpart 3809 rules. This
is particularly important where BLM already has pending Plans of Operations on file for
approval. BLM's delay in processing such Plans or accompanying NEPA documentation
should not penalize the operator.
Response: BLM has changed the proposed rule as suggested to specify that where a Plan
of Operations or modification is pending on the effective date of the final regulations, that
Plan would fall under the old Plan content requirements and performance standards,
including the old definition of unnecessary or undue degradation. But BLM believes it is
necessary that the new regulations on other administrative provisions such as bonding and
enforcement apply to all existing and future operations and that future modifications
incorporate the new performance standards to the degree practical as described in the
proposed final regulations 3809.433.
- Comment: The fundamental changes being proposed by BLM could trigger significant
added investment so that the Plan of Operations would conform to the revisions. The
revisions may prompt fundamental project design changes and the need to submit
substantially more information. Since the burden of the added requirements ultimately
rests on the operator, not BLM; the operator should be able to face the prospects of those
requirements with some degree of certainty.
Response: The proposed final regulations do not require operators with pending Plans of
Operations to submit more information to conform to the rules if they had submitted their
Plan of Operations to BLM before the effective date of the final regulations.
3809.401-Operator Information
- Comment: The rules must state clearly that the substitution of owners/operators in
connection with a Plan of Operations, no matter where in the process the Plan is (whether
pending, approved subject to pending modification, or fully approved), does not bring into
play the transition rules. It is a nonevent for purposes of grandfathering and transition.
The only issues relevant to the change of operator when mines are sold or operators are
changed is the determination that the new owner or operator is covered by the same or a
substituted financial assurance.
Response: BLM agrees with the comment that substitution of owners and/or operators in
connection with a Plan of Operations, no matter where in the process the Plan is (whether
pending, approved subject to pending modification, or fully approved), does not bring into
play the transition rules for Plans of Operations. BLM does not believe the regulations
need to specify all conditions under which they do not apply, just those under which they
would apply.
- Comment: Under existing Nevada laws and regulations, operators collect all the
information required by proposed 3809.401. As mentioned, such information is available
to BLM for review during the NEPA process. Thus, the most that most of the proposed
new application requirements would accomplish is to compel operators to expend
significant sums gathering such materials earlier than they do today, and then later having
to amend and repackage the materials as the NEPA process moves forward. BLM could
save resources for other activities by eliminating its proposal to increase the amount of
information operators must submit with plans of operation.
Response: While the regulations are more specific on the information BLM requires, it is
not much different from information many offices have been requiring under the existing
regulations. BLM needs this information for evaluating the Plan of Operations to
determine whether operations would cause unnecessary or undue degradation, and to
conduct the environmental analysis required by NEPA. Since the information is not
required in any particular format, applications prepared to meet state requirements could
be submitted to BLM to satisfy the pertinent information requirements in section
3809.401. The timing of the submission of this material could be worked out on a case-by-case basis, but the material would have to be provided early enough to support the Plan
review and NEPA analysis processes.
- Comment: There is no compelling need for BLM to obtain this volume and detail of
information at the beginning of its review process. Detailed engineering, management,
and monitoring plans are not essential to the NEPA analysis, particularly during its initial
scoping stages. Indeed, until BLM is fairly far along in the NEPA process, it cannot even
accurately gauge whether such detailed plans are in fact adequate. The final test of what is
or is not required and the level of detail can be finalized only after scoping has been
completed. In short, front loading the process will at best produce preliminary information
that would be of little value to BLM. In contrast, by submitting such information later,
operators need to make extensive and costly changes to Plan s in light of knowledge
gained during the NEPA process.
Response: The purpose of the information requirements is to obtain a Plan of Operations
that describes what the operator proposes to do in enough detail for BLM to evaluate
impacts and determine if the Plan will prevent unnecessary or undue degradation. The
required level of detail will vary greatly by both type of activity proposed and
environmental resources in the project area. On large EIS-level projects scoping may
actually start before a Plan of Operations is submitted through discussions with BLM staff
on the issues and level of detail expected. A certain level of detail is required to begin
public scoping. In the initial Plan submission the operator must determine what level of
detail to include in the Plan. BLM will then advise the operator if more detail is required,
concurrent with conducting the NEPA scoping process. By conducting the NEPA issue
identification process (scoping) concurrent with the Plan completeness review, both BLM
and the operator can determine the proper level of detail for the Plan of Operations.
- Comment: Plans of Operations 3809.401(b) require operators or mining claimants to
"demonstrate that the proposed operations would not result in unnecessary or undue
degradation of public lands." This required demonstration should be eliminated because it
shifts a burden to the operator to establish a negative. Coupled with the circular definition
of unnecessary or undue degradation in 3809.5, the burden is impossible to carry. The
proposed regulations conflict with FLPMA, 43 USC 1732(b). Under the current regime,
the "prudent operator" standard is an objective test that reconciles the right to mine under
the mining laws with the requirement to avoid unnecessary or undue degradation under
FLPMA.. This assertion of a burden to be placed on operators, along with BLM's
assertion earlier that it has discretion to deny Plans that do not prevent unnecessary or
undue degradation, is inconsistent with the statutory rights granted under the Mining Law.
The proposed rules abandon that objective standard in favor of a very subjective, even
arbitrary standard. The new standard is simply the requirement of every operator to
comply with whatever BLM imposes under these proposed regulations. This language
will allow any reviewing official to stonewall an operation until the claimant is forced to
give up. Small operations cannot afford to hire environmental analysts or other
professionals to soothe every concern that a reviewing official can come up with.
