4.1.5.3. Impacts of the Proposed Action on Wildlife
4.1.5.3.1. Impacts on Wildlife Habitat
In addition to other changes, this section has been modified from the
November 1996 Draft EIR in response to comments to increase the off-site
land acquisition compensation ratio for disturbed microphyll woodland habitat
from 1:1 to 3:1.
The total area of surface disturbance resulting from Project construction
and operation within the Project mine and process area would be 1,302 acres.
This would include approximately 1,215 acres of desert scrub habitat
and approximately 87 acres of microphyll woodland habitat. The loss
of wildlife habitat, particularly the loss of microphyll woodland habitat,
would directly or indirectly displace resident birds within or near the
Project mine and process area. The Project would also result in an incremental
loss of foraging habitat for wildlife and/or migratory species such as bats
and raptors. The effects of the loss of habitat from the Project on wildlife
would continue over the life of the Project, and some of the effects would
continue for an extended period following final reclamation. Wildlife would
eventually return to the Project mine and process area as vegetation reestablishes
and disturbed surfaces are reclaimed or recover. However, the projected
period before conditions return to an approximate pre-Project status with
respect to wildlife carrying capacity may exceed several decades following
completion of the active life of the Project (Rado 1997). To compensate
for this reduction in carrying capacity, the Proposed Action contains many
measures (which are also contained in Mitigation Measures 4.1.5-7 through
4.1.5-26) to reduce the impacts on microphyll woodland habitat and associated
wildlife which use this habitat; reduce the long-term impacts of the Proposed
Action; provide off-site compensation for these habitat losses; and enhance
reclamation. These are each discussed below, as is the level of significance
for each.
As discussed in Section 3.5.6, the CDFG considers microphyll
woodland to be a sensitive habitat. It is considered second only to riparian
habitat in wildlife diversity in the desert area, and it is considered a
particularly important habitat component to deer and other wildlife species
(Personal Communication, Nancy Andrew, CDFG, 1996). CDFG has a policy of
requiring replacement of habitat "on-site" and "in kind"
when possible for wetland habitat impacted as a result of proposed projects.
This means that sensitive wetland habitat lost within a proposed project
area as a result of proposed project activities would be required to be
replaced by the project applicant with the same type and quality of sensitive
wetland habitat somewhere within the project area when possible, or outside
of the project area when on-site replacement is not possible. Wetland habitat
would not be impacted by the Imperial Project, but the CDFG also adapts
this wetland habitat policy to other habitats which they consider sensitive,
such as microphyll woodland, when evaluating measures to mitigate the biological
effects of projects which may require Stream Alteration Agreements (Personal
Communication, Lilia Martinez, CDFG, 1996).
Surface disturbance from the Imperial Project would result in the destruction
of approximately 87 acres of microphyll woodland habitat within the
Project mine and process area. Based on the work done at the Picacho Mine,
it is apparent that microphyll woodland vegetation can be re-established
(Bamberg and Hanne 1997; see also Attachment B to Appendix A,
Reclamation Plan). The estimated time for recovery of a microphyll woodland,
that is, for establishment of trees and shrubs to a density approaching
the natural wash vegetation, is estimated at five (5) years; for recovery
to a condition approaching maturity is estimated at twenty (20) years.
Plant succession and changes in structure would continue for approximately
50 years for trees (up to 30 feet). The expected survival of ironwood
seedling transplants after one (1) year, based on Picacho experience (December
1995 to December 1996), is approximately 80 percent (Bamberg and Hanne
1997). Studies are underway on ironwood propagation at the Picacho Mine
working in conjunction with the Desert Legume Program at the University
of Arizona. Other typical wash plant species (palo verde, brittle bush,
saltbush, sweetbush, desert mallow, wire lettuce, and annual grasses and
forbs) have been successfully grown from seed collected in washes (Bamberg
1997b; see Appendix G).
Measures are incorporated into the Project design to minimize the area of
microphyll woodland habitat disturbed by the Project to 87 acres and
to mitigate the adverse effects of the Project on microphyll woodland habitat.
Reclamation measures would result in reestablishment within the Project
mine and process area of approximately one-half (2) of these 87 acres
of disturbed microphyll woodland habitat. Additional Project measures intended
to compensate for the loss of microphyll woodland habitat from the Project
include providing for the acquisition of off-site private lands containing
microphyll woodland habitat at a ratio of 3:1 for all of the acres of microphyll
woodland habitat disturbed within the Project mine and process area, reclamation
of previously disturbed public lands not associated with the Proposed Action
to be identified and approved by the BLM (see
Section 4.1.5.4).Vegetation, wildlife and ecosystem processes
are also expected to benefit from off-site compensation of upland habitat
for desert tortoise and microphyll woodland habitat. Compensation lands
that are in close proximity to the Project mine and process area, of equal
or better habitat quality, and of similar vegetation community, elevation,
hydrology, wind patterns, and substrates, would provide the greatest benefit.
