      
|
Telephone Flat Geothermal Development Project Final EIS/EIR
|
Table 3.7.14: Estimated Noise Levels at Sensitive Biological Receptor Locations from Power Plant Operations
|
|
Biological Receptor Locationa
|
Sound Levels/Octave Band in dB
|
Overall (Leq) in dBA
63 Hz
|
125 Hz
|
250 Hz
|
500 Hz
|
1 Khz
|
2 Khz
|
4 Khz
|
8 Khz
|
BS-1E-NGH
|
55
|
55
|
51
|
47
|
41
|
34
|
17
|
0
|
48
|
BS-2E-TB
|
38
|
35
|
29
|
20
|
2
|
0
|
0
|
0
|
24
|
BS-3N-OS
|
50
|
49
|
45
|
41
|
33
|
22
|
0
|
0
|
42
|
BS-4S-NSO
|
47
|
46
|
41
|
36
|
26
|
12
|
0
|
0
|
37
|
BS-5S-PYN
|
47
|
47
|
42
|
37
|
28
|
14
|
0
|
0
|
38b
|
BS-6SW-BE
|
39
|
37
|
31
|
23
|
6
|
0
|
0
|
0
|
26
a The biological receptors/species of concern are not identified to protect the receptors from potential harassment or vandalism.
b Terrain acting as a noise barrier is effective at this site. Terrain barriers are generally ineffective at the other sites.
| | | | | | | | |
|
Construction of the well pads and well
drilling would be expected to increase noise
levels at sensitive biological sites. The noise
increase is inversely proportional to the
distance between the source and receptor.
Power plant operations would also increase
noise level at sensitive biological sites but
less than the increases associated with well
pad construction and drilling. Although well
pad construction would be noisier than well
drilling and power plant operational noises,
it is expected to be intermittent and of
relatively short duration (about two weeks).
Noise levels at the sensitive biological sites
would be higher during well drilling than
during power plant operations. The effects
of noise on biological sensitive species is
addressed in the biological resource section
(see Section 3.3).
Engineering or administrative measures
should be considered as an alternative to
moving a well pad location to reduce noise
effects because a significant reduction (6 dB
or more) of noise at a well pad would
require very large changes in well pad
location.
|
|
3.7.3.3.2 Unavoidable Adverse Impacts of the Proposed Action
|
|
Even with mitigation, noise levels at human receptor
locations and sensitive biological sites would
increase with the Project.
|
|
3.7.3.4 Alternative Power Plant Site A
|
|
3.7.3.4.1 Consequences of Alternative Power Plant Site A
|
|
Alternative Site A would locate the power plant site
eastward about ¼-mile of the Proposed Action site.
This would include only minor changes in well pad
locations. Therefore, this section focuses only on the
effects of the different power plant location.
Relocation of the power plant would not affect noise
produced by other Project operations at other
locations, such as well pad construction noise or well
drilling noise.
Consequences of Construction and Operation Noise
at Human Receptor Locations From Site A:
As shown in Table 3.7.5, construction noise levels at
the four human receptor locations are expected to
increase with construction at the Alternative Site A
power plant location rather than at the Proposed
Action location. Noise levels are expected to be
higher if the power plant is at the Alternative A
location because the power plant would be at an
elevation that is about 100 feet higher than the
Proposed Action location (7,070 feet versus 6,970
feet). This higher elevation results in lower noise
reductions due to terrain barriers. Thus, the estimated
noise levels of the receptors are somewhat higher
even though the distance is greater between the
Alternative Site A location and any human receptor
location than is the case with the Proposed Action
power plant site.
Noise levels estimated to result from the power plant
operating at the Proposed Action site and the two
Project Alternative locations are provided in
Table 3.7.8. As presented in previous tables, the
noise levels associated with power plant operations
are lower than those from construction. The pattern
of noise level increases at the human receptor
locations is, on average, slightly higher for
Alternative Site A than the Proposed Action and the
rationale follows that described above for
construction-related noise.
|
|
Power plant operational noise from the Alternative
Site A location should not be audible at any of the
human receptor locations because the noise levels are
significantly less than ambient (See Table 3.7.1).
By contrast, construction noise may be relatively
more audible from Alternative Site A than from the
Proposed Action site at three of the four receptor
locations (the two residential locations and the
campgrounds at Bullseye and Blanche Lakes); the
exception is the campground on the north side of
Medicine Lake. The increase in audibility does not
exceed 10 dB.