Response: This section merely articulates the current requirements. It has always been
incumbent upon the operator to produce a Plan that prevents unnecessary or undue
degradation. The Mining Law never provided for degradation beyond that necessary for
mining purposes. The operator does not have to prove a negative, but rather produce a
Plan of Operations that BLM believes would be successful in preventing unnecessary or
undue degradation of the public lands. This sentence has been moved in the proposed
final rule to section 3809.401(a) to describe the overall standard of review BLM will
require a Plan to meet in order to be approved.
- Comment: 3809.401 (b). Under what criteria should the operator be required to
establish the practices? The operator should be allowed to use standard engineering
practices. The operator and BLM should use only proven technology, that technology
that's engineered and proven under unnecessary or undue degradation (UUD) abilities.
Pilot programs or phase-in practices with a potential for preventing UUD should be
allowed as the project develops.
Response: BLM intends that the operator use equipment, devices, or practices that will
meet performance standards and prevent unnecessary or undue degradation, including
applying standard engineering practices and using proven technology. BLM also intends
that operations be allowed to test and develop new methods or techniques for pollution
prevention and reclamation. Where such test methods are applied, they would be
conducted at a smaller scale and be backed up with proven technology in the event of
failure.
- Comment: 3809.401 (b) (1). Requirement for SS# is not reasonably related to the
purposes of the proposed rule. How is a person's social security number reasonably
related to the purposes of the proposed rule? How will BLM use it? Federal statute that
created the Social Security system specifically prohibits the use of the social security
numbers for identification purposes outside of the authorizing statute. Social security
numbers should not be included in the requirements. A tax I.D., yes, but not a social
security number. What is BLM's authority for making this information a requirement of
the Notice or Plan? Will a Notice or Plan be rejected if this information is not given? For
a corporation, operators and thus I.D. numbers are constantly changed. This becomes a
reporting nightmare for a corporation and BLM in receiving, acknowledging, and filing
constant changes. A more reasonable requirement would be to require the corporate
operator to wear a corporate badge.
Response: The purpose of the requirement is for BLM to be able to determine the
operator responsible for both the operation and site reclamation. The term has been
changed to require a taxpayer identification number as suggested. A Notice or Plan would
not be considered complete without enough information to identify the responsible
operator. If a corporation is the operator, it should provide the corporate identification
number. Persons working for a corporation do not have to provide individual
identification or wear badges.
3809.401-Description of Operations
- Comment: These proposals have the potential to increase the time required to get a
permit by years. The process is now bogged down so that approval of Plans can take
forever. Adding this layer of proposals will further delay time and increase costs as well
as create a tremendous workload for BLM.
Response: The requirements for Plans of Operations essentially put into regulation the
process that most BLM field offices are implementing. By describing these requirements
in the regulations BLM intends to improve consistency among field offices and give
operators more precise information on what is expected from them. The time it takes to
process a Plan under these regulations is related more to the amount of other workloads
and staffing expertise than to a change in the Plan content requirements.
- Comment: The Carlota Final EIS largely ignored the historic record in extensive sections
presenting mitigation and design schemes, etc., thereby not addressing the proven
effectiveness of the proposals. Such situations should be avoided. Your EIS, for example,
in the discussion of pit lakes, addresses the track record objectively. BLM should require
all Plans of Operations, EISs, etc. to include an effectiveness assessment that shows how
well proposals have worked, where, under what conditions, and for how long. If
proposals are untested or experimental, they should be so labeled.
Response: Guidance on topics BLM should include in its environmental analysis of a Plan
of Operations is more suitable for agency policy documents or handbooks, and is not
detailed in these regulations.
- Comment: This and the next section are the most important sections of the reformed
regulations. The description of operations requires only "preliminary designs,..." ((2)(I)).
Preliminary implies the Plans are not final. Does BLM propose to approve Plans that are
not final?
Response: Many Plans of Operations present preliminary or conceptual designs for mine
facilities that must eventually be highly engineered before construction. During its review,
BLM typically requests information about such facilities to ascertain location, size, general
construction, operation, environmental safeguards, and reclamation. The level of detail
required is highly variable and site specific, but must be great enough so that the agency
can evaluate whether the facility is going to result in unnecessary or undue degradation.
An approved Plan of Operations allows the facility to be built within the parameters
outlined in such preliminary designs. Since operators may be uncertain as to BLM's
decision, they may wait until BLM issues its approval before committing the resources for
preparing detailed final engineering drawings and specifications. For example, an operator
may propose a tailing impoundment of a certain size and location, but the environmental
analysis is evaluating several alternative locations or disposal methods. In this case, there
is no point in the operator's preparing final designs for an impoundment that may never be
built. Once the preferred alternative is selected, the Plan of Operations approval decision
could then require the operator to submit final approved engineering designs (and later
"as-built" reports) to verify that the Plan of Operations, as approved, would be followed.
Section 411(d)(2) had been added to clarify this process.
- Comment: 3809.401(b)(2) is overly detailed, requiring extensive description of
operations while still in the planning process. The current process is to try to avoid
continual amendments to the Plan of Operations. But under these proposed regulations
any changes (and many could be needed) to the description of operations would require
plan modifications. BLM does not need this level of information at this juncture to carry
out its surface management responsibilities. BLM should require only information
sufficient to allow evaluation of impacts from the proposed operation. Extensive
descriptions of the mining of multiple sites within one major mining operation due to
variation of grade content or industrial material needs become vary complex, redundant,
and of minimum administrative benefit, especially when they all constitute similar mining
activities.
