      
|
Telephone Flat Geothermal Development Project Final EIS/EIR
|
3.9.3.2 Assessment Methodology
|
|
The Proposed Action and Project Alternatives are
compared with existing land uses and land use plans
to determine if the Project would adversely affect
these land uses or conflict with existing land use
plans. The significance criteria are then applied to
determine if the adverse effects would be considered
significant impacts if the Project was implemented.
|
|
The Proposed Action would construct and operate a
geothermal power plant, construct and drill
geothermal wells, install pipelines to carry the
geothermal fluid to and from the wells to and from
the power plant, and install an electrical transmission
line to conduct the electricity from the power plant to
the BPA transmission line located east of Tionesta.
The majority of the electrical transmission line would
be constructed within a designated utility corridor
which was the subject of an earlier EIS/EIR prepared
for the proposed Fourmile Hill Project (BLM et al.
1998). The Telephone Flat Project facilities would be
constructed and installed in a geothermal leasehold
located in the Modoc National Forest.
Decommissioning of the project facilities is expected
to occur approximately 50 years after commencement
of project operations.
|
|
3.9.3.3.1 Environmental Consequences of the Proposed Action
|
|
Project impacts during the construction, operation
and decommissioning phases of the project would
remain the same with respect to land use issues.
Consistency with Applicable Plans or Policies: The
Project would be consistent with the LRMP as all the
management prescriptions in the area of the Proposed
Action allow for geothermal exploration and
development. Visual retention areas along Primary
Forest Road 97 and partial visual retention areas
surrounding Alcohol Crater also allow for mineral
development if it is consistent with visual quality
objectives. The findings of the visual resource
assessment indicate that no significant visual impacts
would result from the Project after mitigation
measures are applied (see Section 3.8). The Medicine
Lake Management Area S&G state that geothermal
development should not be precluded by other
management activities. There are no Forest-wide
S&G that would preclude the Project.
The Project would be consistent with the standards
and guidelines of the NFMP ROD amendments to the
Modoc National Forest LRMP (see Section 3.3).
The Project would comply with the environmental
stipulations of the respective federal geothermal
leases comprising the proposed Participating Area.
The Project would be consistent with the Siskiyou
County General Plan and its Elements, particularly
the Geothermal and Energy Elements. The Project
would not directly conflict with existing land uses in
the area of proposed operations.
Federal, state, and local land use plans were reviewed
and analyzed to determine if conflicts existed
between goals and objectives in these documents and
the Proposed Action. It was found that several of
these documents, including the LRMP and the
Siskiyou County General Plan Geothermal and
Energy Elements, had provisions for geothermal
development of the project vicinity. No adverse
effects are expected to occur with respect to land use
plan conflicts if the Project were to be implemented.
Disrupt or Divide an Established Community: The
area of the Proposed Action is relatively undeveloped
and uninhabited; no community is expected to be
physically or socially divided or disrupted by any
proposed facilities. No adverse effects are expected
to result that would destabilize any established
communities.
Conflict with Established Recreational, Educational,
Religious or Scientific Uses of the Area: Recreational
use of the area is discussed in Section 3.10 of this
EIS/EIR; Native American traditional and spiritual
uses of the area are discussed in Section 3.6. No
educational or scientific uses of the area are expected
to be adversely affected by the proposed Project. The
proposed power plant and associated facilities could
become a visitor attraction to those wishing to see a
modern geothermal power plant in operation, and the
Project could thus increase the educational and
scientific value of the area. No adverse effects except
those described for Native Americans (see Section 3.6.3)
are expected to occur to recreational, educational,
religious or scientific uses of the area.
Compatibility with Existing Land Uses in the Area:
The Project would be compatible with existing land
uses and Forest management prescriptions in the area
of the Proposed Action. Impacts discussed in other
environmental resource sections (i.e., air quality,
noise, visual resources, and recreation) of this
EIS/EIR identify adverse effects of the Project which
may affect offsite land uses or periodic visitors in the
area of the Proposed Action, but the resource-specific
impacts are considered to be below the level of
significance after prescribed mitigation measures.
