Devers-Palo Verde No.2 Transmission (CACA-48771)

Federal Process & Documents


The following diagram shows the current progress for this proposed project with links to applicable project-related documents. The colored bar in the center indicates the items that have been completed or are currently underway.

 

Federal Coordination Process
   

- Right-of-Way Grant

Record of Decision -  
  - Notification of Final EIS

Publication of Final EIS -

  
  - Public Comment Period
Notice of Availability of Draft EIS -  
  Draft EIS/EIR
Notice of Intent -  

Overview

Project Fact Sheet
Project Map 1
Project Map 2

Announcements & Documents

Notice of Intent

Published in Federal Register, 12/07/05
BLM news release issued, 12/23/05

Publication of the joint CPUC-BLM Draft EIS/EIR

BLM news release issued, 07/27/06

Notice of Availability of Draft EIS

Public comment period ended August 11, 2006
Published by BLM in Federal Register, 07/28/06
BLM news release issued, 07/27/06

Public Comments Received

Notice of Availability of Final EIS

Published by EPA in Federal Register, 11/03/06
Published by BLM in Federal Register, 03/15/07
BLM news release issued, 11/03/06

Notice of Availability of Record of Decision - 07/14/11

Published by BLM in Federal Register, 7/19/11
BLM news release issued, 7/14/11


Decision & Authorization Documents

Right-of-Way Grant & Notice to Proceed, 9/19/2011

Record of Decision, 7/14/2011

Environmental Documents

Final Environmental Impact Statement

Executive Summary and Maps

Biological Opinion from US Fish & Wildlife Service 

State of California Process - CPUC

Documents, Reports, and Public Participation

* For latest BLM news and renewable energy announcements: http://www.blm.gov/ca/st/en/info/newsroom.html