Response: Operations that are still in the "planning process" may not be ready to submit
a Plan of Operations to BLM. For BLM to properly review a Plan of Operations,
operators must give BLM a description of what they are proposing. This description must
contain enough detail so that BLM can conduct the analysis required under NEPA,
ascertain whether the Plan of Operations would prevent unnecessary or undue
degradation, and develop any mitigation that may be needed to prevent unnecessary or
undue degradation.
- Comment: Some level of information is needed, but it is not necessary to require the
same scope and level of detail for small operations as for large operations.
Response: BLM agrees. The level of detail will be based on the site-specific operation
proposed and the geographic location. The performance standards under the Proposed
Action are standards by which the operation will be measured. BLM will not dictate the
methods and operational activities carried out by industry. Only the results of the methods
will be evaluated by the standards. Therefore, the level of detail needed to complete the
permitting process and meet the standards will depend on the natural resources at the
mining site. BLM does not intend to require extensive resource data unless the data is
needed to make a reasoned decision and to measure the operations by the standards
outlined. The level of detail will be based on the operation proposed and the potential
natural resources affected. But if a small operation potentially affects a significant
resource, the level of detail could be substantial.
- Comment: If obtaining the detailed information in Section 3809.401(b)(2) requires more
exploration work, many exploration targets may never be explored because of the time
and expense of detailed exploration work, especially considering the proposed new
requirements that will impose more costs and add considerable approval time to
exploration projects on federal lands.
Response: The information required for a Plan of Operations would not substantially
change over current practices under the existing regulations. The exploration work
mentioned should be occurring, independent of any BLM requirements, to make sound
technical and financial decisions on whether an economic deposit is present and to
evaluate how it might be developed.
- Comment: These sections of the proposed regulations should be revised to make it clear
that the requirements of 3809.401 apply to a final Plan and to acknowledge that all
elements will not be completed until after the NEPA and permitting processes are
complete. BLM officials in the field should be given clear authority to adjust the level of
detail required in the proposed Plan to reflect the timing and circumstances of each
operation. The regulations should also allow conditional approval of the Plan (as is
common now) pending completion of certain requirements. For example, a Plan might be
approved contingent on submission of a final monitoring plan with a NPDES permit or a
mitigation plan in connection with a 404 permit.
Response: The requirements of 3809.401(b) apply to proposed Plans of Operations. If
the requirements apply and the Plan submission has addressed each element, then the Plan
is deemed complete, meaning BLM has a complete description of the proposed action, and
the NEPA process can continue. After completion of the NEPA process, BLM may issue
a decision approving the Plan of Operations subject to any changes or conditions needed
to prevent unnecessary or undue degradation. Section 401(d)(2) has been added to clarify
where BLM might issue a conditional approval subject to inclusion of other agency
permits into your Plan of Operations.
- Comment: Plans of Operations BLM's proposed regulations require that an operator
deliver a complete Plan of Operations as a finished product before BLM will begin its
review of the proposal. Proposed 43 CFR 3809.411(a). With respect to timing, the
proposed regulations create significant confusion as to when a Plan must be deemed
"complete," and fail to reflect current practice, which is working effectively. Proposed
3809.401 describes the information needed for a complete Plan. Proposed 3809.411(a)
provides that BLM will review the Plan and may notify the operator that the submittal
does not contain a complete description of the Plan under 3809.401. These two proposed
rules can be read to impose a requirement that a Plan of Operations meet all of the content
requirements of 3809.401 before BLM will begin processing the Plan. The proposed rule
appears to be failing to distinguish between the requirements for an application for a Plan
of Operations and a completed Plan of Operations.
Response: BLM starts the NEPA process as soon as a Plan of Operations is submitted,
sometimes even sooner if operators wish to consult with BLM as they are preparing their
Plans. The regulations describe the contents of a proposed Plan of Operations for it to be
considered "complete." A complete Plan constitutes the proposed action of the NEPA
document. The final, or approved, Plan is what results when the NEPA analysis is
complete and BLM issues an approval decision.
- Comment: 401(b)(2) Description of Operations: We question what BLM envisions in
engineering design, water management, and quality assurance plans. Does BLM have staff
members who can review this type of information.
Response: The level of detail for these specific plans will vary depending upon the type
of operation being proposed, the local environmental setting, and the issues of concern.
Often what you provide for an analogous state requirement would be adequate. BLM
encourages you to consult with your local BLM office to determine how best to satisfy
these requirements. BLM does employ mining engineers, geologists, hydrologists, and
other natural resource staff that can evaluate this information. BLM also coordinates its
reviews with other state or federal agencies who have expertise in these areas.
- Comment: 3809.401(b)(2) What types of plans are being referred to? What is
considered rock? What is considered rock handling? BLM requirements for
characterizing rock should be clearly stated. What rock should the operator characterize?
What is quality assurance? The state typically requires quality assurance plans for some
parts of large mining operations. We do not require them for everything, nor do we
require them for any operation at most smaller mines. We do not know what is being
requested here. Is it quality assurance plans for construction of building, liners, dams, ore
assays, or water quality sampling?
