      
|
Telephone Flat Geothermal Development Project Final EIS/EIR
|
2 ALTERNATIVES INCLUDING THE PROPOSED ACTION
|
|
This chapter of the EIS/EIR provides a detailed
description of the Telephone Flat Geothermal
Development Project (Proposed Action) as proposed
by the Project Applicant, California Energy General
Corporation (CEGC), a wholly owned subsidiary of
CalEnergy Company, Inc. The chapter also identifies
Project Alternatives (i.e., both a range of alternatives
to the Proposed Action and the NEPA and CEQA
required No Action Alternative). The environmental
effects of each of the Project Alternatives is
evaluated in detail in this EIS/EIR. A summary
comparison of the facilities required for each of the
Project Alternatives is tabulated. This chapter also
briefly describes alternatives to the Proposed Action
that were considered for analysis in the EIS/EIR but
were rejected from detailed consideration in the
EIS/EIR.
|
|
2.1.1 NEPA and CEQA Requirements for Project Alternatives
|
|
Both NEPA and CEQA require that a reasonable
range of alternatives to the Proposed Action be
considered that could feasibly meet the objectives of
the Proposed Action as defined in the purpose and
need for the Project described in Section
[40 CFR 1502.14(a) and CEQA Guidelines
Section 15126(d)]. CEQA guidelines also advise that
the range of potential alternatives to the proposed
project shall include those that could feasibly
accomplish most of the basic purposes of the project
and could substantially lessen one or more of the
significant effects [CEQA Guidelines
Section 15126(d)(2)]. The range of alternatives
required is governed by a rule of reason (i.e., only
those feasible alternatives necessary to permit a
reasoned choice need be considered). Reasonable
alternatives are those that are practical or feasible
based on technical and economic considerations [46
Fed. Reg. 18026 (March 23, 1981), as amended, 51
Fed. Reg. 15618, April 25, 1986].
|
|
2.1.2 Project Alternatives Development and Selection Process
|
|
Project Alternatives were formulated and developed
during scoping and were refined throughout the
EIS/EIR process. A range of alternatives was
developed that would meet the primary project
objectives described in Section 1.3 and that would
also be responsive to concerns raised during public
scoping (see Section 1.10.3).
|
Considerations used by CEGC to develop the
Proposed Action included:
- Development of a geothermal-powered electrical
generation project using geothermal resources
from CEGCs federal geothermal leases
CA12370, CA12371, CA12372, CA13803,
CA21933, and CA2500;
- Use of an electrical power generation technology
suitable to the geothermal resources that exist
within the identified CEGC leases;
- Development of a geothermal production and
injection wellfield within reasonably accessible
surface and subsurface portions of the identified
CEGC leases;
- Location of the geothermal wellfield in areas of
the identified CEGC leases with a high
probability for successfully encountering
commercially suitable geothermal resources
during well drilling;
- Location of the power plant site in a centrally
located part of the wellfield development area to
minimize pipeline distances and resulting heat
loss from the produced geothermal fluid;
- Location of well pads and the power plant site on
relatively flat topography reasonably accessible
to existing roads; and
- Development of a project that would be
technically viable, economically feasible, and
would minimize adverse environment effects.
|
|
These same criteria and other agency management
directions were taken into consideration during the
development of the range of alternatives by the
agencies.
|
|
It is also an assumption of the Proposed Action and
each of the other action Project Alternatives that a
preferred utility corridor from the Medicine Lake
Highlands (MLH) to the existing BPA Malin-Warner
transmission line east of Highway 139 would be
selected by the USFS as the result of an earlier
proposal for geothermal development on the MLH
(i.e., the Fourmile Hill Geothermal Development
Project). The pending decision on the Fourmile Hill
Project includes a range of utility corridors (see
Section 2.2.5.1). The preferred alternative identified in the
Final EIS/EIR prepared for the Fourmile Hill Project
is for a Northern Utility Corridor (transmission line
segments A3, B1, and C2) (BLM et al. 1998). It is
assumed that the transmission line corridor selected
by the USFS for the Fourmile Hill Project would be
accessible from a power plant site within the
Telephone Flat Project wellfield area via an
interconnection tie in transmission line (see Section 2.2.5).
If the Fourmile Hill Project is not constructed, then
the entire 21-mile transmission line from the
Telephone Flat Project power plant site to the BPA
Malin-Warner transmission line would be constructed
originating with an interconnection transmission line
route to a tie in point with the agency preferred
Northern Utility Corridor as part of the Telephone
Flat Project.
|
|
Alternatives to the Proposed Action were selected to
reduce potentially significant effects of the Project
with respect to visibility of the Project facilities;
potential conflicts with residential and developed
recreation use areas adjacent to Medicine Lake from
Project-generated noise, traffic, malodors, or other
temporary or intermittent intrusions; and potential
effects of the Project on regional groundwater
hydrology. Each of the Project Alternatives selected
has the capacity to substantially reduce one or more
of these potentially significant effects of the Proposed
Action.
|
CEGC submitted a Plan of Operations (POO) for
Development and Production and a POO for
Utilization and Disposal to the BLM for constructing,
operating, and maintaining a 48 MW (gross), dual
flash, geothermal power plant and wet cooling tower,
associated geothermal production and injections
wells, well pads, roads, interconnected geothermal
fluid pipelines, and accompanying segments of a
230-kV transmission line (CEGC 1997 and 1997a).
