      
|
Telephone Flat Geothermal Development Project Final EIS/EIR
-
Other Measure 3.8.3.4-4: To the extent
possible, all well pads should be located far
enough away from nearby points of public use
(such as forest roads) to prevent easy viewing
through the forest. Access roads and pipeline
corridors to the well pads should be constructed
with sufficient curve in order that a line-of-sight
view, down the road or pipeline to the wellhead
or ancillary structures, is not possible. All well
pad fences and other facilities shall be
constructed of non-reflective material, and to the
extent feasible all lighting shall be directed away
from potential points of public view.
Impact 3.8.3.4.-5: Transmission line segment
D1, if constructed, would cross both Forest
Route 43N21 and Forest Route 43N53.
Significance of the Impact: This impact is less
than significant and no mitigation measures are
required.
Impact 3.8.3.4-6: Transmission line segment
D2, if constructed, would cross Forest
Route 43N53.
Significance of the Impact: This impact is
considered less than significant and no
mitigation measures are required.
Impact 3.8.3.4-7: Surface disturbance would
remain visible for a long time.
Significance of the Impact: This impact is less
than significant and no mitigation measures are
required, but the following other measures would
reduce the adverse effects of the impact:
Other Measure 3.8.3.4-7a: Mulch all disturbed
soil as soon as possible after disturbance to
encourage revegetation. Revegetate according to
USFS standards and State of California Best
Management Practices.
Other Measure 3.8.3.4-7b: Plant trees of
species recommended by the USFS on all areas
where forest cover was removed as soon as
possible following disturbance. Follow USFS
reforestation practices applicable at the time.
Some of the Project facilities would be visible from
surrounding peaks, and some of the elevated areas in
the Project vicinity have historically been utilized by
Native Americans for traditional uses. The potential
visibility of the Project facilities from areas used by
Native Americans for traditional activities is not
evaluated as a visual resource impact, but it is
addressed in the Native American Values analysis
(see Section 3.6).
|
|
3.8.3.4.2 Unavoidable Adverse Effects of the Alternative Power Plant Site A
|
|
These effects would be essentially identical to those
of the Proposed Action.
|
|
3.8.3.5 Alternative Power Plant Site B
|
|
3.8.3.5.1 Consequences of the Alternative Power Plant Site B
|
|
The effects of the Alternative Power Plant Site B
alternative on visual resources differ from those of
the Proposed Action and the Alternative Power Plant
Site A in that the field assessment concluded that
none of power plant facilities located on Alternative
Power Plant Site B would be visible from the Primary
Forest Route 97 KOP, or from any of the potential
KOPs. Therefore, only some of the impacts expected
for the Proposed Action or Alternative Power Plant
Site A, and only some of the measures proposed to
mitigate these same impacts from the Proposed
Action or the Alternative Power Plant Site, are
applicable to the Alternative Power Plant Site B.
Field observations relevant to the visibility of the
Alternative Power Plant Site B power plant site are
summarized in Table 3.8.4.
As shown in the upper photosimulation of Alternative
Power Plant Site B, none of the power plant facilities
are visible from the Forest Route 49 KOP (see
Figure 3.8.9). Some portions of the power plant
facilities may still be visible from some points of
public access, and as shown in the lower
photosimulation in Figure 3.8.9, the cooling tower
plume, when present, would be visible against the
sky when viewed from the Primary Forest Route 49
KOP.
|
-
Impact 3.8.3.5-1: Although not visible from the
KOP, some portions of the power plant facilities
may still be visible from some points of public
access, and the cooling tower plume, when
present, would be visible against the sky when
viewed from the Primary Forest Route 49 KOP.
|
|
Table 3.8.4: Visibility of the Alternative Site B Power Plant Site from Identified Potential KOPs
|
|
Potential KOPs
|
From the Potential KOP Looking Toward the Alternative Site B Power Plant Site
|
From the Proposed Power Plant Site Looking Toward the Potential KOP from 80 Feet Above Ground Surfacea
|
Topographic Map Line-of-Sight Assessment of the Visibility of Proposed Action Power Plant Site
|
Forest Route 49
|
Not Visible
|
Not Visible
|
Not Potentially Visible
|
Forest Route 97
|
Not Visible
|
Not Visible
|
Not Potentially Visible
|
Forest Road 43N53
|
Not Visible
|
Not Visible
|
Potentially Visible
|
Forest Road 43N21
|
Not Visible
|
Not Visible
|
Not Potentially Visible
|
a Viewer was located in a tree on the power plant site at 80 feet above ground surface
| | | | | |
-
Significance of the Impact: This impact is
considered less than significant and no
mitigation measures are required, but the
following other measures would reduce the
adverse effects of the impact.