Response: Definitions for common terms such as "rock" are found in many standard and
geological dictionaries. As used in the regulations, "rock" refers to materials such as
overburden or waste rock and ore that would be excavated. "Rock handling" refers to
plans for how this material will be characterized and handled or placed in order to mitigate
its potential to generate acid rock drainage (ARD) or other leachate. What is required for
rock characterization and material handling plans is highly site specific, depending upon
the risk of ARD generation and the other resources in the area of operations that are
potentially affected. Since material characterization can be both time consuming and
costly, consultation between BLM, the state, and the operator on the needed level of
characterization is recommended early in the Plan review process. "Quality assurance
plans" are plans or programs for monitoring and testing mining and reclamation
components during construction. They are needed where performance highly depends on
proper construction or installation as specified in the approved plans. Examples include
earthen compaction for tailing dams or soil liners, synthetic liner installation, and placing
specified thicknesses of growth medium for revegetation. Specific quality control plans
are of developed under overall quality assurance programs.
- Comment: BLM proposes to substantially revise both the requirements for filing and the
content of proposed Plans of Operations. Proposed 3809.401. The proposed
requirements do not differ materially from the typical contents of a final Plan of
Operations for a large, modern mining project. We have three important concerns about
the proposed requirements, however. The first is that the regulations are written for very
large, complex mining operations, but will applied to all activities conducted under a Plan,
even exploration. In the context of a smaller operation or an exploration project, some of
the proposed requirements just do not make sense (e.g. water management plans, rock
characterization, and handling plans). But BLM must require them or determine that the
requirements do not apply. The second major concern relates to timing. The proposed
regulations do not clearly specify when a Plan of Operations needs to be complete. The
third major problem flows from the requirement in proposed 3809.411(c)(1) that BLM
disapprove a Plan that does not meet the content requirements.
Response: BLM does not have to make a specific determination that each element of
Section 3809.401(b) applies. Rather, BLM simply has to determine that the Plan
describes the proposed activity in enough detail for BLM to analyze the Plan's potential
impacts and give the operator a written list of items that are missing or incomplete. The
sequence described in 3809.411 is that the Plan of Operations has to be complete before
BLM completes the environmental review required by NEPA and any other consultations
required by other laws or regulations. This means that the Plan must be complete before
BLM can produce an environmental assessment or a draft EIS for public comment. This
does not mean BLM will not start the NEPA process before receiving a complete Plan. In
fact, conducting NEPA scoping concurrent with review of the initial Plan of Operations
submission helps BLM and the operator focus the completeness review on issues of
concern. But BLM obviously cannot approve a Plan if the Plan lacks enough detail for
BLM to evaluate its impacts. An incomplete Plan is one example where BLM would
withhold approval until it has received and evaluated the information.
- Comment: Section 3809.401(b)(2)(viii) requires the operator to describe fully in the Plan
of Operations plans for all access roads, water supply pipelines, and power and utility
services. This requirement is too prescriptive. Supplying preliminary site layout drawings
(rather than detailed layouts) gives BLM the information to assess unnecessary or undue
degradation and gives the operator the flexibility and latitude to complete the final design.
Response: The level of detail required is highly site specific. Section 3809.401(b) has
been revised to state that the level of detail must be sufficient for BLM to determine if the
Plan of Operations would result in unnecessary or undue degradation.
- Comment: Plans of Operations Water Management Plans. Within Alaska, discharges
into surface and ground water are regulated by the EPA and Alaska Department of
Environmental Conservation (DEC). EPA regulates storm water management. We are
unclear what is asked of the operator under the water management requirement listed in
this section. If it is only to provide information already required by EPA and DEC, then
that should be clear. If this is a different and new requirement, we understand neither
what is being required, how BLM would regulate it, or how it will be coordinated with
EPA and DEC.
Response: Water management plans are plans for managing storm water, mine drainage,
or processing solutions. Such information may already be required by other federal or
state agencies. Review of water management plans would be coordinated between BLM
and these other agencies according to local practice and interagency agreements such as
memorandums of understanding.
- Comment: Plans of Operations EPA has delegated the regulation of surface water under
the Clean Water Act and ground water is regulated under state law. In Nevada, a
Monitoring Plan is part of the Water Pollution Control Permit. This requirement is
redundant and unnecessary.
Response: BLM does not intend to regulate water quality in duplication with state or
other federal agencies. Rather BLM must consider how mining and reclamation affect
water quality and how certain operating or reclamation practices may be conducted to
reduce or eliminate potential impacts to water resources on its lands. The monitoring of
water quality or quantity is one way to evaluate the performance of mining operations and
the success of reclamation measures.
- Comment: Plans of Operations, Section 3809.401(b)(2). BLM specifies several types of
plans that must be submitted with Plan of Operations, such as water management plans,
waste rock management plans, and spill contingency plans. These plans are usually
developed with the states while the Plan of Operations is being reviewed and approved.
EPA has delegated authority for these programs to the states. It may not be possible to
include these plans with Plans of Operations; nor would BLM have the approval authority
under federal regulations.
Response: Being able to consider these plans is critical in determining whether the
proposed Plan of Operations would prevent unnecessary or undue degradation.
Furthermore, such plans may of themselves call for building certain facilities on BLM
lands, such as monitoring wells, capture ponds, access roads, or storm water diversions,
and therefore must be given to BLM as part of the overall Plan of Operations in order to
get such facilities approved.
- Comment: Plans of Operations Spill Contingency Plans. The state and EPA require spill
contingency plans. We do not know what is requested here other than to meet the existing
requirements of those agencies. If that is requested, it should be so stated and coordinated
with the other agencies. If BLM is proposing something different from those
requirements, we are concerned about duplicative agency jurisdiction. This is an excessive
requirement that would fall under NEPA anyway, and the operator would not get an
operating plan without it.
Response: NEPA compliance is a procedural requirement and does not require spill
contingency plans. BLM can also require spill contingency plans to protect public land.