-
Impact 3.7.3.4-1: Hikers and other forest
visitors within about ½-mile of areas of active
surface disturbance would be able to hear Project
construction activities. These sounds would be
audible but visitors are expected to be transient
and the adverse effects of Project construction
noise would be temporary.
Significance of the Impact: This impact is
considered to be below the level of significance
and no mitigation measures are required.
Similarly, the noise levels estimated at any of the
four receptor locations do not attain Leq = 54 dBA,
which is considered the threshold for significance
according to Siskiyou County.
-
Impact 3.7.3.4-2: Under some worst case
conditions, sound may be audible at some human
receptor locations near Medicine Lake. In
general, well drilling noise would be louder than
operational noise from the power plant. The
maximum projected noise levels would not
exceed Siskiyou County’s noise limit (Leq = 54
dBA).
Significance of the Impact: This impact is
below the level of significance and no mitigation
measures are required, but, the following other
measure is provided to reduce the adverse effects
of the impact.
Other Measure 3.7.3.4-2a: Project Applicant
shall erect temporary noise shields around
portions of the drilling rig during well drilling to
further reduce the noise effects on human
receptors. Generally, noise shields would be
needed on only those wells identified herein as
being dominant (i.e., wells at well pads 73-13,
16-18, 87-13, 51-18 and 56-18).
Other Measure 3.7.3.4-2b: The Project
Applicant shall install “residential grade”
mufflers on the noisiest well drilling equipment.
Consequences of Construction and Operation Noise
at Native American Vision Quest Sites From Site A:
The estimated noise levels at the traditional cultural
site location 17 and location 20 noise receptors
during construction of the two nearest well pads and
the Alternative Site A power plant site are shown in
Table 3.7.11. The Table also provides estimates of
the sound levels during the drilling of wells at the
two nearest well pads to the receptor locations. The
Table shows that the projected noise levels at
location 17 are uniformly lower than those estimated
for location 20. Noise levels due to construction are
estimated to be at least 10 dBA higher than ambient
and would be expected to be audible.
Project noise levels at the traditional cultural site
location 17 and location 20 receptor locations during
power plant operations are also shown in
Table 3.7.11. At location 17, the estimated noise
levels are less than ambient levels regardless of the
alternative power plant site selected. In contrast,
noise levels would be more audible at location 20
from Alternative Power Plant Site A than from the
proposed power plant site.
Noise levels at the identified Native American vision
quest sites would be higher during well drilling and
construction than during power plant operations. The
effects of noise at these sites is addressed in the
Native American Values section (see Section 3.6.2.7).
Consequences of Construction and Operation Noise
on Sensitive Biological Species From Site A:
Since terrain barriers were assumed not to be
functioning for five of the six SBS receptor locations
(SBS BS-5S-PYN is the exception), the changes in
noise level at the various SBS locations reflect the
changes in distance relative to the distance between
the Project Alternative Power Plant Site A location
and the SBS receptor locations. For example, the
Proposed Action power plant site is farthest from
SBS BS-2E-TB, and Alternative Site A is closer to
that receptor. Therefore, as shown in Table 3.7.6,
construction noise levels become louder as the power
plant location moves from 39 dBA at the Proposed
Action location to 41 dBA at Alternative Site A.
|
|
In contrast, the Proposed Action is nearest to SBS
receptor location BS-4S-NSO, while Alternative
Site A is farther from this SBS location. As shown in
Table 3.7.9, power plant operational noise decreases
as the power plant location moves from the Proposed
Action location to the Project Alternative Power
Plant Site A location.
Alternative Site A is nearer to SBS receptor location
BS-1E-NGH than are either the Proposed Action or
the Alternative Site B power plant sites. Thus, as may
be seen in both Tables 3.7.6 and 3.7.9, the noise
levels during construction or when the power plant is
operating are expected to be loudest when the power
plant is located at Alternative Site A and quieter at
either of the other two locations.
The effects of the increases in Project-related
construction and operation noise levels on some
sensitive wildlife and wildlife habitat resulting from
moving the power plant site from the Proposed
Action location to the Alternative Site A location is
discussed in Section 3.3.
|
|
3.7.3.4.2 Unavoidable Adverse Impacts of Alternative Power Plant Site A
|
|
Even with mitigation, noise levels at human receptor
locations and sensitive biological sites would
increase with the Project.
|
|
3.7.3.5 Alternative Power Plant Site B
|
|
Alternative Site B would locate the power plant site
eastward about ½-mile of the Proposed Action site.
