| Analysis Number | Project Name/Description | Analysis Type | Initiation Date | Contact Name | Case Number | Document Completion Date | Remarks |
| RE-2006-01 | Panich Acquisition | EA | 10/20/2005 | Matzat | CA46480 | 11/17/2005 | OHV area parcel |
| RE-2006-02 | ALC Acquisition | EA | 10/20/2005 | Rodriguez | CA47565 | 6/2/2006 | Avilla Lot 2 |
| RE-2006-03 | Cox Access Road | EA | 10/20/2005 | Wright | CA47447 | 9/18/2006 | Sky Ranch Road Area |
| RE-2006-04 | Singh Access Road | EA | 10/20/2005 | Wright | CA47448 | 5/25/2006 | Adobe Road |
| RE-2006-06 | Roberts East Access | EA | 10/25/2005 | Wright | CA47557 | 12/22/2005 | Hawkinsville Canal Gulch Rd |
| RE-2006-07 | Roberts West Access | EA | 10/25/2005 | Wright | CA47548 | 12/13/2005 | Canal Gulch Existing Rd |
| RE-2006-07 | Neal Spring Dev | EA | 11/29/2005 | Matzat | CA47456 | 12/1/2005 | N of French Gulch |
| RE-2006-09 | Meissner R/W Renewal | EA | 11/18/2005 | Matzat | CA31467 | 12/1/2005 | French Gulch |
| RE-2006-09 | City of Redding Donation | EA | 11/30/2005 | Rodriguez | CA47646 | 6/14/2006 | Clear Creek Parcel |
| RE-2006-100 | Sacramento Watershed OHV Trails | EA | 12/18/2005 | Zaffarano | | 1/16/2007 | |
| RE-2006-12 | Integrated Weed Management on BLM Public Lands within North-Central California | EA | 11/30/2005 | Diridoni | | | FONSI signed 6/14/07. Public review from June 25-July 25. |
| RE-2006-14 | Clear Creek Boulder Clusters | EA | 12/1/2005 | Miller | | 5/9/2006 | 15 boulders for fish habitat |
| RE-2006-20 | Alan Abbs Team Sunsweet | EA | 1/3/2006 | Lytle | CA360SRP06-11 | 4/3/2006 | |
| RE-2006-25 | Juniper Removal - HWY 36 | EA | 1/26/2006 | Williams | | 3/23/2006 | To protect oaks. project started 9/2006 |
| RE-2006-38 | Coram Road Relocation | EA | 3/15/2006 | Zaffarano | | 5/11/2006 | Relocate 2.9 miles of Coram Road |
| RE-2006-44 | Bowman Parcel sale | EA | 4/3/2006 | Emry | | 8/16/2006 | |
| RE-2006-45 | Hogsback Parcels Sale | EA | 4/3/2006 | Emry | | | |
| RE-2006-49 | Dry Creek Sale | EA | 4/6/2006 | Emry | | | |
| RE-2006-54 | Cummins Road | EA | 4/11/2006 | Matzat | CA47942 | 7/5/2006 | Terminal Access road off Highland Ridge Rd |
| RE-2006-55 | Dever Trust Road | EA | 4/11/2006 | Wright | CA47943 | 10/4/2006 | |
| RE-2006-56 | Bucktail piezometers Trinity Rive | DNA | 5/15/2007 | | 04/17/06 | | |
| RE-2006-57 | Trinity Co. PUD 12 kV powerline | EA | 5/1/2006 | Emry | CA47560 | 6/8/2006 | Weaverville area |
| RE-2006-61 | Bass Pond Pipe | EA | 5/10/2006 | Williams | | 5/15/2006 | |
| RE-2006-62 | Cummins Access | EA | 5/11/2006 | Matzat | CA47942 | 6/27/2006 | |
| RE-2006-66 | Big Gulch Acquisition | EA | 5/22/2006 | Matzat | | 6/21/2006 | |
| RE-2006-68 | Lowden Field Wetland | EA | 5/15/2007 | | | | wetland enhancement from CDWR project by TCRCD in review, working on cultural concerns 01/01/07 |
| RE-2006-71 | Coleman Weir Temp Diversion | EA | 6/16/2006 | Wright | CA48044 | 7/14/2006 | Battle Ck bypass at diversion. BLM DR/FONSI tied to BR EA. |
| RE-2006-74 | Redding 2007 OHV Acquisition Grant | EA | 6/28/2006 | Zaffarano | | 7/24/2006 | |
| RE-2006-82 | Fish and Game Donation | EA | 7/20/2006 | Wright | | | |
| RE-2006-83 | Pape Seep Well and Water Pipeline | EA | 7/20/2006 | Emry | CA48157 | 8/6/2006 | |
| RE-2006-84 | ROW existing pole line & reroute | EA | 7/20/2006 | Matzat | CA46489 | 7/24/2006 | |
| RE-2006-88 | Trinity Co. PUD 12 kV powerline | EA | 8/3/2006 | Emry | CA48276 | 8/23/2006 | La Grange Mine area |
| RE-2006-89 | Cobb Seep Well R/W | EA | 8/7/2006 | Emry | CA48283 | 10/4/2006 | |
| RE-2006-91 | Avilla Estates #1 Acquisition | EA | 8/18/2006 | Rodriguez | CA48311 | 8/24/2006 | Sacramento River ACEC |
| RE-2006-96 | Folta Fire Egress Road | EA | 8/30/2006 | Wright | | | Old Diggins Area |
| RE-2006-99 | Canyon Creek BR Sites | EA | 9/23/2006 | Wright | CA48299 | 9/28/2006 | EA prepared by TRRP. BLM has separate FONSI/DR |