Spill contingency plans provided to meet state or other federal requirements would also
likely be adequate for BLM purposes. BLM would review such plans as part of the
overall Plan of Operations review in coordination with other agencies.
- Comment: Insofar as BLM has determined that is lacks adequate information on any
relevant aspect of a Plan of Operations, BLM not only can require the filing of
supplemental information, it is obligated to do so. We emphatically reject any suggestion
that BLM must limit its consideration of any aspect of a Plan of Operations to the
information or data that a claimant chooses to provide.
Response: BLM requires enough information to evaluate the performance of a Plan of
Operations for preventing unnecessary or undue degradation. The information
requirements listed under proposed 3809.401(b) are not exhaustive. Proposed section
3809.401(c)(1) requires information for completing the NEPA process, and proposed
section 3809.401(c)(2) gives BLM the option of deciding that more information is
required than is listed in the previous sections.
- Comment: Plans of Operations 3809.401 (b) Required Information The implication of
this section is that BLM may require that an EIS be prepared for a mineral exploration
program. I'm sure that such a requirement is not contemplated in the intent of the Federal
Land Policy and Management Act (FLPMA). As with the previous section, this section
must be modified to acknowledge the distinction between different stages and scales of
operations in accordance with FLPMA.
Response: The level of analysis (EA or EIS) is determined by the potential for the Plan of
Operations to cause significant impacts and not necessarily by whether the activity
proposed is exploration or mining. This determination is guided by the regulations for
implementing the National Environmental Policy Act (NEPA) found at 40 CFR 1500,
et.seq. BLM approval of a Plan of Operations under the 43 CFR 3809 regulations is a
federal action. As such it is subject to the NEPA regulations. These regulations require
the preparing of an EIS for actions causing significant impacts. Environmental
assessments (EAs) can be prepared for approval of actions that do not cause significant
impacts. While most exploration does not present the potential for significant impacts, a
particular exploration project could still cause significant impacts. In that case an EIS
would have to be prepared.
- Comment: Plans of Operations Section 3809.401 (b) 2. There must be some sort of
minimal documentation for a beginning operation. My claim has not been surveyed. We
have not taken core samples. We do not know the scope of the deposit. The minimal
documentation level must be in the regulations and not left to the opinion of the local
reviewer.
Response: The amount of information required in a Plan of Operations depends upon
what you propose to do. The drilling and reclaiming of a single exploration hole could be
presented on one or two pages, whereas large-scale mining may require thousands of
pages of information to describe completely. Call you local BLM office for guidance on
the level of detail it believes is needed for your particular project.
3809.401-Reclamation Plan
- Comment: Plans of Operations The exact timing of each of the plans may vary by the
type of operation, the location (both state and BLM district), interests of other federal
agencies, and issues raised in the NEPA process. A reclamation plan may follow a similar
path. An operator may first propose facilities with a particular layout. BLM (through the
NEPA process or otherwise) may consider alternative locations. The operator or other
agencies may suggest alternative locations. Reclamation techniques are likely to be
considered for each facility at each location, but at a relatively general level of detail. It
makes no sense to require a reclamation plan with a "detailed description of the
equipment, devices, or practices" to be used until the final location of the facilities is
determined. Similarly, of course, it makes no sense to require a detailed reclamation cost
estimate until the final reclamation plan is set.
Response: Operators must present reclamation plans that they believe will meet the
requirements of the regulations. The reclamation plan, as part of the Plan of Operations,
is then analyzed in the NEPA process to determine its effectiveness. To analyze the plan a
certain level of detail is needed up front. Final approval of the Plan of Operations may
require the reclamation plan to be conditioned or modified as needed to prevent
unnecessary or undue degradation. Section 3809.401(d) is worded so as not to require
the reclamation cost estimate until later in the process when there is more certainty about
what will be the final approved reclamation plan.
- Comment: Plans of Operations 3809.401(b)(3) require a suitable level of detail for
reclamation plans. The proposed language should be amended to read: "Reclamation Plan.
A plan for reclamation must meet the standards in section 3809.420." The other language
in 3809.401(b)(3) should be deleted because it is not needed and creates potential conflicts
between provisions. If the performance standards are met, a detailed description of
reclamation equipment, devices, and practices are not needed, especially this early in the
planning stage.
Response: The word "detailed" has been removed from the first section of this sentence.
But the requirement is still to provide enough of a description on "how" the performance
standards will be met that BLM can evaluate whether the reclamation plan is feasible and
will achieve the desired outcome.
- Comment: Plans of Operations 401(b)(3) Reclamation Plan: The term "riparian
restoration" has a meaning different from reclamation. We do not understand the term
"deleterious material" because it is not defined.
Response: The term "riparian restoration" is not used in 3809.401(b)(3). The term used
is "riparian mitigation," which refers to plans for meeting the performance standard under
proposed 3809.420(b)(3)(ii) for returning disturbed riparian areas to proper functioning
conditions. "Deleterious material" is material with the potential to cause deleterious
effects if not properly handled. Deleterious material could include material that generates
contaminated leachate, is toxic to vegetation, or threatens wildlife or human health. The
term is more inclusive than material with the potential to produce acid rock drainage.
- Comment: Plans of Operations 3809.401(b)(3) The list in this section is too vague,
especially in the "among other things." BLM requires the plan to be complete but how
can an operator provide a complete plan if there is not a complete list of requirements.
Response: The exact details of what must be in a reclamation plan is highly project
specific and site specific. If the Plan of Operations does not involve drilling then a
reclamation plan for drillhole plugging is not needed. If the Plan of Operations does not
involve disturbance in a riparian area then obviously a riparian mitigation plan is not
needed. The operator must consider what activity they want to conduct and where, and
then propose a reclamation plan for that activity that will meet the performance standards.
