Timeline for the RMP Revision (text version)

RMP Home | Area Photo Tour | RMP Process | Community Based Planning | Contact Information | Public Meeting Schedule | General Schedule | How to Get Involved | Documents/Bulletins/Maps | Links


Visit the graphic version of this page.

General Project Schedule

Time FrameProcess MilestonesPublic Participation Components
Winter 2004Notice of Intent
(completed process)
"Notice of Intent" published in the Federal Register Winter 2004
Winter 2004Scoping

Identify Concerns
(current process)

  • 60-day public scoping period
  • Public scoping meetings held in Craig, Steamboat Springs & Maybell, CO (January 2005)
  • Informal scoping conducted by NWCOS to solicit public issues/comments for the RMP
Winter 2004/2005Planning Issues & Criteria Development

Ensure decisions address the pertinent issues

 
Winter 2004/2005Data CollectionNWCOS provides additional background documents/surveys for inclusion in the Analysis of the Management Situation (AMS) document and Alternatives Development
Summer/Fall 2005Alternative Formulation

Develop range of reasonable management alternatives

 
Winter 2005/2006Alternatives Assessment

Analyze a Preferred Alternative

 
Fall 2006Draft RMP/EIS

Analyze a Preferred Alternative

  • Written for public audience
  • Circulate and publicize availability of Draft RMP/EIS document
  • Request public comment
  • 90-day comment period
  • Public hearings will be held in the community
Summer 2007Final EIS & Proposed RMP
  • Consideration of and response to public comments obtained on draft RMP/EIS
  • File Final EIS with Environmental Protection Agency (EPA) and make publicly available
  • Make copies of any substantial Mitigation Action Plan publicly available
Summer/Fall 2007Protest Period
  • 30-day protest period
  • Protests are submitted to BLM Director