Jarbidge Resource Management Plan RevisionRMP Home | Why is this Plan Being Prepared? | Planning Process | How to get Involved and Comment | Public Meetings | News & Newsletters | Federal Register Notices | Planning Documents | Photos
Planning Process| Process | Date | | Notice of Intent published in the Federal Register | January 10, 2006 | | Public scoping period | January 10 - June 15, 2006 | | Public scoping meetings | May 16, 18, 23 & 24, 2006 | | Scoping Summary Report | September 28, 2006 | | Formulate alternatives and prepare draft RMP/EIS | 2007-2010 | | Draft RMP/EIS with plan alternatives available for 150-day public review and comment | September 3, 2010 | | Prepare final EIS and proposed RMP | | | Proposed RMP/final EIS available for 30-day public review and protest period | | | Resolve protests | | | Record of Decision and approved RMP signed | |
|