- Comment: Plans of Operations What standards are being applied and how does the
operator plug a drill hole? Define regrading and under what situations regrading would be
required. Will BLM consider a project's unnecessary or undue degradation plan if the plan
proves that the riparian areas are improved after the project? This would meet the
requirement for no net loss. Referring to: "...the reclamation plan might also contain
information related to other topics." What data collection is needed? Please specify in
detail the types of data. It appears that an operator will need to have a Plan of Operations
for a baseline study.
Response: Plugging requirements for drill holes vary by hole depth, aquifers encountered,
water inflow, and artesian pressures. Regrading is moving excavated material to create a
surface suitable for further reclamation. Plans that improve riparian areas would meet the
performance standard in proposed section 3809.420. The quote on other information is
not in the section on reclamation plans, but the list is not exhaustive, and other topics may
have to be addressed by a reclamation plan if relevant. On large or complex projects it is
not unusual for the operator to present a plan for collection of baseline information to
BLM for review and comment.
- Comment: The proposed rule also goes much further in the amount of reclamation
planning required before the NEPA process begins. Operators submitting proposed Plans
of Operations now must simply describe measures they will take to reclaim disturbed
lands. The proposed regulations, in contrast, require an operator to submit a detailed
reclamation plan that must include plans for the following: (1) drill-hole plugging; (2)
regrading and reshaping; (3) mine reclamation; (4) riparian mitigation; (5) wildlife habitat
rehabilitation; (6) topsoil handling; (7) revegetation; (8) isolation and control of acid, toxic
or deleterious materials; (9) facilities removal; and (10) post-closure management.
Response: This is no change from what operators currently should be doing. Measures
to reclaim disturbed lands under the current regulations should include all applicable
elements of the proposed regulations you have listed. One reason new regulations are
needed is to clarify what operators are currently expected to provide.
- Comment: Plans of Operations. Revise .401(b) by deleting (3)(iv) and merge with (3)(v)
because riparian in only one habitat type found on federal land. This special identification
is unsuitable when BLM has presented no authority to require "mitigation" for
nonjurisdictional wetlands or riparian habitat unless the project area is in a congressionally
designated unit or non-congressionally designated unit where nonjurisdictional wetlands
and riparian habitat are expressly listed and perhaps where BLM has a completed land use
plan that shows the area for the proposed mining operation to be within an area of critical
environmental concern (ACEC) that clearly names the resources to be protected and the
mineral values lost on the same scientific basis.
Response: Under FLPMA, BLM has the authority to require mitigation of impacts to
resources on the lands it manages. The authority for requiring mitigation of impacts to
riparian areas is no different than that for any other type of habitat. But riparian habitat
generally has greater biological diversity and hence higher resource values, making it
suitable for individual consideration in the regulations.
- Comment: Plans of Operations Revise .401(b)(3)(v) to assure that it includes all wildlife
habitat to explain what is meant by the term "rehabilitation." Or better yet, reference a
definition in 3809.5. Assure that BLM and the Forest Service are using the same
definitions and standards.
Response: Rehabilitation means to create usable and functioning wildlife habitat from a
disturbed area, including all types of wildlife habitat. Although it may not be practical to
recreate the same type of wildlife habitat that was disturbed, the area itself has to be
suitable wildlife habitat. BLM cannot change the Forest Service surface management
regulations. The scope of this rulemaking is limited to BLM regulations.
- Comment: Plans of Operations. Revise .401(b)(3)(v) to accept as a proper identification
of wildlife habitat that has been described in the approved BLM or Forest Service (FS)
land use plan for the project area. The existing wildlife habitat described in the approved
BLM or FS land use plan also becomes the baseline datum for considering the extent to
which the proposed project will or will not modify wildlife habitat and whether the
modification will benefit or harm the existing wildlife habitat.
Response: BLM encourages the use of land use planning information to help operators in
the baseline characterization of wildlife habitat or other resources and to help develop
mitigation plans. But information in land use plans is often collected at a broad scale and
may not give enough detail about the project area's resources. Supplemental studies are
often needed to support mining-level project approvals.
- Comment: Plans of Operations. Revise .401(c)(3)(v) by modifying wildlife habitat to be
only those expressly identified as an ACEC where existing and reasonably projected future
mineral values have been professionally evaluated or in a congressionally designated
special management area for a particular individual or group of wildlife species.
Response: Significant wildlife habitat values exist on BLM-managed public lands both
within and outside special management areas. Limiting rehabilitation of wildlife habitat to
those special areas is not in the public interest because it would create significant impacts
to wildlife on other lands and these impacts can be readily mitigated by most operations.
3809.401-Monitoring Plan
- Comment: Plans of Operations It is not practical or useful for an operator to design and
submit a detailed water quality monitoring plan before discharge permit outfall locations
have been selected and approved by state water quality permitting authorities. Similarly,
plans for riparian mitigation, wildlife habitat rehabilitation, and facilities removal serve no
purpose at this stage of review of the Plan of Operations. Certain elements of the Plan of
Operations must remain fluid during the review and permitting process and can be
finalized only after BLM has competed that review. Proposed 3809.401(b)(4) describes in
great detail the content of a monitoring plan. Typically, a monitoring plan is not finalized
until after the Plan of Operations has been through the NEPA process and key state
environmental permits have been obtained. In fact, air, and water quality monitoring
points are typically determined through the state permitting processes and named in the
permits. Those permits are issued with specific monitoring requirements, and then those
monitoring requirements are incorporated into the Plan of Operations. Other components
of Plans of Operations, including water management plans, rock characterization and
handling plans, quality assurance plans, spill contingency plans and reclamation plans, are
also developed and refined as the permitting process moves forward. The exact timing of
each of the plans may vary by the type of operation, location (both state and BLM
district), interest of other federal agencies, and issues raised in the NEPA process.