Additional measures to mitigate and compensate for the impacts of the Proposed
Action on the ephemeral stream channels and associated microphyll woodland
habitat are provided in the required Stream Alteration Agreement between
the Project Applicant and the CDFG. A draft Stream Alteration Agreement
has been prepared and is currently under negotiation between the CDFG and
Glamis Imperial (Glamis Imperial 1997; see Section 4.1.5.4).
With the implementation and success of these measures proposed as a part
of the Proposed Action or required by regulation, the effect of the Proposed
Action on microphyll woodland habitat within the Project mine and process
area would be below the level of significance.
Diversions of the major surface drainages through constructed channels around
the Project facilities would continue to provide the same flow and quality
of water into these major wash systems downgradient of the Project mine
and process area as exists prior to mine construction. No substantial impact
on wildlife habitat or species in the major wash system downgradient of
the Project mine and process area is expected. Similarly, wildlife habitat
in the Algodones Sand Dunes foothill "pockets" of microphyll vegetation
downgradient of the mine would not be affected by the Project. Although
some minor, ephemeral tributaries of the major channels would be "truncated"
by the construction of the waste rock stock piles and the heap, thereby
reducing the amount of water which may flow into these small tributary channels,
the amount of reduction in water flow in the major channels would be imperceptible
and would not result in any significant effects.
The through-flowing surface drainages would be located as close to their
original courses as reasonably possible in comparably-sized channel(s) which
would tie into the original wash systems downgradient of the diversion point.
As discussed in Section 4.1.5.2, these diverted drainages would
be revegetated with microphyll vegetation to reestablish microphyll woodland
habitat. However, as a result of Project construction, the affected microphyll
woodland habitat in the smaller drainages which are not diverted cannot
be reestablished within the Project mine and process area, and thus there
would be a net reduction of microphyll woodland habitat in the Project mine
and process area as a result of the Project. However, with implementation
of the elements of the Proposed Action to compensate for the permanent loss
of microphyll woodland habitat within the Project mine and process area,
this loss would be less than significant.
As discussed in Section 3.5.6, approximately 2 acres of
microphyll woodland habitat within the Project ancillary area and approximately
1 acre of microphyll woodland habitat in the overbuilt 92 kV/34.5 kV
transmission line corridor are expected to be impacted by surface disturbance
associated with the Proposed Action within these areas. The proposed removal
of Project facilities and the other reclamation activities contained in
the Proposed Action to be completed as part of final reclamation within
the affected portions of the Project ancillary area and the overbuilt 92 kV/34.5 kV
transmission line corridor are expected to fully reclaim the disturbed microphyll
woodland habitat in these two (2) areas. These impacts would be below
the level of significance.
Several small, isolated, ephemeral water seeps located northwest to southwest
of the Project ground water well field area, in the vicinity of or adjacent
to the Algodones Sand Dunes, likely provide seasonal water and habitat for
wildlife which is otherwise limited in this region. As indicated in Section 3.3.1,
because Project ground water production would be from a different aquifer than these seeps, it would not impact the
shallow source of the seeps, and would not impact biological resources which
may be supported by these seeps.
4.1.5.3.2. Impacts on Wildlife and Wildlife
Movement
Wildlife species which inhabit, move through, or forage within the approximately
1,340 acres of surface area to be disturbed within the Project area
would be subject to increased mortality or displacement as a result of the
Proposed Action. Increased mortality would result from direct physical impacts
or entombment during construction or processing activities, or result in
indirect mortality from stress or increased predation pressure resulting
from displacement into off-site areas. Individual animals could also be
subject to injury or mortality during on-site blasting and continued mining
operations and geological survey activities, and increased mortality from
project-related stresses, including night lighting, in the vicinity of the
Project mine and process area. Noise-sensitive species would be expected
to avoid both the Project area and neighboring areas over the life of the
Project, but would be expected to return when noise generating operations
are discontinued. Similarly, species intolerant of surface disturbance and
human activities would also be expected to avoid the Project area and neighboring
areas over the life of the Project. Because of the substantial amount of
alternative habitat available, these impacts to wildlife and wildlife movement
are not considered significant.
Some wildlife species might come under increased pressure from opportunistic
predators (i.e., ravens, coyotes and kit foxes) attracted to the Project
area by increased water availability, refuse, or noise. In addition, during
the life of the Project the movements of some wildlife through the Project
mine and process area would be restricted as a result of the perimeter fence,
the constructed Project features (such as the pits, waste rock stockpiles,
and heap), or the general level of human presence and activity. Because
of the substantial open space surrounding the Project mine and process area,
these effects are not considered significant.
