Vitals
Proposed Location: Imperial Valley, southwest of El Centro near the Mexican border
Electricity Production Capacity: Up to 600 megawatts
Company: A subsidiary of 8 Minute Energy Renewables, LLC
Acreage: A proposed 5.5 mile long 120 foot wide corridor for a transmission line on BLM land (85 acres)
Status: Environmental review pending
Public Comment: An opportunity for public comment will follow publication of the environmental analysis
Electrictrical Transmission Connection: 230 kV line that would cross BLM land and interconnect with the Imperial Valley Substation