Other Measure 3.8.3.5-1a: To minimize the
color contrast of the power plant structures with
the forest canopy, all power plant buildings and
other structures shall be painted a color at least
one shade darker than the forest cover, and all
reflective surfaces shall be eliminated to the
extent feasible.
Other Measure 3.8.3.5-1b: To maximize the
effectiveness of vegetative screening, the
minimum number of trees necessary for
construction of the power plant shall be
removed. The accidental disturbance of
additional areas, including damage to trees, shall
be minimized by erecting temporary fencing
before construction begins at the limits of those
areas approved for disturbance during
construction. No unplanned activities beyond the
fencing that would affect the continued screening
value of existing terrain or vegetation shall occur
without the prior approval of the USFS.
Other Measure 3.8.3.5-1c: A maximum of two
access routes to the power plant site shall be
constructed, and curvilinear shapes shall be used
to the extent feasible for construction boundaries
and access roads to avoid the creation of highly
visible straight lines. Cuts and fills should also
be shaped to mimic surrounding natural
landforms wherever possible.
Impact 3.8.3.5-2: Power plant lights may be
indirectly visible from Medicine Lake, Primary
Forest Route 97, and from Forest Road 43N53.
Significance of the Impact: This impact is
considered less than significant and no
mitigation measures are required, but the
following other measures would reduce the
adverse effects of the impact.
Other Measure 3.8.3.5-2a: Power plant lighting
locations shall be selected to minimize the
potential for direct visibility outside the power
plant site. Power plant and wellfield lighting
shall also be designed such that lighting
locations and intensity would provide the
minimum intensity lighting necessary for safe
operation of the plant and personnel safety.
Other Measure 3.8.3.5-2b: All power plant and
wellfield lighting shall be shielded to shine only
directly on the plant or well pad grounds, with no
side- or up-directed lighting, with the exception
of lighting which may be required by the Federal
Aviation Administration (FAA).
Other Measure 3.8.3.5-2c: Individual lights and
groups of lights shall not be lit during hours
unnecessary for safety.
Other Measure 3.8.3.5-2d: Non-reflective
material shall be used for all surfaces facing
potential points of public access.
Other Measure 3.8.3.5-2e: Project Applicant
shall prepare and submit a detailed Exterior Lighting
Design and Management Plan to the Modoc National
Forest for review and approval prior to Project
construction activities that incorporates the following
guidelines:
- Lights that may be in view of Primary Forest
Routes shall only used when necessary for
conducting night-time operations or
maintenance activities or for emergency
purposes;
- Constant outside area lighting shall be limited
to only those places that must be observed
from a distance for safety purposes;
- Area lighting, cooling tower lighting, exterior
turbine-generator building lighting, and
security lighting shall be controlled by the use
of time switches, photo-sensors, and/or motion
detector activation controls so lights are only
on when necessary;
- All exterior power plant light fixtures shall be
shrouded or shielded in such a way as to
minimize offsite lighting and to block direct
light from Primary Forest Routes;
- Drill rig mast lighting shall be shrouded and
directed down onto the drill rig mast or floor
and shielded in such a way as to minimize
offsite lighting;
- Stray light shall be controlled through use of
low-brightness fixtures with optical controls.
|
-
Impact 3.8.3.5-3: Construction at the power
plant, wellfields and transmission lines would
cause short-term visual effects.
Significance of the Impact: This impact is
considered less than significant and no
mitigation measures are required, but the
following other measures would reduce the
adverse effects of the impact.
Other Measure 3.8.3.5-3a: Measures to control
substantial fugitive dust emissions at
construction sites and on frequently traveled
unpaved roads, such as watering or application
of dust palliatives, shall be implemented as
necessary to reduce visible dust plumes.
Other Measure 3.8.3.5-3b: All drilling rig
lights shall be shielded in a manner that limits
direct light to the immediate work area, except as
may be necessary to comply with FAA
requirements. Special care shall be taken to
minimize or avoid the placement or use of lights
which may be directly visible from areas where
substantial viewers may be present. Work lights
shall only be on at times required for safety.
Impact 3.8.3.5-4: The two potential well pads
located near Primary Forest Route 97, as well as
other well pads, may be visible through the
forest after construction.
