      
|
Telephone Flat Geothermal Development Project Final EIS/EIR
|
2.2.6.2 Wellfield Facilities Decommissioning
|
|
All wellfield surface facilities including production
and injection pipelines and structures would be
dismantled and removed. The geothermal production
and injection wells would be plugged and abandoned
in conformance with BLM requirements, well pad
sumps would be closed, and well pads would be
restored as discussed in Section 2.2.3.7. The groundwater
well would be (a) preserved for other CEGC uses, (b)
closed in conformance with applicable water well
abandonment requirements, or (c) donated to the
USFS as a supplemental local water source. Below
ground pipelines or facilities would be either
removed or left buried in place to minimize impacts
as directed by the USFS.
|
|
Decommissioning would be scheduled to take place
at the end of the operation phase (i.e., about 50±
years after commencement of Project operations), but
various factors could extend the life of the Project
and delay Project decommissioning. These factors
would include an increase in the selling price of
geothermal energy, modifications to the proposed
facility that would increase the production capacity of
the wells, the ability to access geothermal fluid with
existing wells, or a decrease in the cost of production.
Other factors that could extend the operational life of
the Project include continued demand for power,
extension or renewal of the power sales contract, and
reservoir longevity. It is possible that the power plant
could continue operating while some of the wells
would be shut down. Conversely, decreased demand
for electrical power, failure to renew the power sales
contract, poor geothermal reservoir performance, or
other unanticipated adverse factors could decrease
the operational life of the Project. Project activities
and facilities would be the same regardless of
whether the operational life of the Project is shorter
or longer than the projected 50± years of anticipated
operation phase.
|
|
2.2.6.4 Financial Assurance
|
|
Financial assurances for various aspects of the
Project that could be applicable to Project
decommissioning and site restoration include bonds,
or other instruments of financial assurance, required
by the responsible agencies. CEGC, as a federal
geothermal lessee, is required to submit a bond to the
BLM prior to conducting drilling operations on a
federal geothermal lease (43 CFR 3206.1-1). CEGC
has already submitted a $150,000 bond (Bond No.
U436101) in compliance with these regulations
(Personal Communication — Sean Hagerty, BLM
State Office; January 28, 1998). In addition to the
lease bond, CEGC would be required to submit a
power plant site license bond of not less than
$100,000 prior to the development of the power plant
site (43 CFR 3250.7).
|
|
Other bonds or instruments of financial assurance
would be expected to be required by other
responsible agencies as a condition of their respective
permits and approvals.
|
|
2.2.7 Water Use and Hydrologic Monitoring
|
|
2.2.7.1 Water Consumption
|
|
As described in previous sections, fresh water from
the shallow groundwater aquifer in the Medicine
Lake basin would be used during well drilling, for
dust abatement, to fill the cooling tower basin prior to
startups, for fire protection, and for domestic
purposes during power plant operations. Estimates of
the water usage during the construction, operations,
and decommissioning phases of the Project are
presented in Table 2.2.8.
|
|
Geothermal fluid would be consumed during the
testing of geothermal wells (see Sections 2.2.3.2 and
3.2.3), and
steam condensate from the flashed fraction of the
geothermal fluid would be used for cooling water
makeup and consumed by evaporative cooling from
the cooling tower (see Table 2.2.2).
|
|
2.2.7.2 Proposed Hydrology Monitoring Plan
|
|
A plan for monitoring hydrologic and geothermal
resources in the vicinity of the Project has been
proposed by CEGC and submitted to the BLM and
USFS for consideration (see Exhibit 5). The plan
generally envisions collecting baseline data from
selected wells, lakes, and springs in the Project
vicinity on a semi-annual basis for a period of three
years, and annually thereafter. The plan also includes
collection of baseline meteorologic information from
an established meteorologic station within the Project
area; monitoring geothermal fluid and production and
injection; and monitoring the temperature of one of
the gas vents and the extent of non-vegetated areas in
the vicinity of the “Hot Spot” on the northwest flank
of Glass Mountain. Reports of the monitoring
activities would be prepared annually and submitted
to the BLM and the California Regional Water
Quality Control Board—Central Valley Region
(RWQCB).