Over the life of the Project, additional injuries and mortality to wildlife
would be expected to result from direct impacts with motor vehicles commuting
to the Project area and other equipment traveling to and from the Project
mine and process area and the ancillary area. Experience in other remote
areas suggests that measures to reduced speeds on public roads, such as
posting reduced speed limits, to minimize inadvertent vehicle impacts with
wildlife are impractical to enforce. Individual animals attracted to the
Project area from available water sources in the area may also be injured
or killed by vehicles on the roads inside the Project mine and process area
and in the Project ancillary area. The realignment of a portion of Indian
Pass Road and creation of new roads to ancillary facilities would create
a temporary impact on the movement of wildlife in the area, particularly
for mule deer, coyotes, foxes, and badgers. These species are expected to
acclimate to the new roads, but there may be some permanent displacements
and readjustments of home ranges, even though the road realignment and ancillary
area access roads are temporary. These impacts to wildlife and wildlife
movement from roads and vehicles are not considered significant.
Wildlife could be affected by the hazardous chemicals used by the Project.
There would be a potential for impacts to wildlife due to the transport
of hazardous chemicals to the Project area via public highways and access
roads. The probability of hazardous chemical spillage occurring due to a
transport accident is considered low, but the potential for occurrence cannot
be entirely eliminated. The preventative and corrective measures discussed
in Section 4.1.12.3 would reduce both the potential risk of
and effects to wildlife resulting from spills of hazardous chemicals being
transported to the Project area to below the level of significance. Wet
liners on ponds could attract shorebirds because they mimic wetland shores,
which could result in injury or death from the ingestion of toxic chemicals
in the ponds. Individual animals could also be subject to drowning in mine
process fluid impoundments and increased mortality from exposure to process
chemicals within the solution ponds. The Proposed Action includes measures
to prevent wildlife from entering process ponds, and the residual effects
would be below the level of significance.
The natural tinajas and wildlife guzzlers installed to provide artificial
sources of water would not be affected by the ground water withdrawal at
the Project ground water well field area, and the wildlife supported by
these water sources would not be affected.
An existing section of 34.5 kV transmission line would be overbuilt
with a 92 kV/34.5 kV transmission line, and a new transmission
line would be constructed along Indian Pass Road, to provide electrical
power to the Project mine and process area. Temporary and short-term impacts
on wildlife and wildlife movement would occur during pole placement and
line stringing activities as a result of minor surface disturbance and human
presence. The transmission lines could also increase the availability of
potential perch sites for bird predators in the area, which could result
in an increase in predatory pressure on wildlife species comprising the
prey base for predatory birds in the area. The transmission lines would
also increase the potential for collisions or electrocutions of raptors
and other bird species. However, all of these impacts would be below the
level of significance.
The Proposed Action would result in the excavation of three (3) open
pits, two (2) of which would be backfilled with waste rock. The East
Pit would remain as an open approximately 198-acre excavation which would
remain as a slight long-term impediment to the movement to some wildlife
species. Individual terrestrial wildlife species could become injured or
killed by falls within this open pit, although as part of the Proposed Action
a rock rubble barricade would be constructed around the open pit to prevent
vehicular access and limit pedestrian and wildlife access, and haul roads
within the open pit would be regraded such that wildlife or humans would
still be able to use them to exit the open pit should they pass beyond the
barricade. Ground water could accumulate in the bottom of the open pit and
form a pit lake, although this is not likely, and measures are incorporated
as part of the Proposed Action to reduce the possibility further. Although
any water in a pit lake would not be injurious to wildlife (see Section 4.1.3.2.2),
wildlife species coming to drink could be exposed to predators which may
use the pit area as a place to wait for prey. The Proposed Action also includes
measures to offset the net reduction of habitat as a consequence of the
open pits. The effects of the Proposed Action on general wildlife species
and wildlife movement would be below the level of significance.
If mining is suspended or terminated prior to backfilling of the West Pit,
the West Pit would remain as an open excavation and would remain as a long-term
impediment to the movement to some wildlife species. Individual terrestrial
wildlife species could become injured or killed by falls within this open
pit. Ground water could accumulate in the bottom of the open West Pit and
form a pit lake, although this is not likely, and measures are incorporated
as part of the Proposed Action to reduce the possibility further. Although
any water in a pit lake would not be injurious to wildlife (see Section 4.1.3.2.2),
wildlife species coming to drink could be exposed to predators which may
use the pit area as a place to wait for prey. These effects of the open
West Pit on general wildlife species and wildlife movement would be above
the level of significance.
4.1.5.3.3. Impacts to Threatened or Endangered
Wildlife Species
One species listed on both federal and California threatened species
lists, the desert tortoise, would be directly impacted by the Project. Two (2)
other currently listed or proposed wildlife species (peregrine falcon and
Gila woodpecker), which were either documented during the surveys or previously
recorded in the Project area, are also discussed below, but would not likely
be impacted by the Proposed Action.
Desert tortoise: The habitats within the Project area are unclassified
by the BLM with respect to desert tortoise, and
the Project area has not been designated critical desert tortoise habitat
by the USFWS (USFWS 1990). However, as a result of field survey documentation
of the tortoise within the Project area, the Project area would be considered
Category III tortoise habitat (BLM 1989).
