      
|
Telephone Flat Geothermal Development Project Final EIS/EIR
|
2.2.3.6 Spills and Upsets
|
|
A spill containment system would be put in place to
prevent any accidental spills of geothermal fluids,
chemicals, petroleum products, or contaminated
storm water runoff from leaving the power plant pad
or well pad areas. There would be no intentional
offsite discharge of geothermal fluids, chemicals or
petroleum products.
|
|
Accidental spills of condensate, cooling water or
geothermal brine outside of the containment areas
(e.g., along pipeline routes) would be handled as if it
were storm runoff (i.e., directed to drainage ditches
where it is expected to be absorbed by the porous
soils.
|
Spill containment areas would include, but not be
limited to, the following areas:
- Plant transformers;
- Turbine lube oil system;
- Liquid reduction skid and chemical storage area;
- Secondary abatement chemical area (if secondary abatement is needed);
- Cooling water chemical treatment area;
- Diesel engine fire pump area;
- Diesel fuel storage tank; and
- Well pad chemical injection system
|
|
Spill control provisions would consist of berming the
areas subject to spills to contain 150 percent of the
potential maximum spill volume and providing the
bermed area with a sump for a temporary sump
pump. Inside the sump would be a water drain-off
valve that would normally be closed. Any
uncontaminated rainwater could be released by
opening this valve. Uncontaminated rainwater from
spill containment areas inside the fenced plant area
would flow to the plant water storage pond.
Uncontaminated rainwater from the well pad
chemical injection system spill containment would
flow to the well pad sump. Any spills or potentially
contaminated runoff occurring within the spill areas
would either be removed by a licensed hazardous
waste hauler, pumped into a tanker truck for offsite
disposal at an appropriate location, or pumped to an
injection well for disposal.
|
|
2.2.3.7 Well Abandonment and Wellfield Site Restoration
|
|
Should a production test well be drilled that is not
suitable for conversion to an injection or observation
well, and therefore proposed for abandonment,
abandonment would be accomplished in accordance
with the GRO Orders, stipulations of the BLM and
USFS, and all other applicable permits or regulations.
During a typical well abandonment the hole would be
plugged back with cement. The well casing would be
cut off below ground surface, capped with a welded
plate, the cellar back-filled, and the site restored to
USFS specifications.
|
|
Prior to closing the solids disposal sump at each well
pad, the liquid contents of the sump would be
removed and the dry sump contents would be
sampled and analyzed to confirm that the material
was nonhazardous. If the sump contents were
determined to be hazardous, or otherwise determined
to be unacceptable for burial in place, the sump
contents would be removed and transported to an
off-site disposal facility authorized to accept the
waste. Subsequently, the sump would be backfilled
and graded to contour.
|
|
The lined fluid sump would be emptied of any
residual fluid and destroyed. The sump liner would
be either removed entirely, or the liner would be cut
to below ground surface, punctured to allow water to
permeate through it, and backfilled with native soil.
The entire pad would be regraded to approximate
natural contour and scarified to promote revegetation.
|
|
Wellfield roads that are no longer needed would be
closed or reclaimed as directed by the USFS. If a
road is to be closed, it would be abandoned as
directed by the USFS. Roads that are reclaimed
would be scarified, culverts would be removed, water
bars would be installed to control drainage, surfaces
would be replanted with native tree species, and the
road would be blocked with an earthen barrier or
down and dead woody material.
|
|
2.2.3.8 Production and Injection Fluid Pipelines
|
The high and low pressure (HP and LP) steam and/or
brine (for injection) cross-country piping from each
well pad to the power plant would utilize common
pipe support structures (see Figure 2.2.8). The pipe
support structures would keep the pipeline off of the
ground surface at a height of about 3 feet on level
terrain. The height of the pipeline above the ground
surface would vary up to about 6 feet, as necessary to
span topographic highs and lows along the pipeline
route. All pipelines and well pad equipment would be
wrapped with 3 inches of insulation. Figure 2.2.9
shows a typical geothermal pipeline corridor layout.