The Project would not prohibit Native American use
of the area. No specific land use incompatibilities
were identified.
|
|
3.9.3.3.2 Unavoidable Adverse Impacts of the Proposed Action
|
|
Recreational enjoyment and traditional Native
American use of the area may be aesthetically
diminished for some people as the Project would
introduce an industrial-like appearance into the area
of operations. Residential and Special Interest Areas
may also experience adverse effects due to changes
in the visual, air quality, and noise environment. The
environmental resource-specific effects are described
in the respective environmental resource sections of
this EIS/EIR.
|
|
3.9.3.4 Alternative Power Plant Site A
|
|
3.9.3.4.1 Consequences of Alternative Site A
|
|
The adverse effects of the Project Alternative Site A
on land use are expected to be approximately the
same as those identified for the Proposed Action.
|
|
3.9.3.4.2 Unavoidable Adverse Impacts of Alternative Site A
|
|
Unavoidable Adverse Impacts of Project Alterative
Alternative Site A are expected to be approximately
the same as those identified for the Proposed Action.
|
|
3.9.3.5 Alternative Power Plant Site B
|
|
3.9.3.5.1 Consequences of Alternative Site B
|
|
The adverse effects of the Project Alternative Site B
on land use are expected to be approximately the
same as those identified for the Proposed Action.
However, one well pad (77-18) under the Power
Plant Site B Project Alternative would be located
within the Medicine Lake MLSA, immediately south
of Primary Forest Route 97 (see Figures 2.3.3
and 3.3.2). The construction of well pad 77-18 would
also include approximately 900 feet of new access
road and adjacent pipeline corridor for a total surface
disturbance of about 6 acres in the MLSA. The well
pad and ancillary facilities would be located on the
northern fringe of the MLSA.
The NFMP ROD (page C-17) states, “Developments
of new facilities that may adversely affect
Late-Successional Reserves [including MLSAs]
should not be permitted. New development proposals
that address public needs or provide significant
public benefits, such as powerlines, pipelines,
reservoirs, recreation sites, or other public works
projects will be reviewed on a case-by-case basis and
may be approved when adverse effects can be
minimized and mitigated. These will be planned to
have the least possible adverse effects on
Late-Successional Reserves. Developments will be
located to avoid degradation of habitat and adverse
effects on identified late-successional species (USFS
and BLM 1994).” As discussed in Section 1.3, the
proposed Project meets the criteria of public needs
and benefits that would allow the development to
occur as long as the adverse effects are minimized
and mitigated. Measures to minimize and mitigate the
adverse effects of the Site B Project Alternative on
late-successional habitat are described in Section 3.3.3.5.1.
-
Impact 3.9.3.5-1: Approximately 6 acres of
surface disturbance would occur in the Medicine
Lake Managed Late-Successional Area from the
construction of well pad 77-18 and related
access road and pipeline corridor. This
development could be inconsistent with direction
from the Northwest Forest Management Plan
Record of Decision and the Forest Land and
Resource Management Plan.
Significance of the Impact: This impact is
considered potentially significant but
implementation of Mitigation Measures 3.3.3.3-9
and 3.3.3.3-10 would reduce the adverse effects
of the impact to below the level of significance.
|
|
3.9.3.5.2 Unavoidable Adverse Impacts of Alternative Site B
|
|
Unavoidable Adverse Impacts of Project Alterative
Alternative Site B are expected to be approximately
the same as those identified for the Proposed Action.
|
|
3.9.3.6 Alternative Transmission Line Routes
|
|
Previous Transmission Line Impact Assessment:
As discussed in Section , the transmission line
originating at the Telephone Flat Project power plant
site would be routed to interconnect with a
transmission line located within one of the six
alternative utility corridors evaluated in the Fourmile
Hill Project EIS/EIR to be selected by the agencies as
the preferred utility corridor between the Medicine
Lake Highlands and the existing BPA Malin-Warner
transmission line (BLM et al. 1998). The Fourmile
Hill Project EIS/EIR evaluated seven different
possible line segments (segments A1, A2, A3, B1,
B2, C1 and C2) which could be used in different
combinations to comprise the preferred utility
corridor. Only five of these line segments (A2, B1,
B2, C1 and C2) could possibly be used by the
Telephone Flat Project, and the Plans and Policies as
well as the Land Use and Recreation analysis from
the Fourmile Hill Project EIS/EIR of the five line
segments which could be potentially used by the
Telephone Flat Project are incorporated by reference
into this EIS/EIR (see pages 3-148 through 3-179,
and 4-180 through 4-209 of the Fourmile Hill Project
EIS/EIR; BLM et al. 1998). The findings of the
earlier assessment are also summarized in Exhibit 4
of this EIS/EIR (See Table S-5, pages S-30 to S-36,
in Exhibit 4).