This would include only minor changes in well pad
locations. Only one new well pad (77-18), not
provided for in the Proposed Action or Alternative
Site A would be constructed if Alternative Site B is
implemented. Therefore, this section primarily
focuses only on the effects of the different power
plant location. Relocation of the power plant should
would not affect noise produced by other Project
operations at other locations, such as well pad
construction noise or well drilling noise.
Consequences of Construction and Operation Noise
at Human Receptor Locations From Site B:
As shown in Table 3.7.5, construction noise levels at
the four human receptor locations are expected to
decrease with construction at the Alternative Site B
power plant location rather than either the Proposed
Action or Alternative Site A locations. The elevation
of 7,050 feet for the Alternative Site B location is 20
feet lower than and slightly north of the Alternative
Site A location. At this elevation and location, terrain
barriers are more effective than at Alternative Site A
and Alternative Site B is much farther from the
human receptor locations than is the Proposed Action
location. As a result, construction noise levels at
Alternative Site B are shown in Table 3.7.5 to be
lower than at either the Proposed Action or
Alternative Site A locations. As is shown and
explained in the table, the exception is at the
campground at the north side of Medicine Lake, for
which terrain does not produce an effective barrier. In
addition, well pad 77-13 is unique to Alternative
Site B and well pad construction noise may be
audible at times at the campgrounds at Bullseye and
Blanche Lakes. The increase in audibility does not
exceed 10 dB, rather it is at the ambient level of
34 dBA.
-
Impact 3.7.3.5-1: Hikers and other forest
visitors within about ½-mile of areas of active
surface disturbance would be able to hear Project
construction activities. These sounds would be
audible but visitors are expected to be transient
and the adverse effects of Project construction
noise would be temporary.
Significance of the Impact: This impact is
considered to be below the level of significance
and no mitigation measures are required.
Noise levels estimated to result from the power plant
operating at the Proposed Action site and the two
Project Alternative locations are provided in
Table 3.7.8. As presented in previous tables, the
noise levels associated with power plant operations
are lower than those from construction. The pattern
of noise level increases at the human receptor
locations is slightly lower for Alternative Site B than
either the Proposed Action or Alternative Site A and
the rationale follows that described above for
construction-related noise.
Power plant operational noise from the Alternative
Site B location should not be audible at any of the
human receptor locations because the noise levels are
significantly less than ambient (See Table 3.7.1).
|
Similarly, the noise levels estimated at any of the
four human receptor locations do not attain Leq = 54
dBA, which is considered the threshold for
significance according to Siskiyou County.
-
Impact 3.7.3.5-2: Under some worst case
conditions, sound may be audible at some human
receptor locations near Medicine Lake. In
general, well drilling noise would be louder than
operational noise from the power plant. The
maximum projected noise levels would not
exceed Siskiyou County’s noise limit (Leq = 54
dBA).
Significance of the Impact: This impact is
below the level of significance and no mitigation
measures are required, but, the following other
measure is provided to reduce the adverse effects
of the impact.
Other Measure 3.7.3.5-2a: Project Applicant
shall erect temporary noise shields around
portions of the drilling rig during well drilling to
further reduce the noise effects on human
receptors. Generally, noise shields would be
needed on only those wells identified herein as
being dominant (i.e., wells at well pads 73-13,
16-18, 87-13, 51-18 and 56-18).
Other Measure 3.7.3.5-2b: The Project
Applicant shall install “residential grade”
mufflers on the noisiest well drilling equipment.
Consequences of Construction and Operation Noise
at Native American Vision Quest Sites From Site B:
The estimated noise levels at the traditional cultural
site location 17 and location 20 receptors during
construction of the two nearest well pads and the
Alternative Site B power plant site are shown in
Table 3.7.11. The Table also provides estimates of
the sound levels during the drilling of wells at the
two nearest well pads to the receptor locations. The
Table shows that the projected noise levels at
location 17 are uniformly lower than those estimated
for location 20. Noise levels due to construction are
estimated to be at least 10 dBA higher than ambient
and would be expected to be audible.