The number of desert tortoise currently present within the Project area
has been estimated from review of the survey data to range between 33 and
57 individuals (Rado 1997).
Desert tortoise which occupy the Project mine and process area may be injured
or killed as a result of surface disturbance during Project construction
or processing activities. The surface modification activities would occur
over approximately 1,302 acres and would destroy the tortoise burrows
or pallets within the Project mine and process area, potentially crushing
or entombing individuals. Additional tortoises may also be injured or killed
as a result of heavy equipment traffic within the Project mine and process
area and from impacts with vehicles commuting to and from the Project area
on existing or relocated roads. Tortoise occupying areas adjacent to the
Project mine and process area, or having home ranges overlapping the Project
area, would be similarly affected if they wandered onto the active Project
areas. A total of 1,137 acres of desert tortoise habitat within the
Project mine and process area would be reclaimed. Adjacent tortoise populations
may slowly recolonize this area as vegetative processes establish native
habitats. A total of 165 acres, comprising the East Pit slopes, would
be lost within the Project mine and process area as desert tortoise habitat
after completion of Project final reclamation.
Activities and facilities ancillary to the Project mine and process area
and the overbuilt 92 kV/34.5 kV transmission line corridor could
also adversely affect desert tortoises. Tortoises could be injured or killed
as result of construction of the ground water wells, water pipeline, or
electrical transmission line within the Project ancillary area, or the constructions
of the overbuilt 92 kV/34.5 kV transmission line. The water pipeline
would be buried, so it would not restrict tortoise movement. Construction
of the new or overbuilt transmission lines may also attract, or provide
perches for, tortoise predators (i.e., ravens). Tortoise populations have
been dramatically reduced in areas with higher than normal raven populations.
Ravens eat juvenile and hatchling tortoises and can severely reduce recruitment
to the tortoise populations. Storage ponds within the Project mine and process
area or other sources of standing water and refuse could also serve to attract
and increase tortoise predator populations in the vicinity of the Project
area.
Following completion of mining activities, individual desert tortoises could
wander into the open East Pit. While pit slopes (estimated at 50 degrees)
may allow for the movement of animals, individual tortoises could become
injured or killed as a result of falls or excessive predation from coyotes,
kit foxes, or other species.
Desert tortoises within the Project area would also be subject to displacement
either by capture and removal of individuals to locations outside the Project
area, or by individuals within or near the Project area voluntarily leaving
the vicinity when Project activities are initiated.
Guzzlers constructed in the vicinity of the Project area to mitigate the
effects of the Project on wildlife could inadvertently trap desert tortoise
and result in increased desert tortoise mortality.
Some design elements have been incorporated into the Project to minimize
the effects of the Project on desert tortoise. However, prior to any additional
mitigation, the effects of the Project on desert tortoise are considered
significant.
Peregrine falcon: No peregrine falcons were observed during surveys
of the Project area, but a few falcons have previously been recorded from
the Project area. Similarly, the species has been unreported in surveys
for other projects in the general area (Condor 1991, WESCO 1992; Office
of Arid Lands Studies 1993; Western Resource Development 1993; BLM 1994a). Peregrine falcons are known to nest in cliff
areas along portions of the Colorado River system (USBR 1996). No potential
nesting sites for peregrine falcons occur in the Project area or the surrounding
area. The species could potentially utilize the Project area, including
the Project mine and process area, for foraging on an infrequent basis although,
based on the absence of prior records, this seems highly unlikely. Project
effects on the American peregrine falcon would not be significant.
Gila Woodpecker: A single Gila woodpecker was observed perched on
a large ironwood tree in a large wash near the southwest corner of the Project
mine and process area by a biologist in January 1995 (Rado 1995). Additional
searches for this and other Gila woodpeckers were subsequently conducted
but did not record the bird in the Project area. The single observation
of the Gila woodpecker is believed to have been of a transient bird. The
Gila woodpecker is a cavity nester known to prefer mature cottonwood and
willow trees within riparian habitats not present in the Project area. The
effects of the Project on the Gila woodpecker would be below the level of
significance.
4.1.5.3.4. Impacts to Other Wildlife Species
of Concern and Habitat
In addition to other changes, this section has been modified from the
November 1996 Draft EIR in response to comments to: discuss the impacts
to bats on the basis of the results of a survey of the Project mine and
process area for bats; discuss the impacts to flat-tailed horned lizards
on the basis of the results of a survey of the southernmost end of the overbuilt
92 kV/34.5 kV transmission line corridor for flat-tailed horned
lizard or sign; provide additional assessment on Project impacts on desert
deer and bighorn sheep; and discuss the effects of Project lighting on wildlife.
In addition to the listed species discussed above, the Proposed Action may
adversely effect the following wildlife species of concern.