Thermal expansion would be provided for by a series
of guided pipe supports, expansion loops and anchor
pipe supports. For the most part, the expansion loops
would be horizontal as illustrated on Figure 2.2.9.
However, vertical expansion loops could be desirable
at specific locations such as at the power plant pad
(vertical, upward) or for particular road crossings
(vertical, underground). The injection cross-country
piping would utilize the same pipe support structures
as the steam piping wherever practical.
|
The gathering and injection system pipeline corridor
would be routed through existing cleared areas and
along existing roads and logging trails, to the extent
practical (see Figure 2.2.10). In areas where logging
roads do not exist along the pipeline corridors,
25-foot wide maintenance roads would be located
parallel to the pipelines (see Figure 2.2.3).
Construction corridors, including the maintenance
roads, would be confined to less than 120 feet in
width. After construction, the corridor would be
allowed to revegetate, where practical.
Approximately 25 percent of the pipeline corridor
area would be in continuing operational use as
pipeline piers, footing and access roads. Figure 2.2.9
also illustrates the typical layout of the proposed
cross-country pipeline corridors.
|
|
2.2.3.8.1 Production Pipeline Equipment
|
A typical production wellhead configuration is shown
in Figure 2.2.11. Downstream of each production
wellhead would be a motor-operated master control
valve. This valve could be operated remotely by the
power plant operator or locally at the wellhead. This
valve would be a high performance control valve that
could be used to continually regulate or trim
production rates to the power plant. This valve would
be capable of shutting-in the well under
preprogrammed and emergency shut-in conditions.
Upstream of the motor-operated master control valve
would be a manually-operated valve that would
control the flow of fluids to the wellhead silencer. A
bleed line with an isolation valve would be piped
from the wellhead to the pipeline and silencer. The
wellhead silencers would be used during start-up in
order to warm-up the well prior to diverting the
geothermal fluid into the production pipeline. Liquid
from the silencer would drain into the nearest sump.
Typical production well control facilities are
schematically shown in Figure 2.2.12.
|
|
Downstream of the master motor control valve for
each well would be a high-pressure (HP) steam
separator that would be located on a well pad and
interconnected to several wells. Several high-pressure
separators would be spaced within the wellfield with
two-phase geothermal fluid feeder production
pipelines constructed from the production wells to the
HP separators. The geothermal fluid would be
allowed to partially flash in the HP separators. Steam
from the HP separators would be interconnected to a
common main HP steam pipeline to the power plant.
Liquid from the HP separators would be directed via
feeder pipelines to a centrally located low-pressure
(LP) steam separator where the remaining LP steam
would be flashed from the geothermal fluid,
separated from the heat-spent liquid and transmitted
to the power plant via LP steam pipelines.
|
|
The spent geothermal liquid fraction from
the LP separator would be routed to one or
more injection wells. Several wells would be
expected to be interconnected to a common
HP separator. Downstream of the HP
separator would be motor control valves that
could be used to regulate production from
the interconnected wells.
|
|
2.2.3.8.2 Injection Pipeline Equipment
|
Each injection well would be equipped with
manually-operated wellhead controls and
manually-operated stacked master control valves (see
Figure 2.2.13). Upstream of these valves, hot
geothermal fluid injection wells would be equipped
with a regulating valve that would be the primary
control valve that would regulate the amount of fluid
being injected into each well (see Figure 2.2.14).
Noncondensable gas injection could be utilized as a
system back-up for the gas treatment program. If
noncondensable gas would be injected, it would
either be mixed with the return fluids from the power
plant or mixed at the injection well. The
noncondensable gas piping system would have
separate isolation and regulation valves from the
return fluid pipelines (see Section 2.2.4.5.5).