|
|
The monitoring program is designed to monitor the
proposed geothermal Project activities and address
concerns regarding potential hydrologic effects of the
Project. The proposed monitoring plan is under
consideration by the agencies and may be amended
as a result of agency review and comments received
during the public review process for this EIS/EIR.
|
|
Table 2.2.8: Projected Freshwater Usage for Project Construction, Operations, and Decommissioning
|
|
Project Time Period
|
Activity
|
Volume of Shallow Groundwater Used
|
Construction (Approximately 1 year)
|
Construction of power plant and well pads
(includes dust abatement)
|
5,000,000 to 8,000,000 gallons per year
(15.3 to 24.5 ac-ft/yr)
|
|
Drilling of production and injection wells
|
6,720,000 gallons per year
(20.6 ac-ft/yr)
|
|
Fire protection
|
200,000 gallons (one time only)
(0.6 ac-ft)
|
Domestic uses
(non-drinking water)
|
1,300,000 gallons per year
(4.0 ac-ft/yr)
|
Construction Total:
(non-drinking water)
|
16,220,000 gallons over 1 year
(49.8 ac-ft)
|
|
Project Time Period
|
Activity
|
Volume of Shallow Groundwater Used
|
Operations (Approximately 50 years)
|
Drilling of production and injection wells
|
425,600 gallons per year
(1.3 ac-ft/yr)
|
|
Cooling water required at power plant startup
|
240,000 gallons (one time only)
(0.7 ac-ft)
|
|
Periodic recharge or partial recharge of
cooling water (less than twice per year)
|
400,000 gallons per year
(1.2 ac-ft/yr)
|
|
Domestic uses
(non-drinking water)
|
1,300,000 gallons per year
(4.0 ac-ft/yr)
|
|
Operations Total:
|
106,520,000 gallons over 50 years
(326.7 ac-ft)
Average: 6.5 ac-ft/yr
|
|
Project Time Period
|
Activity
|
Volume of Shallow Groundwater Used
|
Decommissioning
(approximately 3 years)
|
Domestic uses
(non-drinking water)
|
1,300,000 gallons per year
(4.0 ac-ft/yr)
|
|
Decommissioning Total:
|
3,900,000 gallons over 3 years
(12.0 ac-ft)
Average: 4.0 ac-ft/yr
|
|
Total Projected Freshwater Consumption for the Project:
|
127,400,000 gallons over 54 years
(390.8 acre-ft)
|
|
2.2.8.1 Project Exploration
|
|
Workers associated with exploration well drilling and
ongoing maintenance and testing of existing wells
would not be active before mid- to late-1999. Each
drill rig would require about 24 workers split into
two, 12-hour shifts or three, 8-hour shifts.
Exploration drilling, if any, would focus on the two
well pads (56-18 and 13-18) that were previously
approved for drilling. Well testing of new and
existing exploration wells (68-8, 31-17, and 87-13)
would require about five workers to set up the well
test and one worker to monitor the test. Exploration
activities would continue throughout the life of the
Project; however, once the development phase
begins, assuming the Project is approved by the
agencies, the exploration workers would be
considered part of the construction work force. It is
estimated that there would be up to 20 to 40 workers
associated with exploration drilling activities if wells
were to be drilled at each well pad concurrently.
|
|
2.2.8.2 Project Construction
|
|
The construction phase would be expected to begin
upon approval of the Project, weather permitting, and
development well drilling of both injection and
production wells would begin as soon as practical
following approval with one drill rig. Assuming
timely Project approval, this work could be
completed in late-1999. One to two drill rigs could
start up as early as late first quarter to early second
quarter of 1999. It is likely that a third drill rig would
be added in the late second quarter 1999. The drilling
work for 1999 would be completed in late-1999 prior
to the winter months. The same drilling program
would start up again in 2000 and continue until
sufficient production and injection capacity and
reserves are developed to support the Project. The
drilling schedule would be set back accordingly if
Project approval is delayed.
|
|
Power plant and transmission line site clearing would
begin following Project approval, weather permitting.