Telephone Flat Project Route Alternatives:
If the agencies select one of the Fourmile Hill Project
utility corridor alternatives which route through the
Medicine Lake basin in close proximity to the
Telephone Flat Project (i.e., Alternatives 1 through
4), then the Telephone Flat Project would construct
either line segment D1 (if Alternatives 1 or 2 is
selected) or line segment D2 (if Alternatives 3 or 4 is
selected), and no specific agency decision on
transmission line route alternatives would need to be
made for the Telephone Flat Project. However, if the
Northern Utility Corridor for the Fourmile Hill
Project (i.e., Alternatives 5 or 6) is selected as the
agency-preferred utility corridor, then a second
decision for the Telephone Flat Project would need to
be made with respect to how to interconnect the
Telephone Flat Project transmission line with the
Northern Utility Corridor. Two alternative Telephone
Flat Project transmission line routes (Route 1 and
Route 2) are being considered for transporting power
generated from the Telephone Flat Project power
plant site to the Northern Utility Corridor.
|
|
3.9.3.6.1 Environmental Consequences of Route 1 (Line Segments D1 + A2)
|
|
The Telephone Flat Project Alternative Transmission
Line Route 1 (4.95-5.55 miles) consists of an initial
1.28- to 1.88-mile line segment D1 and a 3.67-mile
utility corridor line segment A2. Line segment D1
proceeds northward from the Telephone Flat Project
power plant site and joins the origin of line segment
A2 at the western tip of Glass Mountain. Line
segment A2 proceeds northeast from this point until
it joins the Northern Utility Corridor at the origin of
line segment B1 south of Indian Butte. Although
much of this route would follow existing 4-wheel
drive roads, the route would proceed through the Mt.
Hoffman Released Roadless Area (RRA).
The USFS is currently considering a proposal to
temporarily halt all road construction in roadless
areas on National Forests. While this proposal is
being developed, the USFS issued a proposed interim
policy to temporarily halt road construction in most
areas of the National Forest system that are not
currently roaded. Forest plans that have been
amended by the NFMP ROD, such as the Modoc
National Forest LRMP, would be exempted from the
interim proposal (USFS 1998). Therefore, it is not
expected that the Proposed Action would be affected
by the temporary moratorium on new road
construction as currently proposed.
Line Segment D1:
Line segment D1 is located entirely within the
Project wellfield area, and the effects for line
segment D1 would be the same as those described for
the Proposed Action.
Line Segment A2:
The Proposed Action would be generally consistent
with the standards and guidelines of the NFMP ROD;
however, the NFMP ROD requires that a watershed
analysis be prepared by the Forest prior to any
management activities in a non-Key Watershed that
contains roadless area. For the Proposed Action,
Alternative Transmission Route 1 of the Proposed
Action would proceed through the Mt. Hoffman
Released Roadless Area (RRA); Alternative
Transmission Route 2 would avoid roadless areas.
The Proposed Action would occur in an area subject
to the NFMP ROD, and is considered to be non-Key
Watershed by the Forest.
-
Impact 3.9.3.6.1-1: If Alternative Transmission
Route 1 of the Proposed Action, or any variation
that includes line segment A2 that passes
through the Mt. Hoffman RRA, is selected and
approved for implementation, this Project would
be potentially noncompliant with the standards
and guidelines of the Northwest Forest Plan
unless and until a watershed analysis is
conducted and completed prior to transmission
line construction activities.
Significance of the Impact: This impact is
potentially significant as the Project would be in
noncompliance with USFS and BLM
environmental management direction. This
impact would be reduced to a less than
significant level with the implementation of the
following mitigation measure.
