RMP Schedule
(tentative and subject to revision--updated February 2013)
2008 - Scoping
- Inventory and assemble existing data
- Public comment analysis/summary
- Analysis of the management situation
2009 - Analysis of the management situation
- Travel management - route evaluation
- Alternative development
2010 - 2012 - Internal review of alternatives
- Prepare preliminary draft RMP/EIS for internal review
- Incorporate new guidance addressing sage-grouse into draft RMP/EIS
- Prepare preliminary draft RMP/EIS for internal review
- Internal review of draft RMP/EIS
2013 - Distribute Draft RMP, hold public comment meetings
- Refine alternatives and effects based upon review of public comments
- Incorporate public comments into and prepare Proposed RMP/Final EIS
2014 - Incorporate public comments into and prepare Proposed RMP/Final EIS
- Distribute proposed RMP/Final EIS
- Protest period and governor's consistency review
- Issue approved RMP and record of decision
|