Cheeseweed owlfly: The cheeseweed owlfly has not been documented
within the Project mine and process area. Since the Project occurs within
the geographic range of this species, and because its host plant (creosote
bush) is present, the cheeseweed owlfly could potentially occur here. If
present, the cheeseweed owlfly would be subject to habitat loss associated
with initial blading and grading activities. Additionally, individual cheeseweed
owlflies could be attracted to night lighting during operations; although,
the species is considered a poor flyer (USBR 1996). The geographic range
of this species is extensive and collecting sites widely dispersed. The
short flight season of adults and the indeterminate timing of adult emergence
may reflect the paucity of records. Therefore, information necessary to
determine the effects of the Proposed Action on the cheeseweed owlfly is
unavailable. There is no substantial evidence that the Proposed Action would
substantially affect the cheeseweed owlfly or its habitat; therefore, impacts
would be below the level of significance. Mitigation measures (see Section 4.1.5.4)
have been incorporated into the Project design to further reduce the long-term
impacts of the Project on potential cheeseweed owlfly habitat.
Chuckwalla: Marginal quality chuckwalla habitat exists over approximately
one-half (2) of the Project mine and process area. A total of three (3)
chuckwallas were observed during surveys of the Project mine and process
area, and an estimated 25 individual chuckwallas may inhabit the Project
area (Rado 1995). Chuckwallas are known to display high site fidelity and
would not be expected to flee the area as a result of disturbance. As such,
the chuckwallas present within the Project area could be killed or injured
as a result of surface disturbance associated with mine construction and
ore extraction and processing. Chuckwalla habitats are known to exist in
the vicinity of Peter Kane Mountain north, Picacho Peak east, and the Cargo
Muchacho Mountains south of the Project area. A large portion of the chuckwalla
habitat exists within the Indian Pass Wilderness Area and Picacho Peak Wilderness
Area. While the effects of the Project on the chuckwalla and chuckwalla
habitat would be below the level of significance, measures have been proposed
to further reduce the impacts of the Proposed Action on this species (see
Section 4.1.5.4).
Flat-tailed horned lizard: There were no flat-tailed horned lizards
observed within the Project area during the biological surveys of the area,
and no flat-tailed horned lizard habitat exists within the Project area.
Likewise, there were no flat-tailed horned lizard or flat-tailed horned
lizard sign observed during the specific survey for the flat-tailed horned
lizard, along the southernmost portions of the 34.5 kV transmission
line to be overbuilt for the Project. Flat-tailed horned lizard habitat
does exist south of Interstate Highway 8 in the proximity of the tap
(origin) for the overbuilt 92 kV/34.5 kV transmission line, but
Interstate Highway 8 provides a permanent barrier which would prevent
lizard crossings and potential impacts to the lizard and lizard habitat
south of the highway during construction of the overbuilt 92 kV/34.5 kV
transmission line.
There have been no recorded sightings of flat-tailed horned lizard within
ten (10) miles of the Project mine and process area and Project ancillary
area. However, there is a potential that a small number of flat-tailed horned
lizards may be injured or killed as a result of Project-related traffic
traveling along an approximately one-mile section of flat-tailed horned
lizard habit located immediately north of the junction of Ogilby Road and
Interstate Highway 8. The results of the flat-tailed horned lizard
surveys indicate any impacts to individual flat-tailed horned lizards or
its habitat would be below the level of significance.
Loggerhead shrike: Loggerhead shrikes were frequently observed throughout
the Project area during the biological surveys (Rado 1995). Shrikes are
common and widely distributed in the area. Two (2) family groups were
observed within the Project area during the spring breeding period, suggesting
a high likelihood that nesting occurs within the Project area, but no loggerhead
shrike nests were encountered during the surveys. Based on a projected density
of one loggerhead shrike per 50 acres, as was observed in the alluvial
plain bordering the Santa Rosa Mountains, an estimated 33 shrikes may
currently use the Project area for foraging and/or nesting. During construction
and mining activities within the Project area, approximately 1,340 acres
of shrike habitat would be disturbed, displacing shrikes to neighboring
unmodified lands. Individual loggerhead shrike nests may be destroyed, resulting
in mortality to nestling birds or abandonment of eggs if disturbance occurs
during the spring breeding period. Because of the availability of substantial
off-site shrike habitat, the effects of the Proposed Action on the loggerhead
shrike and shrike habitat would be below the level of significance.
Black-tailed gnatcatcher: Black-tailed gnatcatchers were observed
within the Project area during the biological surveys. Favored gnatcatcher
areas appeared to be in secondary drainages with wash vegetation in which
young ironwood and palo verde trees provide cover (Rado 1995). Gnatcatchers
utilizing the Project mine and process area would be displaced to neighboring
unmodified lands. Individual black-tailed gnatcatcher nests would be destroyed,
resulting in mortality to nestling birds or abandonment of eggs if surface
disturbance occurs during the breeding period. Because of the availability
of suitable gnatcatcher habitat in neighboring areas, the effects of the
Proposed Action on the black-tailed gnatcatcher and its habitat would be
below the level of significance.
