U.S. DEPARTMENT OF THE INTERIORBUREAU OF LAND MANAGEMENT
 
California
Print Page

2006 NEPA Documents - Redding Field Office

Analysis NumberProject Name/DescriptionAnalysis TypeInitiation DateContact NameCase NumberDocument Completion DateRemarks
RE-2006-01Panich AcquisitionEA10/20/2005MatzatCA4648011/17/2005OHV area parcel
RE-2006-02ALC AcquisitionEA10/20/2005RodriguezCA475656/2/2006Avilla Lot 2
RE-2006-03Cox Access RoadEA10/20/2005WrightCA474479/18/2006Sky Ranch Road Area
RE-2006-04Singh Access RoadEA10/20/2005WrightCA474485/25/2006Adobe Road
RE-2006-06Roberts East AccessEA10/25/2005WrightCA4755712/22/2005Hawkinsville Canal Gulch Rd
RE-2006-07Roberts West AccessEA10/25/2005WrightCA4754812/13/2005Canal Gulch Existing Rd
RE-2006-07Neal Spring DevEA11/29/2005MatzatCA4745612/1/2005N of French Gulch
RE-2006-09Meissner R/W RenewalEA11/18/2005MatzatCA3146712/1/2005French Gulch
RE-2006-09City of Redding DonationEA11/30/2005RodriguezCA476466/14/2006Clear Creek Parcel
RE-2006-100Sacramento Watershed OHV TrailsEA12/18/2005Zaffarano 1/16/2007 
RE-2006-12Integrated Weed Management on BLM Public Lands within North-Central CaliforniaEA11/30/2005Diridoni  FONSI signed 6/14/07. Public review from June 25-July 25.
RE-2006-14Clear Creek Boulder ClustersEA12/1/2005Miller 5/9/200615 boulders for fish habitat
RE-2006-20Alan Abbs Team SunsweetEA1/3/2006LytleCA360SRP06-114/3/2006 
RE-2006-25Juniper Removal - HWY 36EA1/26/2006Williams 3/23/2006To protect oaks. project started 9/2006
RE-2006-38Coram Road RelocationEA3/15/2006Zaffarano 5/11/2006Relocate 2.9 miles of Coram Road
RE-2006-44Bowman Parcel saleEA4/3/2006Emry 8/16/2006 
RE-2006-45Hogsback Parcels SaleEA4/3/2006Emry   
RE-2006-49Dry Creek SaleEA4/6/2006Emry   
RE-2006-54Cummins RoadEA4/11/2006MatzatCA479427/5/2006Terminal Access road off Highland Ridge Rd
RE-2006-55Dever Trust RoadEA4/11/2006WrightCA4794310/4/2006 
RE-2006-56Bucktail piezometers Trinity RiveDNA5/15/2007 04/17/06  
RE-2006-57Trinity Co. PUD 12 kV powerlineEA5/1/2006EmryCA475606/8/2006Weaverville area
RE-2006-61Bass Pond PipeEA5/10/2006Williams 5/15/2006 
RE-2006-62Cummins AccessEA5/11/2006MatzatCA479426/27/2006 
RE-2006-66Big Gulch AcquisitionEA5/22/2006Matzat 6/21/2006 
RE-2006-68Lowden Field WetlandEA5/15/2007   wetland enhancement from CDWR project by TCRCD in review, working on cultural concerns 01/01/07
RE-2006-71Coleman Weir Temp DiversionEA6/16/2006WrightCA480447/14/2006Battle Ck  bypass at diversion. BLM DR/FONSI tied to BR EA.
RE-2006-74Redding 2007 OHV Acquisition GrantEA6/28/2006Zaffarano 7/24/2006 
RE-2006-82Fish and Game DonationEA7/20/2006Wright   
RE-2006-83Pape Seep Well and Water PipelineEA7/20/2006EmryCA481578/6/2006 
RE-2006-84ROW existing pole line & rerouteEA7/20/2006MatzatCA464897/24/2006 
RE-2006-88Trinity Co. PUD 12 kV powerlineEA8/3/2006EmryCA482768/23/2006La Grange Mine area
RE-2006-89Cobb Seep Well R/WEA8/7/2006EmryCA4828310/4/2006 
RE-2006-91Avilla Estates #1 AcquisitionEA8/18/2006RodriguezCA483118/24/2006Sacramento River ACEC
RE-2006-96Folta Fire Egress RoadEA8/30/2006Wright  Old Diggins Area
RE-2006-99Canyon Creek BR SitesEA9/23/2006WrightCA482999/28/2006EA prepared by TRRP. BLM has separate FONSI/DR

 
 

 
Last updated: 08-28-2007