This project, known as the Telephone Flat
Geothermal Development Project (Project), would be
located within the Glass Mountain Unit of the Glass
Mountain Known Geothermal Resource Area
(KGRA) on the Modoc National Forest (see
Figure 1.1.1). The geothermal fluid supplies and
wellhead reserves have been projected by CEGC to
be sufficient for at least 50 years and the Project is
expected to continue for at least that long.
|
The Project would occur in three defined phases:
- Wellfield development and site construction
activities (construction);
- Commercial electrical power generation
operations (operations); and
- Decommissioning and site restoration activities
(decommissioning).
|
|
The Project construction phase is the first phase of
the Proposed Action. Previously approved
exploration well drilling and testing would continue
through the 1999 drilling summer season. Assuming
a timely Project approval, construction of new
facilities would be expected to start about mid- to
late-1999 and would be expected to be completed by
late-2001; this would include drilling, constructing
and testing additional production wells, installing the
electrical transmission line, improving and
constructing access roads, and constructing the
geothermal power plant, pipelines, and ancillary
facilities.
|
|
The operation phase would begin when the power
plant begins commercial generation of electrical
power. Project activities that would occur during this
phase would include production of geothermal fluid,
injection of spent fluid, power plant operations and
maintenance, well servicing activities, replacement
well drilling, and maintenance of pipeline and
transmission line.
|
|
At the end of the operation phase, the
decommissioning phase would occur. This phase
would include well abandonment, removal of surface
facilities, and site restoration activities. This phase
would continue for approximately 2-3 years.
|
The proposed geothermal power plant, well pads, and
fluid pipelines would be located within portions of
Federal geothermal leases CA12370, CA12371, and
CA12372 within the Glass Mountain Unit of the
Glass Mountain KGRA and the Modoc National
Forest. The proposed power plant site would be
located in Section 18 within an approximately
8.41 square mile area that defines the Telephone Flat
Project Participating Area, located in Sections 7, 8, 9,
16, 17, 18, 19, and 20 T43N, R4E; and Sections 13
and 24 T43N, R3E, MDB&M, Siskiyou County,
California (see Figure 1.1.4). Previous geothermal
exploration activities in the vicinity of the Project
were discussed in Section 1.8.2, and geothermal
exploration well pads that currently exist within the
Project wellfield area and are shown on Figure 1.1.6.
|
|
2.2.2 Site Access and Roads
|
The Project site would be accessed by several
existing paved and gravel-surfaced arterial roads and
many gravel surfaced collector roads. The main
access route to the wellfield and power plant from the
east would be Primary Forest Route 97 (a.k.a. Modoc
County Road 97 or Road 97), also known as the
Tionesta-Black Mountain Road. This main access
road is a paved two-lane arterial providing access
from California State Highway 139 near Tionesta.
Arterial access roads from the south (Primary Forest
Route 49 and west (Primary Forest Route 15) would
also be expected to be seasonally used to access the
Project site. Several existing gravel-surfaced roads
cross the wellfield, proposed power plant site and
transmission line route. Figure 2.2.1 shows the
location of the existing roads in the wellfield area to
be used by the Project. Year-round access to the
power plant is proposed. This would require plowing
snow-covered sections of Primary Forest Route 97
and the secondary power plant and wellfield access
roads during the winter months (see Section 2.2.4.6).
|
|
2.2.2.2 Road Construction
|
The access road from Road 97 to the power plant and
all well pad access roads would be improved to a
USFS all weather gravel road standard (see
Figure 2.2.2). Figure 2.2.4 shows the approximate
location of the new, reconstructed and improved
roads for the Project power plant site and wellfield.
Approximately 0.6 miles of new road construction
would be necessary and approximately 5.2 miles of
former logging roads and 4-wheel drive trails would
need to be reconstructed by widening, improving
drainage, and improving the surface with gravel.
Approximately 1 mile of Forest Road 43N53 and
0.8 miles of Forest Road 43N21 would have the
surface improved with additional gravel. The
maintenance roads in the pipeline and transmission
line corridors used for construction that are not
primary access routes would be allowed to revegetate
(see Figure 2.2.3).
|
|
Any road gravel or other road materials necessary for
improvement or repair of existing roads or site
construction would be obtained from existing road
material pits with the concurrence of the USFS.
Water would be used as necessary to control dust
during road construction and maintenance.
|
|
2.2.3 Geothermal Wellfield
|
The geothermal wellfield would be comprised of
production and injection wells located on well pads
spatially separated within the Project wellfield area to
optimize field development. An estimated 10-12
production wells would be initially required to
provide geothermal resource to the power plant, and
an estimated 3-5 injection wells would be initially
required to return spent geothermal fluid, condensate
fluids, and cooling tower blowdown to the
geothermal reservoir. Four well pads (87-13, 68-8,
46-8 and 31-17) were earlier constructed in the
Project wellfield area under previously approved
exploration plans of operation. Three existing
geothermal exploration wells were drilled on three of
the constructed well pads, including: wells 68-8,
31-17 and 87-13, and have been incorporated into the
Proposed Action. Two additional well pads (56-18
and 13-18) were also approved for construction in the
Project wellfield area as part of the previously
approved 1995 Plan of Exploration (POE) for
exploration drilling in the Glass Mountain Unit Area.