Sharp-shinned hawk: A single sighting of a sharp-shinned hawk occurred
in the Project area during the biological surveys (Rado 1995). This species
is reported to be an uncommon winter migrant through the area. Implementation
of the Project would result in a small reduction of the regional foraging
habitat available to migrating sharp-shinned hawks, and it could result
in a minor behavior modification of individual birds that cross the Project
area. Based on the low frequency in which sharp-shinned hawks are projected
to utilize the Project area, and the availability of off-site foraging habitat,
the effects of the Proposed Action on the sharp-shinned hawk and its habitat
would be below the level of significance.
Northern harrier: Two (2) sightings of northern harriers were
made within the Project area during the biological surveys (Rado 1995).
The sightings were during the fall and were attributed to isolated birds
presumed to have been migrating through the area. There is no northern harrier
nesting habitat within the Project area. The Project would result in a small
reduction of the regional foraging habitat available to migrating northern
harrier, and it could result in a minor behavior modification of individual
birds that cross the Project area. Based on the low frequency in which northern
harrier are projected to utilize the Project area, and the availability
of substantial off-site foraging habitat, the effects of the Proposed Action
on the northern harrier and its habitat would be below the level of significance.
LeConte's thrasher: LeConte's thrashers were not recorded during
the biological surveys, which included playing recorded bird calls during
the breeding season in an attempt to elicit a response. However, prior records
suggest that LeConte's thrashers may occur within the Project area (CNDDB
1996; BLM records). If present, the species would
be subject to habitat loss, displacement of individuals to off-site areas,
and possible disruption of breeding and nest failure. Because of the availability
of substantial off-site thrasher habitat, the effects of the Proposed Action
on LeConte's thrasher and its habitat would be below the level of significance.
Crissal thrasher: A single crissal thrasher was observed within the
Project mine and process area during the surveys. The species is closely
associated with drainages and wash "edge" vegetation. A total
of about 87 acres of such habitats would be affected by Project actions.
Crissal thrashers that utilize these drainages would likely be displaced
into adjacent unmodified lands as a result of conversion of habitat. Depending
upon timing of year, nests may also be abandoned, resulting in mortality
of nesting birds and/or abandonment of eggs. Because of the availability
of substantial off-site crissal thrasher habitat, the effects of the Proposed
Action on the crissal thrasher and its habitat would be below the level
of significance.
Vaux's swift: Vaux's swifts utilize the general area, including the
Project area, during spring and fall migration. They do not nest in this
region. Development may result in minor behavioral modification of migrating
birds passing through the region. Mining activities would also result in
a reduction of the available foraging/resting habitats for migrating birds.
Because of the availability of substantial off-site swift foraging/resting
habitats, the effects of the Proposed Action on the Vaux's swift and its
habitat would be below the level of significance.
Golden eagle: Golden eagles were not observed during the biological
surveys. Eagle nesting sites are also absent from the Project area and vicinity.
The species may utilize the general area, including the Project mine and
process area, for foraging. Project construction and operations within the
Project area would result in the incidental loss of 1,340 acres of
potential golden eagle foraging habitat. Based on the widespread availability
of off-site foraging habitat for golden eagles, the effects of the Proposed
Action on this species and its habitat would be below the level of significance.
Prairie falcon: Biological surveys did not document the occurrence
of the prairie falcon. However, the prairie falcon has been previously recorded
within the general area and could utilize the Project area and surrounding
area for foraging (BLM records). Project construction
and operation activities within the Project area could result in the loss
of 1,340 acres of foraging habitat for prairie falcons. Based upon
widespread availability of off-site foraging habitat, the effects of the
Proposed Action on this species and its habitat would be below the level
of significance.
Cooper's hawk: Biological surveys did not document the occurrence
of the Cooper's hawk. However, the species has been recorded as a seasonal
visitor in the general area and could utilize the Project area and surrounding
area for foraging (BLM records). Project construction
and operation activities within the Project area could result in the loss
of 1,340 acres of foraging habitat for Cooper's hawk. Based on the
widespread availability of off-site foraging habitats for Cooper's hawk,
the effects of the Proposed Action on this species and its habitat would
be below the level of significance.
Long-eared owl: Biological surveys did not document the occurrence
of the long-eared owl. However, the species has been recorded as a seasonal
visitor in the general area and could utilize the Project area and surrounding
area for foraging (BLM records). Based on the
widespread availability of off-site foraging areas for long-eared owls,
the effects of the Proposed Action on this species and its habitat would
be below the level of significance.