Significance of the Impact: This impact is less
than significant and no mitigation measures are
required, but the following other measures are
provided to reduce the adverse effects of the
impact
Other Measure 3.8.3.5-4: To the extent
possible, all well pads should be located far
enough away from nearby points of public use
(such as forest roads) to prevent easy viewing
through the forest. Access roads and pipeline
corridors to the well pads should be constructed
with sufficient curve in order that a line-of-sight
view, down the road or pipeline to the wellhead
or ancillary structures, is not possible. All well
pad fences and other facilities shall be
constructed of non-reflective material, and to the
extent feasible all lighting shall be directed away
from potential points of public view.
Impact 3.8.3.5.-5: Transmission line segment
D1, if constructed, would cross both Forest
Route 43N21 and Forest Route 43N53.
Significance of the Impact: This impact is less
than significant and no mitigation measures are
required.
Impact 3.8.3.5-6: Transmission line segment
D2, if constructed, would cross Forest
Route 43N53.
Significance of the Impact: This impact is
considered less than significant and no
mitigation measures are required.
Impact 3.8.3.5-7: Surface disturbance would
remain visible for a long time.
Significance of the Impact: This impact is less than
significant and no mitigation measures are required,
but the following other measures would reduce the
adverse effects of the impact:
Other Measure 3.8.3.5-7a: Mulch all disturbed
soil as soon as possible after disturbance to
encourage revegetation. Revegetate according to
USFS standards and State of California Best
Management Practices.
Other Measure 3.8.3.5-7b: Plant trees of
species recommended by the USFS on all areas
where forest cover was removed as soon as
possible following disturbance. Follow USFS
reforestation practices applicable at the time.
Some of the Project facilities would be visible from
locations in the general vicinity of the proposed
Project site that are utilized by Native Americans for
traditional purposes. Because remote locations such
as these are infrequently accessed by the general
public, the potential effects of the visibility of Project
facilities from remote locations have not been
evaluated as a visual resource impact, but the effects
of Project visibility from these sites are separately
evaluated in the Native American Values subchapter
(see Section 3.6).
|
|
3.8.3.5.2 Unavoidable Adverse Effects of the Alternative Power Plant Site B
|
|
These unavoidable adverse effects of Alternative
Power Plant Site B on visual resources would be less
than those of either the Proposed Action or
Alternative Power Plant Site A. None of the power
plant facilities would be visible from the Primary
Forest Route 49 KOP during daylight hours, nor
would plant lighting be directly visible from the
KOP. However, the cooling tower plume, when
present, would be visible against the sky when
viewed from the Primary Forest Route 49 KOP,
overhead transmission lines would still be visible as
they cross either or both Forest Route 43N21 and
Forest Route 43N53, and surface disturbance
associated with the power plant site, well pads,
access roads, pipeline corridors and transmission line
corridors would be visible for years until
reforestation is well established.
|
|
3.8.3.6 Alternative Transmission Line Routes
|
|
Previous Transmission Line Impact Assessment:
As discussed in Section , the transmission line
originating at the Telephone Flat Project power plant
site would be routed to interconnect with a
transmission line located within one of the six
alternative utility corridors evaluated in the Fourmile
Hill Project EIS/EIR to be selected by the agencies as
the preferred utility corridor between the Medicine
Lake Highlands and the existing BPA Malin-Warner
transmission line (BLM et al. 1998). The Fourmile
Hill Project EIS/EIR evaluated seven different
possible line segments (segments A1, A2, A3, B1,
B2, C1 and C2) which could be used in different
combinations to comprise the preferred utility
corridor. Only five of these line segments (A2, B1,
B2, C1 and C2) could possibly be used by the
Telephone Flat Project, and the Visual Quality
analysis from the Fourmile Hill Project EIS/EIR of
the five line segments which could be potentially
used by the Telephone Flat Project are incorporated
by reference into this EIS/EIR (see pages 3-132
through 3-147, and 4-135 through 4-179 of the
Fourmile Hill Project EIS/EIR; BLM et al. 1998).
The findings of the earlier assessment are also
summarized in Exhibit 4 of this EIS/EIR (See
Table S-5, pages S-30 to S-36, in Exhibit 4).
Telephone Flat Project Route Alternatives:
If the agencies select one of the Fourmile Hill Project
utility corridor alternatives which route through the
Medicine Lake basin in close proximity to the
Telephone Flat Project (i.e., Alternatives 1 through
4), then the Telephone Flat Project would construct
either line segment D1 (if Alternatives 1 or 2 is
selected) or line segment D2 (if Alternatives 3 or 4 is
selected), and no specific agency decision on
transmission line route alternatives would need to be
made for the Telephone Flat Project. However, if the
Northern Utility Corridor for the Fourmile Hill
Project (i.e., Alternatives 5 or 6) is selected as the
agency-preferred utility corridor, then a second
decision for the Telephone Flat Project would need to
be made with respect to how to interconnect the
Telephone Flat Project transmission line with the
Northern Utility Corridor. Two alternative Telephone
Flat Project transmission line routes (Route 1 and
Route 2) are being considered for transporting power
generated from the Telephone Flat Project power
plant site to the Northern Utility Corridor.
|
|
3.8.3.6.1 Environmental Consequences of Route 1 (Line Segments D1 + A2)
|
|
The Telephone Flat Project Alternative Transmission
Line Route 1 is composed of initial line segment D1
and utility corridor line segment A2.