Response: The comment is correct in that certain portions of the Plan of Operations are
expected to change as a result of the NEPA process. But BLM requires information on all
aspects of the Plan, including monitoring programs, to determine if they will prevent
unnecessary or undue degradation. This means basic information is required up front on
what resources will be monitored, where and how, and what corrective measures would
be triggered. The purpose of the NEPA process is to find shortcomings in such plans and
develop corrective measure (mitigation) in those plans. BLM does not agree that
development of monitoring programs should be deferred until after the Plan of Operations
has been through NEPA analysis. A monitoring program, tied to corrective action
triggers, can serve to mitigate many environmental impact concerns and should be
developed simultaneously with the EIS alternatives and the Plan of Operations.
- Comment: Plans of Operations. 3809.401(b)(4) governing monitoring plans is also too
detailed, requiring very specific items that must be included, rather than encouraging the
tailoring of the monitoring plan to site-specific conditions. The wildlife mortality
provision should be limited to mortality resulting directly from operations and to specific
species of concern (e.g. specified threatened or endangered species, migratory birds), and
BLM should defer to monitoring plans developed for and approved by other agencies
under federal and state programs (e.g., water quality or wildlife).
Response: The monitoring plan requirement described in proposed 3809.401(b)(4) uses
terms like "where applicable," "may be necessary," and "monitoring the effect on your
operation." Such language reflects that BLM expects monitoring plans to be tailored to
site-specific conditions. If an operation even warrants monitoring for wildlife mortality in
the first place, the monitoring plan would be developed around the specific wildlife
concern. For example, the issue at one operation may be wildlife mortality from vehicles.
At another operation the issue may be waterfowl mortality on a tailings impoundment.
Each operations monitoring plan would target the mine facilities and wildlife of concern.
BLM encourages operators to incorporate monitoring plans developed to meet other
federal or state agencies requirements in order to eliminated duplication, and expects that
these plans would most likely satisfy BLM requirements. But BLM would not
automatically defer to such plans unless interagency agreements were in place.
- Comment: Plans of Operations. Monitoring plans should include provisions to expand
the monitoring as impacts are observed. Mining often occupies geologically complex
regions. The monitoring plan must provide for changes if conditions warrant. BLM must
be able to expand the area and density of monitoring systems. For example, aquifer
systems often have many fracture layers. It is essential to adequately monitor each layer.
It may not be possible to determine the location and depth of each system in advance of
writing the monitoring plan for the Plan of Operations. The regulations should reflect
BLM's need to require expanded monitoring. Cost should not be a concern.
Response: Expanded or extended monitoring is one of the standard responses to adverse
monitoring results and would, therefore, be part of most operations' monitoring plans.
Furthermore, BLM could require expanded monitoring under proposed sections
3809.431(b) and 3809.601(a).
- Comment: Plans of Operations. 401(b)(4) Monitoring Plan: Requiring a detailed
monitoring plan duplicates this state's requirements and attempts to give BLM authority
to regulate water and air quality. BLM simply does not have the delegated authority to
regulate water and air quality under the Clean Water Act and Clean Air Act.
Response: A monitoring plan provided to meet state requirements would most likely
meet BLM requirements, depending on the resource to be monitored. Proposed section
3809.401(b)(4) has been revised to encourage operators to incorporate other monitoring
program requirements. States regulate water quality and air quality by monitoring
discharge levels and comparing them to a state standard to determine compliance. BLM
does not regulate water or air quality but mining that might affect these resources. To
evaluate the performance of mining waste units and the effectiveness of mitigation, it is
important to have the feedback that monitoring gives. Requiring monitoring plans does
not give BLM any more authority than it already has under FLPMA to prevent
unnecessary or undue degradation.
- Comment: Plans of Operations. The discussion of monitoring plans should recognize
explicitly that such plans may be required under other federal and state environmental
programs and provide that BLM will adopt and incorporate those plans by reference
without a duplicative review.
Response: Proposed section 3809.401(b)(4) has been revised to encourage operators to
incorporate other monitoring program requirements. But it is not necessarily a given that
such programs would cover the entire range of BLM's concerns and need for monitoring.
Unless specific memorandums of understanding (MOUs) are in place deferring to other
state or federal agency monitoring requirements, BLM reserves the right to require more
or supplemental monitoring as needed to prevent unnecessary or undue degradation.
- Comment: Plans of Operations. 3809.401 (401) Monitoring plan-requires that the
operator specify a monitoring plan; this has historically been BLM's responsibility and
BLM's abdication thereof places an onerous burden on the operator.
Response: Though the operator first proposes a monitoring program, it is BLM's
responsibility to review and approve the monitoring programs as adequate. BLM must
also review data collected by monitoring programs and make determinations on operator
compliance with the Notice or approved Plan of Operations, in cooperation with the
states. BLM does not feel that it is an unfair burden to require operators to collect
monitoring data on their operations. Nor is this a change from current practices.