Barn owl: Natural caves, fissures, old mine tunnels and shafts, or
abandoned buildings often used for barn owl nesting are not present within
the Project area. Project development would potentially result in the creation
of barn owl nesting within storage sheds, maintenance buildings, or other
"open" structures. Since this species has been recorded in the
general area (BLM records), Project operations
within the Project area would result in the potential reduction of 1,340 acres
of barn owl foraging habitat. Based on widespread availability of off-site
foraging habitat for barn owls, the effects of the Proposed Action on this
species and its habitat would be below the level of significance.
Yuma puma: No pumas or sign were documented during surveys of the
Project area. Use of the Project area by deer, a primary prey species for
pumas, suggests that mountain lions may occur in the general area. Unconfirmed
sightings of mountain lion in the region have been conveyed to the CDFG
by hunters (Personal Communication, Rusty McBride, CDFG, 1996). Mine construction
and operation activities would result in the reduction of 1,340 acres
of foraging habitat potentially available to mountain lions. Associated
impacts to deer could also incrementally affect the prey base for mountain
lions. Based on the widespread availability of off-site foraging habitat
for mountain lions, the effects of the Proposed Action on this species would
be below the level of significance.
American badger: Badgers are presumed to utilize the Project area
for foraging, but the actual number of badgers that may use the area is
indeterminate. Previous studies of the species reported individual badgers
having home ranges of 1,400 and 2,100 acres (Messick 1987). Based on
the area of these home ranges, few American badgers would be expected to
occupy habitat within the Project area. The Project would result in a reduction
of the habitat available to badgers in the Project area, and increased noise,
lighting, and traffic would likely result in behavior modifications by badgers
to avoid the area. Based on the availability of off-site foraging habitat,
the effects of the Proposed Action on the American badger and its habitat
would be below the level of significance.
Sensitive bat species: No sensitive bat species were recorded within
the Project mine and process area during the original biological surveys
(Rado 1995). No mine adits, caves, or large rock crevices exist in the Project
area, thereby limiting the species of bats which may day roost within the
Project mine and process area. However, some bat species could roost in
trees or in small rock crevices. A survey of the Project mine and process
area for bats was conducted by Patricia E. Brown, Ph.D. in June 1997 (see
Section 3.5.6.2). Five (5) sensitive bat species designated
by the USFWS as Special Status Species and/or California species of concern (CSC)
could conceivably roost, and also forage, in the Project area, including:
Yuma myotis, small-footed myotis, cave myotis, occult little brown bat,
and desert pallid bat. An additional six (6) Special Status Species/CSC
bat species would not roost in the Project area but could use the Project
area as nighttime foraging habitat, including: Townsend's big-eared bat,
spotted bat, western mastiff, California leaf-nosed bat, big free-tailed
bat, and pocketed free-tailed bat.
Large numbers of bats would neither be killed nor displaced by the Project.
Foraging habitat would be affected, but similar habitat is widespread around
the Project area. Night lighting from the Project would attract insects
and could result in a net increase in bats foraging in the vicinity of the
Project mine and process area. This could lead to individual bat collisions
with lights or drownings in ponds. However, based on the availability of
off-site day roost areas and foraging habitat, the effects of the Proposed
Action on sensitive bat species and their habitat would be below the level
of significance.
Mule deer: Desert deer are widely distributed throughout the Project
area and surrounding area, but the deer population is reported to be low
(Celentano and Garcia 1984). Deer were observed to use the northeast-southwest
trending wash channels as movement corridors and to also move cross-gradient
over the upland areas and across the washes in the Project area.
The Proposed Action would impact deer habitat by eliminating the use of
the Project mine and process area by deer over the life of the Project,
until habitat is reestablished, and would permanently eliminate the majority
of the open East Pit from deer habitat. Project-related impacts to deer
habitat could result in a slight net reduction in the numbers of deer that
seasonally utilize the Project area, and/or that may reside in the Project
area due to the availability of water in maintained guzzlers located south
and also east of the Project mine and process area. Potential impacts to
deer and deer habitat would include:
- The general loss of most of the Project mine and process area as foraging
habitat during the life of the Project, and in particular the loss of the
approximately 87 acres of microphyll woodland habitat which would
be destroyed during Project construction.
- To the extent the Project mine and process area serves as deer fawning
habitat, the approximately 87 acres of microphyll woodland in the
washes would be destroyed as potential fawning habitat during Project construction.
- Restricted access through the Project mine and process area as a result
of fencing may limit deer movement in the vicinity of the Project mine
and process area. Access to three (3) big game guzzlers located east and
south of the Project mine and process area boundaries would be slightly
reduced.
- Noise from equipment operation, blasting activities, and human presence,
as well as night lighting of the Project mine and process area facilities,
would be expected to inhibit deer activity in the immediate vicinity of
the Project mine and process area in the short-term; however, deer would
be expected to acclimate to Project noise over time and resume utilization
of the areas outside the boundaries of the Project mine and process area
(Personal Communication, Nancy Andrew, CDFG, 1997).