|
|
2.2.3.9 Freshwater Wells and Pipelines
|
|
Water for drilling/construction activity would either
be trucked or piped from existing wells in the Arnica
Sink currently used by CEGC and Modoc National
Forest. There are two water wells, north well and
south well, in the Arnica Sink area originally
constructed for geothermal operations. The south
well is owned by CEGC. This well would be the
primary supply well for the project. The north well
was also constructed by geothermal developers and
was dedicated to the USFS for general uses. Both
wells could be used during construction. If piping
water to well sites is determined to be practical,
temporary above-ground pipelines would be laid
along existing roads or other appropriate routes from
the source to the drill site. Example quantities of
water use would be: (a) temperature gradient well
operations generally require 3,000 to 5,000 gallons of
water per day; (b) exploratory and production test
wells would require generally 9,000 gallons of water
per day and up to 40,000 gallons per day may be lost
in circulation zones. Produced fluids from successful
wells would be used to reduce the need for other
drilling water sources.
|
A pipeline would also be constructed to transport
groundwater to the power plant site. The pipeline
would be buried beneath the frost zone and would
generally follow a former logging road to the power
plant site (see Figure 2.2.10). Water from the shallow
groundwater wells would be used to initially charge
the power plant cooling towers, but makeup water to
replace evaporative cooling tower losses would come
from geothermal production fluid steam condensate
(see Section 2.2.4.5.2).
|
|
The proposed power plant would be located in
Section 18, T43N, R4E (see Figure 2.2.4).
Commercial operation of the power plant to generate
electricity represents the second phase (operation) of
the Proposed Action.
|
The power plant site and adjacent laydown area
would encompass a total area of approximately
15 acres (i.e., about 580’ x 1,140’) and would include
the power plant pad, an equipment laydown area,
water storage ponds, contingency cut and fill areas,
and a 50-foot wide fire break around the surface
facilities (see Figure 2.2.15). The site would be
generally rectangular and would be cleared of
vegetation and graded to balance cut and fill
requirements. However, the Proposed Action also
assumes construction of well pad 52-18 adjacent to
the power plant facilities. The location of this well
pad is superimposed over the equipment laydown
area to minimize the total surface disturbance
required for the well pad and equipment laydown
area construction.
|
|
Based on current knowledge of the geothermal
resource conditions in the Project wellfield area, the
power plant would be constructed using double-flash
technology. The proposed power plant would be
capable of generating 48 MW (gross) electrical
power, with 45 MW (net) deliverable to the BPA
inter-tie point near Tionesta, California.
|
|
The power plant would be engineered and
constructed in accordance with utility standards. The
Project would utilize commercially available
geothermal technologies and equipment successfully
utilized at other project sites. The projected annual
capacity factor would be 90 percent or greater of the
electrical power generation capacity of the power
plant.
|
|
2.2.4.2 Process Flow Projections
|
Figure 2.2.16 is a schematic flow diagram showing
the fluid flow paths from the production wells
through the power plant and heat rejection (cooling)
system to the injection wells. The accompanying
tabulated material balance (see Table 2.2.2) identifies
the projected fluid mass flows, temperatures and
pressures throughout the power cycle based on the
currently projected geothermal resource conditions
(see Table 2.2.3).
|
|
2.2.4.3 Proposed Facilities
|
Table 2.2.4 lists the major power generation
equipment/systems expected to be used for the
proposed project and includes a description or
general specification for that equipment/system. A
plot plan of the proposed power plant site showing
the major power plant structures and exterior
equipment is provided as Figure 2.2.15.
Figure 2.2.17
shows the general elevations of the building, cooling
tower, and other prominent power plant facilities.
The following subsections describe the general
process and equipment proposed for this project.
The locations of the facilities within the proposed
power plant site, including the building, cooling
tower, water storage pads, rock boxes, switch gear,
and construction laydown area are shown on
Figure 2.2.15.
|
|
A dedicated communications system would be
installed at the existing Red Shale Butte
communications site located at the summit of Red
Shale Butte. The communications site includes the
existing USFS communications center, a USGS
communications pole and other radio towers. The site
has adequate room to install a new Project relay
without additional surface disturbance. The Project
equipment would have radio frequencies that do not
interfere with existing users. A Communications Plan
describing the equipment and frequency would be
prepared by CEGC and submitted to the USFS for
review and approval prior to installation.
|
Telephone Flat Geothermal Development Project Final EIS/EIR
 |
|
|