- Comment: Environmental monitoring can be a good thing if there have been complaints
or if there is the possibility of environmental hazard. To require environmental monitoring
on all operations on the Notice and Plan level would create a mountain of paperwork and
backlog of samples that show nothing and would be expensive to acquire. The percentage
of mining operations that have any pollution problems, especially at the Notice level, must
be extremely small. Small operations cannot economially be expected to collect this kind
of data. We are not trained in this field.
Response: The detail and complexity of monitoring programs depend on the type of
operation and the environmental resources potentially affected. Small operations would
require small monitoring programs. Exploration programs may not need monitoring
programs beyond visual inspection.
- Comment: Plans of Operations Monitoring - In many situations monitoring is a
requirement under NEPA. Monitoring in and of itself is not mitigation. Monitoring with
action levels defined and followup described is necessary. (for example if monitoring of
ground water exceeds Safe Drinking Water Act standards, a plan for treatment and/or
stopping further degradation is required. Same for air issues.
Response: You are correct. Monitoring by itself is not mitigation. That is why the
monitoring plans required under 3809.401(b)(4) must include a description of the
response actions that would be triggered by adverse monitoring results.
- Comment: I come under a Plan of Operations. I've recently done some reclamation, but
I notice that you want a monitoring plan now. This monitoring plan would require air
quality monitoring, noise levels, and wildlife mortality. I don't know why BLM is
requiring all this except as harassment. I don't think any of it is needed. In the mine area
you're going to alter the environment. That's all there is to it. Until you reclaim
afterwards and the area goes through its natural stages of ecological succession, nothing is
going to happen. You are going to change the wildlife there, and I don't know why you're
monitoring.
Response: One of the purposes of monitoring is to watch for offsite impacts that may
constitute unnecessary or undue degradation.
3809.401-Baseline Data
- Comment: Plans of Operations. 3809.401(c)(1) addresses BLM's ability to request
information on nonpublic lands. This provision should be deleted because it gives the
mistaken impression that BLM has, outside the NEPA process, the authority to require
such information. This provision does not provide any guidance on the purposes for which
BLM could need such information to "analyze""a Plan of Operations, and suggests that
BLM may intend to regulate "nonpublic lands" under this provision.
Response: The provision is tied to the NEPA process as stated in 3809.401(c)(1).
Guidance on how information is used in the NEPA process is available in the CEQ
regulations for implementing NEPA (40 CFR 1500, et. seq.) and in agency handbooks.
BLM has no regulatory authority over private lands. Section 3809.2(d) has been added to
make this clear. But the scope of environmental analysis required by NEPA is to describe
the environmental effects on all lands, even though BLM is only issuing an approval action
for the public lands portion of a project.
- Comment: Plans of Operations. 3809.401(c) The all-encompassing nature of data
requirements under NEPA is being cited as a component of 3809. By referencing NEPA
requirements in 3809, BLM is attempting to use NEPA authority to regulate mining.
NEPA is intended to be an analysis and disclosure process, not a regulatory device.
Response: You are correct. NEPA compliance is a procedural requirement and does not
set substantive requirements that operators must achieve. But the NEPA regulations do
require BLM to describe impacts to all resources, including those over which BLM may
not have regulatory authority or where BLM shares regulatory authority with other
agencies.
- Comment: Plans of Operations. The proposed rule authorizes BLM to require operators
to submit operational and baseline environmental information. BLM may also require
"static and kinetic testing to characterize the potential for...operations to produce acid
drainage," as well as the submission of any other materials needed to ensure that
operations comply with the regulations. These proposed requirements would impose
substantial additional burdens on operators. The added burdens are especially troubling
given the lack of any demonstrable need for new application requirements. Operators
already provide the information that would be collected under BLM's proposed rule to
states and other federal agencies. After a proposed Plan is given to BLM, BLM still has
ample time to incorporate the information into its decision making process. In fact,
gathering and submitting the information later in the plan approval process results in
substantial cost savings to the operator without any prejudice to BLM.
Response: As the commenter correctly points out, the information requested by the
proposed rule is already being collected to meet state and federal requirements. It is
therefore unclear how the proposed rule would constitute a "substantial additional burdens
on operators." The regulations merely lists the types of information BLM has been
requiring from operators under the existing regulations to provide for a more standardized
approach and inform operators in advance of the information requirements.
- Comment: What is the need for baseline environmental data for a moderate to large
exploration project?
Response: Any Plan of Operations approval requires the preparing of an environmental
analysis under NEPA. Depending upon the specifics of the exploration project and its
location, baseline data may be needed for the NEPA analysis.
- Comment: BLM has no authority to adopt a requirement with the all-inclusive language
of 3809.401(c)(2) allowing BLM to request any other information it desires to comply
with the subpart. It seems that BLM could define what information it requires in the Plan
of Operations to prevent unnecessary or undue degradation. As such, this information
should be included in the proposed regulations as a clear and concise checklist. BLM
should not have the authority to make unlimited requests for any information it feels
would be supportive of a Plan of Operations.
Response: Due to the wide variety of environmental settings where mining occurs, the
range of mineral commodities of interest, and the variations in mining and reclamation
technologies, BLM cannot list all potential information needs. Operators who feel that a
specific BLM information request is not warranted can question the request or, as a last
resort, use the appeal process in proposed 3809.800.
- Comment: The proposed language of section 401(c) is inconsistent with NRC (1999)
study Recommendations 14 and 15.
Response: NRC Recommendation 14 discusses planning to assure proper postclosure
management of mine sites. Recommendation 15 discusses guidance manual preparation on
BLM's authority to protect resources not protected by other environmental laws.
Requiring baseline operation and resource information under proposed 3809 401(c)
presents no conflict with these recommendations a |