Project noise levels at the traditional cultural site
location 17 and location 20 receptor locations during
power plant operations are also shown in
Table 3.7.11. At location 17, the estimated noise
levels are less than ambient levels regardless of the
alternative power plant site selected. In contrast,
noise levels would be more audible at location 20
from Alternative Site B than from either the proposed
power plant site or from Alternative Site A.
Noise levels at the identified Native American vision
quest sites would be higher during well drilling and
construction than during power plant operations. The
effects of noise at these sites is addressed in the
Native American Values section (see Section 3.6.2.7).
Consequences of Construction and Operation Noise
on Sensitive Biological Species From Site B:
Since terrain barriers were assumed not to be
functioning for five of the six SBS receptor locations
(SBS BS-5S-PYN is the exception), the changes in
noise level at the various SBS locations reflect the
changes in distance relative to the distance between
the Project Alternative Power Plant Site B location
and the SBS receptor locations. For example, the
Proposed Action power plant site is farthest from
SBS BS-2E-TB, and Alternative Site B is closest to
that receptor. Therefore, as shown in Table 3.7.6,
construction noise levels become louder as the power
plant location moves from 39 dBA at the Proposed
Action location to 43 dBA at Alternative Site B.
In contrast, the Proposed Action is nearest to SBS
receptor location BS-4S-NSO, while Alternative
Site B is farthest from this SBS location. As shown in
Table 3.7.9, power plant operational noise decreases
as the power plant location moves from the Proposed
Action location to the Project Alternative Power
Plant Site B location.
Alternative Site B is nearer to SBS receptor location
BS-1E-NGH than the Proposed Action power plant
site but further than the Alternative Site A power
plant site. Thus, as may be seen in both Tables 3.7.6
and 3.7.9, the noise levels during construction or
when the power plant is operating are expected to be
generally quieter when the power plant is located at
Alternative Site B than at either of the other two
locations.
The effects of Project-related construction and
operation noise levels on some sensitive wildlife and
wildlife habitat resulting from moving the power
plant site from the Proposed Action location to the
Alternative Site B location is discussed in
Section 3.3.
|
|
3.7.3.5.1 Unavoidable Adverse Impacts of Alternative Power Plant Site B
|
|
Even with mitigation, noise levels at human receptor
locations and sensitive biological sites would
increase with the Project.
|
|
3.7.3.6 Alternative Transmission Line Routes
|
|
Previous Transmission Line Impact Assessment:
As discussed in Section , the transmission line
originating at the Telephone Flat Project power plant
site would be routed to interconnect with a
transmission line located within one of the six
alternative utility corridors evaluated in the Fourmile
Hill Project EIS/EIR to be selected by the agencies as
the preferred utility corridor between the Medicine
Lake Highlands and the existing BPA Malin-Warner
transmission line (BLM et al. 1998). The Fourmile
Hill Project EIS/EIR evaluated seven different
possible line segments (segments A1, A2, A3, B1,
B2, C1 and C2) which could be used in different
combinations to comprise the preferred utility
corridor. Only five of these line segments (A2, B1,
B2, C1 and C2) could possibly be used by the
Telephone Flat Project, and the Noise analysis from
the Fourmile Hill Project EIS/EIR of the five line
segments which could be potentially used by the
Telephone Flat Project are incorporated by reference
into this EIS/EIR (see pages 3-201 through 3-207,
and 4-254 through 4-270 of the Fourmile Hill Project
EIS/EIR; BLM et al. 1998). The findings of the
earlier assessment are also summarized in Exhibit 4
of this EIS/EIR (See Table S-5, pages S-30 to S-36,
in Exhibit 4).
Under Fourmile Hill Project Alternatives 1 and 3, the
construction and decommissioning of the three
transmission line towers of line segment C1 nearest
to residences in Tionesta, are expected to require less
than one week for each phase. During this period,
daytime noise levels from these activities are
estimated to be about 61 dBA at the residence
approximately 1,500 feet from the power lines. The
noise level would be about 57 dBA at the residence
farthest from the power lines. Noise levels at both
residences would exceed Modoc County's 48 dBA
limit ( 65 Ldn) for residential uses if that noise level
was present over 24 hours. However, tower line
construction and decommissioning are expected to
require roughly 9 hours per day, and the average
noise level over the 24-hour period is calculated to be
Ldn = 53, which is well below the County's limit.
Although the construction and decommissioning
noise may be audible, it is expected to be of relatively
short duration (about 1 week for each Project phase)
and thus the impact on residents of Tionesta was
determined to be below the level of significance
(BLM et al. 1998).
