The following is a list of ongoing and completed projects for the Alturas Field Office. The level of analysis are:

  • CX=Categorical Exclusion-The project falls into one of several categories of minor, routine projects excluded from needing more
    analysis. Each time a specific categorical exclusion is used, the required review must be prepared.
  • EA=Environmental Assessment-An EA must be prepared for proposed actions that (1) are not exempt from NEPA, (2) have not
    been categorically excluded, (3) have not been covered in an existing Resource Management Plan EIS or other environmental
    analysis, or (4) do not normally or obviously required an EIS. An EA may be prepared for any action at any time to assist in
    planning and decision making. A Finding of No Significant Impact (FONSI) is prepared if the criteria are met.
  • EIS=Environmental Impact Statement-When a proposed action, including a proposed policy or legislative recommendation, is
    projected to have a significant impact on the quality of the human environment, an EIS must be prepared. An EIS is intended to
    provide decision makers and the public with a complete and objective evaluation of significant environmental impacts, both
    beneficial and adverse, resulting from a proposed action and all reasonable alternatives. An EIS is a major vehicle for fulfilling the
    substantive environmental goals set forth in NEPA.
Comment/Appeal Period

The Field Office Manager has the discretion to determine whether or not the EA and FONSI should be made available for public review prior to making a final decision, as defined in the CEQ regulations (40 CFR 1501.4(e)(2)). Program-specific guidance should also be consulted to determine if the EA and FONSI must be reviewed by the public prior to a decision. The manager must notify the public, including affected State and local governments and Indian tribes, of the review period (40 CFR 1506.6). The comment period for an EA is generally 30 days. If a public review is determined unnecessary, the affected and interested public must be notified of the availability of the EA and the FONSI (40 CFR 1501.4(e)(1) and 1506.6). The manager responsible for authorizing the action determines the appropriate means for notifying the public and ensuring availability based on the extent of concern and interest in the action. Any person who is adversely affected by the decision has the right to appeal within 30 days of the signing of the Decision Record (DR) (43CFR 4.410(a) and 43 CRF 4.411(a)).

 

Number
 Type
 Project
Name
 Project
Description
 Project
Lead
 Start
Date
Staff
Comments
Due
FONSI/
DR/CX
Signed
Appeal
Period
Over
 Comments/
Status
 CA320-NEPA-07-01
 CX
CGF Borrow Pit
CDF Borrow Pit RimRock Allotment 
Singleton
11/16/06
 
 
 
 
N/A 
 
 

CA-320
NEPA-07-02


EA

South Ash Valley Group Grazing Permit Renewal

Grazing Permit Renewal

Butow

12/12/06

 

 

01/29/07

 

 
 03/05/07 

Interested Party Protested-Pending Final Decision

 

CA-320
NEPA-07-03

EA

 Joe Russ Group EA

Grazing Permit Renewal

Lowrey

01/09/07

02/26/07

 07/23/07

09/14/07

 10 Year Grazing Issued

CA-320-NEPA-07-04

EA

 

 

Fitzhugh Ck Parking Area

Recreation and Riparian Enhancement

Singleton

 

 
    

Project needs S&D and Clearances

CA-320-NEPA-07-05

EA

Dry Ck Project EA 2

Riparian Exclosure

Butow

    

Project needs S&D and Clearances

CA-320-NEPA-07-06

CX

Stipa Reservoir Lining

Reservoir lining

Butow

    

Project needs Clearances

CA-320-NEPA-07-07

CX

Nelson Corral Reservoir Test sites

Reservoir test sites

Butow

    

Project needs Clearances

CA-320-NEPA-07-08

CX

Juniper Ridge Headcut Repair

Headcut Repair

Butow/McKirahan

    

Project needs S&D and Clearances, except Wildlife

CA-320-NEPA-07-09

CX

Stipa Harter Burn

Prescribed Fire

Savage

    

Project needs  Clearances, except Wildlife

CA-320-NEPA-07-10

CX

108 Juniper Project

Juniper Treatment

Hall

 

    

CA-320-NEPA-07-11

EA

 

 

Williams Allotment & Aspen/Riparian Fence

Exclosure Fencing & Water Development

Butow

1/31/2007

3/09/07

 

 

03/18/07

06/06/07 

CA-320-NEPA-07-12

EA

Bubble Spring Exclosure & Spring Improvement

Exclosure Fencing & Water Development

Lowrey

 

 

2/1/2007

 

 

3/30/2007

05/03/07

06/22/07

08 Construction

CA-320-NEPA-07-13

EA

Intregrated Weed Management Program 

 Noxious Weed Treatment

Dolan

     

CA-320-NEPA-07-14

CX

Muck Valley Commerical Firewood Cutting

Juniper Treatment

 

 

Hall

     

CA-320-NEPA-07-15

 EA

 Rocky Prairie Grazing Permit Renewal

 Grazing Authorization Renewal 

 Butow

 03/12/07

 04/20/07

   

CA-320-NEPA-07-16

EA

N. Graves/
Mackey Grazing Permit Renewal

Grazing Authorization Renewal 

Lowrey

04/17/07

05/18/07

07/10/07

08/29/07

10 Year Grazing Issued

CA-320-NEPA-07-17

cx

 

 

Arrowhead RX

 

 

Fuels Reduction

 

 

Savage

 

 

03/18/07

 

 

 

 

 

Pending

 

 

CA-320-NEPA-07-18

DNA

Casuse Mtn. Grazing Lease Renewal

Grazing Authorization Renewal

Lowrey

03/30/07

N/A

05/01/07

06/22/07

10 Year Grazing Issued

CA-320-NEPA-07-19

cx

Whitewater Family Adventures Permit

Recreation Permit

Singleton

 03/31/07

    

CA-320-NEPA-07-20

CX

Baier ROW

Right of Way Permit

Foster-Curley

06/11/07

 

 

 

 

CA-320-NEPA-07-21

CX

 

 

Hall

06/25/07

 

 

 

 

CA-320-NEPA-07-22

CX

 

 

Hall

06/25/07

    

CA-320-NEPA-07-23

CX

Pavalek ROW

Right of Way Permit

Burke

06/26/07

    

CA-320-NEPA-24

CX

Modoc Guide Service

Guide Service Permit

Singleton

07/11/07

    

CA-320-NEPA-07-25

CX

 

Comm Site

Prisco

07/11/07

    

CA-320-NEPA-07-26

EA

Power Fire Emergency Stabilization Plan

Fire Rehab

Dolan/
Lowrey

07/30/07

N/A

08/14/07

09/18/07

Plan Funded & Implemented

CA-320-NEPA-07-27

CX

Unavco GPS Communication Site

Comm. Site ROW

Collum

08/21/07

N/A

N/A

N/A

Site Constructed

 CA-320-NEPA-07-28

 DNA Lauer Dam

Geotechnical Test Drilling

 Burke

 08/28/07    

 CA-320-NEPA-07-29

EA

Silva Flat Group Livestock Grazing Authorization

Grazing Permit Renewal 

Aarstad

07/10/07

08/10/07

09/24/07

11/19/07

 

CA-320-NEPA-07-30

CX

Jay Fairs Guide Service

Guide Permit

Singleton

  

09/27/07

  

CA-320-NEPA-07-31

CX

Woods ROW

Road Maintenance

Prisco

  

12/05/07