Line Segment D1:
The visual effects and visibility of line segment D1 as
it relates to the Proposed Action, Alternative Power
Plant Site A, and Alternative Power Plant Site B is
described above in the impact assessment for each of
those power plant site alternatives.
Line Segment A2:
Line segments A2 and other potentially relevant
transmission line utility corridor alternative line
segments, were the subject of earlier environmental
analysis as part of the Fourmile Hill Project EIS/EIR.
The Fourmile Hill Project EIS/EIR analysis of the
effects on visual resources of utility corridor
transmission line segments relevant to the Telephone
Flat Project is incorporated into this EIS/EIR by
reference. Those visual effects attributable to line
segment A2 are summarized below.
Impact 3.8.3.6.1-1 (Fourmile Hill Impact
described in Section 4.9.1): Vehicles and
equipment on forest roads during construction
and decommissioning of the transmission line
would result in a temporary visual effect.
Vehicles and equipment on forest roads during
operation of the transmission line would not
result in visual impacts. Additionally, the
helicopter that would be used to erect poles and
string wire of the transmission line may be seen
from a variety of forest roads and recreational
destinations points such as the Medicine Lake
Recreational Area and the Lava Beds National
Monument.
Significance of the Impact: The visibility of the
construction vehicles and equipment would be a
short-term adverse, but less than significant
visual impact. No mitigation measure is required.
Impact 3.8.3.6.1-2 (Fourmile Hill Impact
described in Section 4.9.7): The upper portions
of the poles and conductors (during pole erection
and wire stringing) along a mile portion of
transmission line segment A2 would be visible
from Lyons Peak Loop Road (KOP 12) during
construction. The view from this KOP would be
from an elevated position looking down on the
transmission line, against a forest backdrop.
While not visible from any KOP, line segment
A2 would cross Glass Mountain in the vicinity of
the Glass Mountain Lava Flow, which has a
VQO of Preservation. Line segment A2 would
pass a gap between the main portion of the lava
flow on the east and a small remnant portion of
the lava flow on the west. This gap between the
two portions of the lava flow has a VQO of
Modification. Line segment A2 would not
actually cross the lava flow and the area that has
a VQO of Preservation.
During operation, the visibility of the
transmission line from Lyons Peak Loop Road
would be similar to that described for
construction, except that structures would be
fully erected and would be maintained for the
life of the project. Operation of the transmission
line involving maintenance activities such as tree
trimming and maintenance vehicle activity
within the right-of-way or along access roads
may be visible from KOP 12. However, these
temporary activities (expected to occur twice a
year in the spring and fall) would not impact the
overall visual characteristics or views from the
Lyons Peak Loop Road vantage point.
The presence of the transmission line segment
A2 over the life of the project would create a
long-term inconsistency with the VQO of Partial
Retention that occurs along segments in areas
visible from KOP 12.
Similar to construction, short-term adverse visual
effects could occur with decommissioning as a
result of dismantling and removing transmission
line facilities. The ultimate removal of facilities
and revegetation of disturbed areas, associated
with decommissioning, would restore the
transmission line route to pre-project conditions,
which is considered a beneficial effect. However,
long-term (50 to 70 years), readily evident
contrast would remain between the mature forest
canopy that exists in the project area and areas
cleared for the project, as it would take many
years for the forest to return to pre-project
conditions.
Significance of the Impact: Construction and
decommissioning effects would be considered a
short-term adverse visual impact. The visibility
of transmission line facilities and right-of-way
clearance for line segment A2 from Lyons Peak
Road would be a significant impact that can be
mitigated to a less than significant level. The
following mitigation measure would reduce the
visibility of the proposed transmission line from
Lyons Peak Loop Road.
|
-
Measure 3.8.3.6.1-2 (Fourmile Hill Measure
4.9.4a): For the entire transmission line route,
implement the following measures to minimize
the visual effects of right-of-way vegetation
clearance and transmission line facilities:
- To minimize the need for excessive
vegetation clearing from the transmission
line right-of-way, prepare a detailed
transmission line clearing plan for review
and approval by the USFS that takes into
account basic principles of feathering and
scalloping of the transmission line
right-of-way;
- Prior to clearing activities, identify those
trees to be removed, trees to be pruned, and
trees to remain within the transmission line
right-of-way, with review and approval by
USFS;
- To reduce reflection and glare, use only
non-specular conductors; and
- To reduce reflection and glare of metal
poles, use flat paint or integrated material
coloring except where safety colors are
required by code.
|
|
3.8.3.6.2 Environmental Consequences of Route 2 (Line Segments D2 + B2*)
|
|
Telephone Flat Project Alternative Transmission Line
Route 2 is composed of initial line segment D2 and
utility corridor line segment B2*.