Mitigation Measure 3.9.3.6.1-1: A watershed
analysis shall be prepared prior to transmission
line construction activities within the route of
alternative line segment A2 if Alternative
Transmission Route 1 of the Proposed Action, or
any variation that includes line segment A2, is
selected and approved for implementation. The
watershed analysis shall comply with the
requirements of the Northwest Forest Plan and
shall be completed to the satisfaction of the
USFS prior to construction of the affected
transmission route line segment.
Line segment A2 was also the subject of earlier
environmental analysis as part of the Fourmile Hill
Project EIS/EIR (BLM et al. 1998). That analysis is
incorporated by reference into this EIS/EIR, and the
findings of that analysis are summarized below and
amended to be consistent with the statement of
impact and significance formatting of this EIS/EIR.
-
Impact 3.9.3.6.1-2 (Fourmile Hill Impact
described in Section 4.11.5): Line segment A2
would pass through the portion of the Mt.
Hoffman Released Roadless Area that has a ROS
designation of Roaded Natural. Line segment A2
would skirt the northwest margin of the Glass
Mountain Geologic Area which has an ROS
designation of Primitive. Approximately 2 miles
east of Mt. Hoffman, the transmission line would
pass through a gap in the Geologic Area. At this
location, a spur of lava extends to the northwest,
and is separated from a small outlying patch of
lava by several hundred feet. The Glass
Mountain Geologic Area includes both the spur
of lava and the outlying patch, but does not
include the space between the two. The proposed
transmission line would pass through this gap,
which has an ROS designation of Roaded
Natural. Construction of the transmission line in
this area, therefore, would be consistent with the
ROS designation of Roaded Natural, which
allows for road construction and conventional
motorized uses. This consistency with ROS
allocations would be the same during operations
and decommissioning.
Significance of the Impact: Line segment A2
would be consistent with the ROS allocation of
Roaded Natural. Impacts to land use are
expected to be less than the level of significance.
Measure 3.1.3.6.1-2 in Section 3.1.3.6.1 would
ensure that no project activities would take place
in the Glass Mountain Geologic Area.
Impact 3.9.3.6.1-3 (Fourmile Hill Impact
described in Section 4.11.9): Construction of
line segment A2 would remove timber from
designated timber lands being managed for both
future commercial timber harvesting and
resource protection. Operation of the
transmission line would also result in effects to
timber lands as on-going maintenance activities
would limit natural revegetation of cleared areas
over the life of the project. Decommissioning
would return the transmission line corridor to
forest uses.
Significance of the Impact: This impact is
considered adverse but not significant. Although
not required to reduce a significant impact, the
following other measure would ensure that forest
areas disturbed by the implementation of line
segment A2 is revegetated as timber lands.
Measure 3.9.3.6.1-3 (Fourmile Hill Measure
4.11.9a): In consultation with the USFS, the
Project Applicant shall select and plant
appropriate timber species as part of the
revegetation efforts during decommissioning of
the project. Ultimately, this replanting program
would serve to replace timber lands removed as a
result of transmission line development.
|
|
3.9.3.6.2 Environmental Consequences of Route 2 (Line Segments D2 + B2*)
|
|
The Telephone Flat Project Alternative Transmission
Line Route 2 (11.43-12.26 miles) consists of an
initial 0.6- to 1.43-mile line segment D2 and a
10.83-mile utility corridor line segment B2*. Line
segment D2 proceeds eastward from the Telephone
Flat Project power plant site and joins line segment
B2 southwest of Red Shale Butte. Line segment B2*
is that portion of the earlier proposed line segment B2
which originates at the terminus of line segment D2.
Line segment B2* avoids the Mt. Hoffman RRA and
the Glass Mountain Glass Flow Area as it continues
southeast from its origin with line segment D2. Line
segment B2* proceeds eastward south of Red Shale
Butte before proceeding northeast to connect with the
Northern Utility Corridor at the origin of line
segment C1 or C2.
Line Segment D2:
Line segment D2 is located entirely within the
Project wellfield area, and the effects for line
segment D2 would be the same as those described for
the Proposed Action.
Line Segment B2:
Line segment B2 was the subject of earlier
environmental analysis as part of the Fourmile Hill
Project EIS/EIR (BLM et al. 1998). That analysis is
incorporated by reference into this EIS/EIR, and the
findings of that analysis are summarized below and
amended to be consistent with the statement of
impact and significance formatting of this EIS/EIR.