Power plant construction could begin in the early
spring (second quarter) of 1999. The construction
schedule would be set back accordingly if Project
approval is delayed. The final transmission line and
the pipeline construction, including site restoration
and revegetation, could be completed by the end of
the third quarter 2001. Assuming timely Project
approval, power plant operations could start as early
as the end of the second quarter 2001. In addition to
the construction crews, there could be additional
people on site including suppliers and agency
representatives. The construction workforce,
including the drilling work force, would peak
between 220 and 250 workers during the third quarter
of 1999, and an additional 30 non-construction
people could be on-site during this peak period.
Drilling operations would be 24 hours per day, seven
days per week, with a crew of approximately
8-12 personnel per 12-hour shift. Construction of the
transmission line and power plant would be during
daylight hours on approximately 12-hour shifts with a
maintenance crew working during the night shift on
equipment. Night construction would commence
after the turbine-generator building is constructed and
24-hour work schedules can be established for inside
the building. The construction schedule would be set
back accordingly if Project approval is delayed.
|
|
2.2.8.3 Project Operations
|
|
Normal power generation operations would require
about 25 permanent employees. Shifts would be
expected to include crews of seven personnel on
12-hour shifts. A third relief crew would also be used
to rotate the crews. In addition, to the 21 power plant
and wellfield operators comprising the three crews, it
is expected that there would be a site manager, and
engineering, mechanical, and maintenance staff who
would usually be on site during the day shift.
Approximately one-half of these positions would be
filled with trained operators from other CEGC
geothermal plants and about one-half would be filled
by local hires. The new employees would be hired in
the third quarter of 1999 with the plant expected to
begin startup operations by the end of the third
quarter of 2000. The operations schedule would be
set back accordingly if Project approval is delayed.
|
|
2.2.8.4 Project Decommissioning
|
|
The decommissioning phase of the geothermal
facility would require one-third to one-half of the
number of workers that would be required for the
construction phase. Decommissioning would take
about two to three years and would take place
approximately 50± years in the future after the
conclusion of the operation phase of the Project. The
operations phase would be expected to continue as
long as sufficient commercially suitable geothermal
resources are available and a power sales agreement
for the generated electricity exists.
|
|
2.3 Alternative Project Locations
|
|
Concern was raised during scoping regarding the
proximity of the proposed Project to the seasonal
residences and developed recreation areas near
Medicine Lake with respect to a perceived potential
for intrusional impacts from the Project, including:
noise, increased traffic, air emissions and resulting
odors, and the visibility of Project facilities. Members
of the public, comprised mostly of Medicine Lake
homeowners, requested that the Project be moved
further away from Medicine Lake. Alternative
locations were considered which would be responsive
to these concerns and also meet the purpose and need
for the Project. It was determined that the production
wells were generally located in that portion of the
Project area where commercial production of
geothermal fluid could be anticipated and it was
infeasible to relocate the wellfield and still meet the
purpose and need. However, it was determined that
alternative locations for the power plant site within a
reasonable distance of the middle of the wellfield
were technically and economically feasible.
|
|
Two power plant site alternatives are evaluated in
detail in this EIS/EIR. These sites are progressively
further from Medicine Lake than the Proposed Action
power plant site. Potential power plant sites even
further from the Lake were considered, but these sites
were considered either technically or economically
infeasible or offered no environmental advantage
over the Project Alternatives being evaluated in
detail.
|
Telephone Flat Geothermal Development Project Final EIS/EIR
 |
|
|