      
|
Telephone Flat Geothermal Development Project Final EIS/EIR
|
2.7.6 Underground Electrical Transmission Lines
|
|
The 230-kV transmission lines for the Proposed
Action would be a typical overhead transmission line
strung on towers (see Section 2.2.5). While it is
technically feasible to place an electrical transmission
line underground, the cost of constructing and
maintaining and underground transmission line are
high and would be prohibitively expensive in areas of
high terrain and shallow soil with near-surface
bedrock such as the conditions observed in the
Project vicinity and along the alternative transmission
line corridors proposed for transporting electrical
energy from the Medicine Lake Highlands to the
BPA Malin-Warner transmission line.
|
|
The primary advantage of an underground
transmission line is the reduced visibility of the line,
but an underground line would also prevent potential
collisions and electrocution of birds associated with
overhead transmission lines. Disadvantages of an
underground transmission line are similar to those
described for the underground pipelines (see
Section 2.7.5). In areas where bedrock is near the surface
construction would include blasting. Construction of
trenches would cause significant surface disturbance
and soil erosion potential along the entire
transmission line route, and until vegetation is
reestablished, disturbed areas along the line would
remain visible. New access roads would be needed
for construction and maintenance of the buried line.
Installation, repair and maintenance of the buried
lines requires more time and cost compared to
overhead lines and could extend the down-time that
the power plant is off-line and not generating
electricity.
|
|
Buried transmission lines are also susceptible to
geological hazards not typically associated with
overhead transmission lines, including: (a) possible
exposure to damage in rough terrain from soil
erosion; (b) damage from landslides on steep slopes;
(c) seismic or tectonic activity could result in damage
or rupture; and (d) thermal instability could result
from landslide overburden on top of the backfill that
could hamper dissipation of heat through the backfill
to the atmosphere and could result in line damage,
burnout or reduced capacity (Dames & Moore 1981).
|
|
Other problems unique to a buried transmission line
would include: (a) access to the line in areas where
deep snow can accumulate such as the Medicine
Lake Highlands; (b) trenching and burying the
transmission line through stream or ephemeral
channels could adversely affect creek bottom,
increase sedimentation and potentially affect water
quality down gradient.
|
|
Based on the technical and economic constraints and
the increased environmental effects associated with
underground transmission lines in a rough terrain
area such as Medicine Lake Highlands, this
alternative was eliminated from detailed study in the
EIS/EIR.
|
|
2.8 Preferred Alternative
|
|
2.8.1 Environmentally Superior Alternative and Environmentally Preferable Alternative
|
|
CEQA regulations state that if the No Project
alternative (i.e., the No Action Alternative) is the
Environmentally Superior Alternative, then the EIR
must also identify an Environmentally Superior
Alternative from among the other alternatives (CEQA
Guidelines Section 15126(d)(4)). Similarly, NEPA
implementing regulations state that NEPA lead
agencies must identify the alternative or alternatives
considered to be environmentally preferable in the
Record of Decision (ROD) in cases where an EIS is
required (40 CFR 1505.2(b)).
|
|
Based on the analysis provided in this EIS/EIR, the
Project Alternative that would result in the fewest
significant environmental impacts would be the No
Action Alternative and would, therefore, be
considered the Environmentally Superior Alternative;
however, CEQA requires that an Environmentally
Superior Alternative also be selected from among the
other action alternatives. The Environmentally
Superior Alternative that would cause the least
damage to the biological and physical environment,
and that would best protect, preserve, and enhance
historic resources, cultural resources, and other
natural resources, while meeting both the objectives
of, and the purpose and need for, the Project, would
be the Proposed Action (see Executive Summary
Section “Environmentally Preferred Alternative”).
|
|
Assuming the Environmentally Superior Alternative
identified in the Fourmile Hill Project EIS/EIR
(BLM et al. 1998) is approved and the transmission
line is timely constructed, then a Northern Utility
Corridor would exist, and the Environmentally
Superior Alternative route for interconnecting the
Telephone Flat Project transmission line to the
Northern Utility Corridor would be Alternative
Transmission Line Route 1 (see Executive Summary
Section “Environmentally Preferred Alternative”).
|
|
2.8.2 Agency Preferred Alternative
|
|
A Draft EIS may identify a NEPA lead agency’s
Preferred Alternative or alternatives, if one or more
exists; and the Final EIS must identify the Preferred
Alternative unless another law prohibits the
expression of such a preference (40 CFR 1502.14(e)).
There is no requirement for a CEQA lead agency to
identify a Preferred Alternative under CEQA
regulations.
|
|
Based on the findings in this EIS/EIR and agency and
public comments received on the Draft EIS/EIR, the
federal lead agencies have identified the Proposed
Action as the Agency Preferred Alternative and
Alternative Transmission Line Route 1 as the Agency
Preferred Alternative route for interconnecting the
Telephone Flat Project power plant site to the
proposed Northern Utility Corridor (see Executive
Summary Section “Environmentally Preferred
Alternative”).
|
Telephone Flat Geothermal Development Project Final EIS/EIR
 |
|
|