Except for the difference in transmission line length,
the adverse effects of the Alternative Route 2 on land
uses would be similar to those described for Route 1.
However, line segment B2 would be routed through
an approximately 1¾-mile portion of the Medicine
Lake MLSA. Assuming a 125-foot-wide transmission
line right-of-way (BLM et al. 1998), a total area of
about 26.5 acres of surface disturbance in the MLSA
would occur. As described in Section , development
that meets public needs or provides public benefits
can occur in MLSAs as long as the adverse effects of
the development can be minimized and mitigated.
-
Impact 3.9.3.6.2-1 (Fourmile Hill Impact
discussed for Alternative 3): Timber would
also be removed for line segment B2. However,
the value of the timber along line segment B2 is
considered greater as late successional seral
forests exist along this line segment.
Significance of the Impact: This effect is
considered adverse and potentially significant.
Measures 3.3.3.6.2-5a, 3.3.3.6.2-5b, and
3.3.3.6.2-5c would reduce this impact to a
less-than-significant level.
Impact 3.9.3.6-2: Line segment B2 would be
routed through the Medicine Lake Managed
Late-Successional Area. This development could be
inconsistent with direction from the Northwest Forest
Management Plan Record of Decision and the Forest
Land and Resource Management Plan.
Significance of the Impact: This impact is
considered potentially significant but
implementation of Measures 3.3.3.6.2-5a,
3.3.3.6.2-5b, and 3.3.3.6.2-5c would reduce the
adverse effects of the impact to below the level
of significance.
|
|
3.9.3.6.3 Unavoidable Adverse Impact of Alternative Transmission Line Routes
|
|
Either of the alternative transmission line routes
would increase the amount of surface disturbance to
the area and may reduce the enjoyment of the area for
some people.
|
|
3.9.3.7 No Action Alternative
|
|
3.9.3.7.1 Consequences of No Action Alternative
|
The No Action Alternative would result in no change
in the existing or future land use in the area of the
Proposed Action or surrounding areas.
-
Impact 3.9.3.7-1: The No Action Alternative
would deny the proposed development of the
geothermal resources beneath geothermal leases
comprising the proposed Participating Area. This
action would be inconsistent with the LRMP and
the Geothermal and Energy Elements of the
Siskiyou County General Plan, each of which
foresaw and provided for the exploration and
development of the area for geothermal power
generation. This Alternative would also conflict
with authorizations provided in the issued
geothermal leases comprising the proposed
Participating Area which state the lease owner
has the “exclusive right and privilege to drill for,
extract, produce, remove, utilize, sell, and
dispose of geothermal steam and associated
geothermal resources” beneath the leases. The
No Action Alternative would not prohibit future
proposals for development of the geothermal
resources beneath the area comprising these
geothermal leases.
Significance of the Impact: This impact is
considered below the level of significance and no
mitigation measures are required.
|
|
3.9.3.7.2 Unavoidable Adverse Impact of No Action Alternative
|
|
The No Action Alternative by the NEPA lead
agencies, BLM and USFS, or the CEQA lead agency,
SCAPCD, would deny the proposed Project and
prevent the proposed development of the geothermal
resources beneath the federal geothermal leases
comprising the proposed Participating Area and the
proposed generation of 48 MW (gross) of
geothermal-fueled electrical energy. This decision
would be inconsistent with the Modoc National
Forest LRMP and the Geothermal and Energy
Elements of the Siskiyou County General Plan. There
would be no decision to be made by the BPA with
respect to the Power Purchase Agreement or the
Transmission Services Agreement if the No Action
Alternative is selected, but the No Action Alternative
would limit BPA’s ability to evaluate geothermal
resource-generated electrical power as part of the mix
of electricity available to be provided to BPA’s
customers from renewable energy resources.
In addition, if the Project does not proceed, then the
electrical energy that would have been provided by
the Project would need to be met by other sources of
electrical energy. Some of these other sources may
not be renewable energy sources and additional
consumption of the resource(s) supplying the other
source(s) of energy would occur proportional to the
energy demand not provided by the Project.
Similarly, some of the other sources of energy may
have adverse environmental impacts that would be
unavoidable.
|
Telephone Flat Geothermal Development Project Final EIS/EIR
 |
|
|