Line Segment D2:
The visual effects and visibility of line segment D2 as
it relates to the Proposed Action, Alternative Power
Plant Site A, and Alternative Power Plant Site B is
described above in the impact assessment for each of
those power plant site alternatives.
Line Segment B2:
Line segments B2 and other potentially relevant
transmission line utility corridor alternative line
segments, were the subject of earlier environmental
analysis as part of the Fourmile Hill Project EIS/EIR.
The Fourmile Hill Project EIS/EIR analysis of the
effects on visual resources of utility corridor
transmission line segments relevant to the Telephone
Flat Project is incorporated into this EIS/EIR by
reference. Those visual effects attributable to line
segment B2 are summarized below.
Except for the difference in transmission line length,
the adverse effects of the Alternative Route 2 on
visual resources would be similar to those described
for Route 1.
-
Impact 3.8.3.6.2-1 (Fourmile Hill Impact
described in Section 4.9.1): Vehicles and
equipment on forest roads during construction
and decommissioning of the transmission line
would result in a temporary visual effect.
Vehicles and equipment on forest roads during
operation of the transmission line would not
result in visual impacts. Additionally, the
helicopter that would be used to erect poles and
string wire of the transmission line may be seen
from a variety of forest roads and recreational
destinations points such as the Medicine Lake
Recreational Area and the Lava Beds National
Monument.
Significance of the Impact: The visibility of the
construction vehicles and equipment would be a
short-term adverse, but less than significant
visual impact. No mitigation measure is required.
Impact 3.8.3.6.2-2: Line segment B2 would
cross and be seen from the Lyons Peak Loop
Road (Forest Roads 44N53 and 44N99) at two
locations, where it crosses Primary Forest Route
97 (KOP 13) as well as from Forest Road
43N14. Line segment B2 would also be visible
from the Timber Mountain Lookout (KOP 15).
Significance of the Impact: The visual impact
of line segment B2 would be considered
significant. Implementation of Mitigation
Measures 3.8.3.6.1-2 and 3.8.3.6.2-1 where the
transmission line crosses Forest Roads 44N53,
44N99, 43N14, and Primary Forest Route 97
(KOP 13) would reduce this impact to a
less-than-significant level. While the
transmission line facilities would remain evident,
they would be consistent with the VQOs of
Partial Retention and Modification. The facilities
would also not strongly contrast with the
characteristic landscape features in the area.
Measure 3.8.3.6.2-2 (Fourmile Hill Measure
4.9.4b): The following measures shall be
implemented at road crossings in order to
minimize the establishment of a visual corridor
from vegetation clearing under the conductor,
minimize views down the transmission line
right-of-way, and reduce the dominance of the
transmission line:
- For each transmission pole immediately
adjacent to the road, use self-supporting
single steel poles rather than H-frame poles;
- Site transmission line poles as far away as
practical from either side of the road;
redirect the transmission line right-of-way
from the two poles adjacent to the road at a
sufficient angle so that only that portion of
the right-of-way between the two poles
nearest the road may be visible from the
road;
- Retain all trees within the right-of-way
between 5 feet and 12 feet in height
depending upon the height of the conductors
in that segment (30 or 37 feet clearance
between the conductor and the ground); and
- Regrade to create designed earth berm
and/or native trees and understory
vegetation within 100 feet on either side of
the roadway at a density, size, and growth
rate sufficient to screen views into the
right-of-way from the roadway within a
3-year period.
|
|
3.8.3.6.3 Unavoidable Adverse Impacts of Alternative Transmission Line Routes
|
|
There are no unavoidable adverse impacts of
Alternative Transmission Line Routes related to
visual resources.
|
|
3.8.3.7 No Action Alternative
|
|
3.8.3.7.1 Environmental Consequences of the No Action Alternative
|
|
The Project would not be constructed if the No
Action Alternative is selected, and thus there would
be no effects on visual resources from the No Action
Alternative.
|
Telephone Flat Geothermal Development Project Final EIS/EIR
 |
|
|