Although approved, these well pads have not been
constructed. The 4 existing well pad locations and the
two approved exploration well pad locations have
been incorporated into the Proposed Action. Twelve
additional new well pads have been proposed for a
total of 18 existing and alternative well pad locations
in the Proposed Action (see Figure 2.2.5). Not all of
the well pads would be expected to be constructed.
The well pad locations and orientation would be
subject to changes of up to about 200 feet in distance
in any given direction to avoid any potential site
specific environmental resource conflicts that may be
identified.
|
|
The actual number and location of production and
injection well sites to be used during the Project
would depend on the results of drilling, testing, and
the response of the geothermal reservoir. The
expected startup production well sites would be:
16-18, 13-18, 52-18 (or 51-18), and 56-18; and the
expected startup injection well sites would be: 68-8,
72-17, and 15-16. Well sites 46-8, 84-7 and 31-17
could be either production or injection well sites,
depending on Project needs. Existing well 87-13 is
proposed to be used as an observation well. The
existing and proposed Project well pads and
preliminary designation of the pads as either
production or injection well sites is provided in
Table 2.2.1. The other identified well pad locations
would be used if supplemental production or
injection is required as make-up over the life of the
Project.
|
|
Table 2.2.1: Existing and Proposed Well Pads
|
|
Existing Wells and Pads
|
|
Well Number
|
Location
|
Pad Designation
|
Status/Commentsa
|
|
46-8
|
Section 8, T43N, R4E
|
Production or Injection
|
Pad constructed, no wells, existing pad size 250 x 350,
maximum area cleared 300 x 500
|
|
68-8
|
Section 8, T43N, R3E
|
Injection
|
Pad constructed with existing well, existing pad size
200 x 250, maximum area cleared 400 x 400
|
|
87-13
|
Section 13, T43N, R3E
|
Observation
|
Pad constructed with existing well, proposed sump closure,
existing pad size 200 x 200, no plans for pad expansion
|
|
31-17
|
Section 17, T43N, R4E
|
Production or Injection
|
Pad constructed with existing well, existing pad size
250 x 300, maximum area cleared 300 x 500
|
|
Previously Approved Exploration Wells, Pads Not Constructed
|
|
Well Number
|
Location
|
Pad Designation
|
Status/Commentsa
|
|
13-18
|
Section 18, T43N, R4E
|
Production
|
Approved, not constructed, maximum area cleared 400 x 600
|
|
56-18
|
Section 18, T43N, R4E
|
Production
|
Approved, not constructed, maximum area cleared 300 x 400
|
|
Proposed New Well Pads
|
|
Well Number
|
Location
|
Pad Designation
|
Status/Commentsa
|
|
26-7
|
Section 7, T43N, R4E
|
Make-up Production
|
Proposed new well pad, maximum area cleared 400 x 400
|
|
84-7
|
Section 7, T43N, R4E
|
Production or Injection
|
Proposed new well pad, maximum area cleared 400 x 400
|
|
64-8
|
Section 8, T43N, R4E
|
Make-up Injection
|
Proposed new well pad, maximum area cleared 400 x 400
|
|
73-13
|
Section 13, T43N, R3E
|
Make-up Production
|
Proposed new well pad, maximum area cleared 400 x 400
|
|
15-16
|
Section 16, T43N, R4E
|
Injection
|
Proposed new well pad, maximum area cleared 400 x 400
|
|
26-17
|
Section 17, T43N, R3E
|
Make-up Production
|
Proposed new well pad, maximum area cleared 300 x 400
|
|
72-17
|
Section 17, T43N, R4E
|
Injection
|
Proposed new well pad, maximum area cleared 400 x 400
|
|
16-18
|
Section 18, T43N, R4E
|
Production
|
Proposed new well pad, maximum area cleared 400 x 600
|
|
25-18
|
Section 18, T43N, R4E
|
Make-up Production
|
Proposed new well pad, maximum area cleared 400 x 600
|
|
51-18
|
Section 18, T43N, R4E
|
Production
|
Proposed new well pad, maximum area cleared 400 x 600
|
|
52-18
|
Section 18, T43N, R3E
|
Production
|
Proposed new well pad, maximum area cleared 400 x 600
|
|
83-18
|
Section 18, T43N, R4E
|
Make-up Production
|
Proposed new well pad, maximum area cleared 400 x 600
|
|
a The maximum pad size would be the largest well pad constructed at the respective locations. The maximum pad size would be 300 x 500
working surface built within a 400 x 600 cleared area. Multiple-well production well pads would be the largest cleared areas (400 x 600)
and single-well pads with anticipated construction constraints being the smallest well pads within smaller cleared areas.
|
Telephone Flat Geothermal Development Project Final EIS/EIR
 |
|
|