Telephone Flat Project Route Alternatives:
If the agencies select one of the Fourmile Hill Project
utility corridor alternatives which route through the
Medicine Lake basin in close proximity to the
Telephone Flat Project (i.e., Alternatives 1 through
4), then the Telephone Flat Project would construct
either line segment D1 (if Alternatives 1 or 2 is
selected) or line segment D2 (if Alternatives 3 or 4 is
selected), and no specific agency decision on
transmission line route alternatives would need to be
made for the Telephone Flat Project. However, if the
Northern Utility Corridor for the Fourmile Hill
Project (i.e., Alternatives 5 or 6) is selected as the
agency-preferred utility corridor, then a second
decision for the Telephone Flat Project would need to
be made with respect to how to interconnect the
Telephone Flat Project transmission line with the
Northern Utility Corridor. Two alternative Telephone
Flat Project transmission line routes (Route 1 and
Route 2) are being considered for transporting power
generated from the Telephone Flat Project power
plant site to the Northern Utility Corridor.
The initial transmission line segments from the three
alternative power plant sites (i.e., Proposed Action,
Alternative Site A, and Alternative Site B) are
approximately the same. Transmission line
interconnection segment D1 goes north and west of
Alcohol Crater from each of the alternative power
plant sites to tie-in with the Fourmile Hill
Geothermal Project utility corridor line segment A2.
The D1/A2 line segments then comprise the proposed
Telephone Flat Project Transmission Line Alternative
Route 1 to the Northern Utility Corridor.
Transmission line interconnection segment D2 goes
east from each of the alternative power plant sites to
tie-in with the Fourmile Hill Geothermal Project
utility corridor line segment B2*. The D2/B2* line
segments then comprise Telephone Flat Project
Transmission Line Alternative Route 2 to the
Northern Utility Corridor.
|
|
3.7.3.6.1 Environmental Consequences of Route 1 (Line Segments D1 + A2)
|
|
Route 1 would be a total of about 4.95 miles of
transmission line of transmission line from the
Proposed Action power plant site to the Northern
Utility Corridor. Except for the differences
attributable to the different distances of the
alternative transmission line routes, there are no
substantive additional adverse noise effects
anticipated as a result of either of the Alternative
Transmission Line Routes.
Line Segment D1:
Line segment D1 is located entirely within the
Project wellfield area, and the effects for line
segment D1 would be the same as those described for
the Proposed Action.
Line Segment A2:
The noise effects of the construction, operation, and
decommissioning the relevant transmission line
segments comprising the alternative utility corridors
were evaluated as part of the EIS/EIR prepared for
the Fourmile Hill Project (BLM et al. 1998). The
findings of that analysis for transmission line
segments relevant to the Telephone Flat Project are
incorporated by reference into this EIS/EIR. Noise
impacts associated with line segment A2 are
summarized below.
-
Impact 3.7.3.6.1-1 (Fourmile Hill Impact
described in Section 4.14.1): For the proposed
transmission line, noise generated during project
construction would potentially result in a
short-term impact to forest users that may come
in close proximity to the transmission line during
construction. Construction activities would not
exceed County noise standards for more than a
week; this effect would occur only on a
short-term basis.
Operation of the proposed transmission line
would not result in the generation of noise and
therefore would not impact ambient noise levels
in the forest. Routine maintenance activities,
expected to occur twice a year, could produce
temporary noise increases, likely to be much
lower than construction noise levels. The
occasional presence of vehicles and equipment to
repair downed wires, damaged towers, or other
facilities (associated with snow, wind, and other
conditions) could also be present along the
transmission line. Noise levels from such
activities would likely be less than for
construction, but could result in adverse effects
on forest visitors using areas in close proximity
to such line repairs.
Similar to construction, decommissioning would
potentially result in a short-term effect.
Significance of the Impact: Noise impacts to
forest users that may come in close proximity to
the transmission line would be potentially
significant during construction and
decommissioning, but would be short-term in
nature. No significant impacts would occur to
sensitive receptors. The following other
measures would further reduce impacts to
sensitive receptors.
Measure 3.7.3.6.1-1a (Fourmile Hill Measure
4.12.2a): The Project Applicant would use
feasible noise controls on standard construction
equipment to minimize potential noise effects to
existing nearby residences. Impact tools would
be shielded or shrouded when practicable, and
equipment would have a muffled exhaust.
Measure 3.7.3.6.1-1b (Fourmile Hill Measure
4.12.2c): The Project Applicant would
implement site-specific measures to respond to
complaints and minimize future disturbances of
nearby residences. Such measures could include
changing the location of stationary equipment,
installing acoustic barriers around stationary
construction noise sources, shutting off idling
equipment, and rescheduling construction
activity.
|
|
3.7.3.6.2 Environmental Consequences of Route 2 (Line Segments D2 + B2*)
|
|
Route 2 would be a total of about 12.26 miles of
transmission line from the Proposed Action power
plant site to the Northern Utility Corridor. Except for
the differences attributable to the different distances
of the alternative transmission line routes, there are
no substantive additional adverse noise effects
anticipated as a result of either of the Alternative
Transmission Line Routes.
Line Segment D2:
Line segment D2 is located entirely within the
Project wellfield area, and the effects for line
segment D2 would be the same as those described for
the Proposed Action.
Line Segment B2:
The noise effects of the construction, operation, and
decommissioning the relevant transmission line
segments comprising the alternative utility corridors
were evaluated as part of the EIS/EIR prepared for
the Fourmile Hill Project (BLM et al. 1998). The
findings of that analysis for transmission line
segments relevant to the Telephone Flat Project are
incorporated by reference into this EIS/EIR. Noise
impacts associated with line segment B2 are
summarized below.
Except for the difference in transmission line length,
the adverse effects of the Alternative Route 2 on
noise and vibration resources would be similar to
those described for Route 1.
-
Impact 3.7.3.6.2-1 (Fourmile Hill Impact
described in Section 4.14.1): For the proposed
transmission line, noise generated during project
construction would potentially result in a
short-term impact to forest users that may come
in close proximity to the transmission line during
construction. Construction activities would not
exceed County noise standards for more than a
week; this effect would occur only on a
short-term basis.
Operation of the proposed transmission line
would not result in the generation of noise and
therefore would not impact ambient noise levels
in the forest. Routine maintenance activities,
expected to occur twice a year, could produce
temporary noise increases, likely to be much
lower than construction noise levels. The
occasional presence of vehicles and equipment to
repair downed wires, damaged towers, or other
facilities (associated with snow, wind, and other
conditions) could also be present along the
transmission line. Noise levels from such
activities would likely be less than for
construction, but could result in adverse effects
on forest visitors using areas in close proximity
to such line repairs.
Similar to construction, decommissioning would
potentially result in a short-term effect.
Significance of the Impact: Noise impacts to
forest users that may come in close proximity to
the transmission line would be potentially
significant during construction and
decommissioning, but would be short-term in
nature. No significant impacts would occur to
sensitive receptors. The following other
measures would further reduce impacts to
sensitive receptors.
Measure 3.7.3.6.2-1a (Fourmile Hill Measure
4.12.2a): The Project Applicant would use
feasible noise controls on standard construction
equipment to minimize potential noise effects to
existing nearby residences. Impact tools would
be shielded or shrouded when practicable, and
equipment would have a muffled exhaust.
Measure 3.7.3.6.2-1b (Fourmile Hill Measure
4.12.2c): The Project Applicant would
implement site-specific measures to respond to
complaints and minimize future disturbances of
nearby residences. Such measures could include
changing the location of stationary equipment,
installing acoustic barriers around stationary
construction noise sources, shutting off idling
equipment, and rescheduling construction
activity.
|
|
3.7.3.6.3 Unavoidable Adverse Impacts of the Alternative Transmission Line Routes
|
|
Either of the Alternative Transmission Line Routes
would result in increased construction, maintenance,
and decommissioning noise effects. None of these
noise effects is considered a significant impact.
|
|
3.7.3.7 No Action Alternative
|
|
3.7.3.7.1 Consequences of the No Action Alternative
|
|
If the Project is not constructed, Project-related
changes in noise levels at both the human receptors
and sensitive biological sites would not occur.
However, noise levels may increase as a result of an
expected expansion of recreational usage of the
Medicine Lake facilities during both the summer and
winter seasons.
|
|
3.7.3.7.2 Unavoidable Adverse Impacts of the No Action Alternative
|
|
There would be no unavoidable noise impacts as a
result of the No Action Alternative.
|
Telephone Flat Geothermal Development Project Final EIS/EIR
 |
|
|