- Vehicles commuting on roads to the Project mine and process area would
increase the potential for vehicle impacts with deer and resulting injuries
and mortality. If the Project results in an approximate five (5) percent
increase in traffic (see Section 4.1.11.1.2), then a proportional
potential increase in traffic-related deer mortality (i.e., an increase
from approximately two (2) percent to 2.1 percent) would
be expected to result.
- Deer which penetrate the perimeter fence and/or process fence of the
Project mine and process area would be subject to an increased potential
for vehicle impact injuries and mortality and ingestion of potentially
harmful process pond solutions or other chemicals stored and used within
the Project mine and process area.
- Realignment of Indian Pass Road could impact migration routes, dispersal
corridors and deer movement. Deer are expected to acclimate to the road
realignment; however, there may be some permanent displacement.
- Water could accumulate in the East Pit (or West Pit, if not sufficiently
backfilled) and attract deer to the new water source, altering the habitat
for deer. Limited access to and from the pit(s) could potentially serve
as an opportunity for increased predation of deer.
- Deer may become stressed if they get into the Project mine and process
area, and this could reduce fawn production in does.
Because of the low density and scattered distribution of deer in the
area, and the relative abundance of similar habitat in the vicinity of the
Project area, the Proposed Action would not be expected to directly or indirectly
impact a large number of deer. Some deer would be indirectly impacted by
reduction of habitat quality through vegetation removal. Given conflicting
professional opinion as to the importance of the Project area and vicinity
for deer use and as fawning habitat, the specific significance of the impacts
of the Proposed Action on deer and deer habitat without the implementation
of those measures designed into the Proposed Action to reduce the impact
and compensate for the adverse effects on microphyll woodland habitat is
uncertain. However, with the implementation of these measures, impacts to
deer and deer habitat are below the level of significance. Elements of the
Project design which would mitigate impacts on deer include (see also those
measures identified under the applicable heading in Section 4.1.5.4):
- Constructing a 6-foot high, barbed-wire topped, chain-link fence around
all Project-created surface water sources within the Project mine and process
area, including the heap leach pad, process facilities, and fresh water
pond;
- Revegetating disturbed areas following mining activities, and including
native deer forage plants as a part of this effort (subject to BLM and CDFG approval);
- Performing revegetation within the permanent diversion channels, including
direct transplanting of microphyll species from disturbed drainages, planting
of young seedling palo verde and ironwood and seeding with species common
to the microphyll woodland habitat;
- Performing revegetation on selected adjacent drainages subject to historic
damage unrelated to the Proposed Action;
- Directing diverted surface drainages back into the same major channels
to maintain continuity of flow and water quality to habitat downstream
of the Project mine and process area;
- Constructing a rock barrier around the remnant East Pit and back filling
the pit to a level above any predicted pit lake, if necessary;
- Constructing three (3) off-site big game guzzlers at a location in
the vicinity of the Project area mutually agreeable to the Applicant, the
CDFG and the BLM; and
- Constructing one or more on-site big game or small game guzzlers at
the conclusion of final reclamation.
Desert bighorn sheep: No bighorn sheep were observed within the
Project area during the biological survey, and the Project area is not within
established bighorn habitat. Natural dispersal corridors, between Peter
Kane Mountain to the north and the Cargo Muchacho Mountains to the south,
lie several miles to the east of the Project mine and process area, and
these routes would not be directly affected by the Project activities. Although
noise from Project operations, especially from blasting, may be discernable
in these areas, the effect on bighorn sheep would be below the level of
significance. The Project facilities may impact movement of bighorn sheep
rams between mountain ranges; however, this direct route is not considered
a substantial movement corridor and the impact of the Project on desert
bighorn sheep movement would be below the level of significance.
4.1.5.4. Measures Incorporated by Project Design
and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
The following measures have been incorporated into the Project design
to reduce the impacts to plant and wildlife species and habitat during the
active life of the Project.
- 4.1.5-1: Applicant shall construct a fence around the entire Project
mine and process area. The fence shall be constructed no less than four
(4) feet in height with 3-strands of smooth wire, or equivalent. That portion
of the perimeter fence constructed along the western boundary of the Project
mine and process area, including all of the fenceline adjacent to Indian
Pass Road (see Figure 2.2), shall be a chain-link fence, no
less than six (6) feet in height, to restrict public access to the
Project mine and process area. The entire perimeter fence shall include
desert tortoise exclusion fencing, in conformance with responsible agency
requirements, to inhibit tortoise access to Project facilities (see also
Mitigation Measure 4.1.5-40). Applicant shall construct a chain-link fence,
no less than six (6) feet in height, with one (1) foot of barbed
wire at the top, around the ore leach pad, process facilities, and fresh
water pond to further restrict wildlife from accessing these facilities.
Applicant shall routinely inspect and repair the fences, as necessary.
Applicant shall document any deer or other wildlife mortalities observed
within the Project mine and process area, shall monthly report such mortalities
to the BLM and the CDFG, and shall work with
the BLM and CDFG to implement additional or
amended measures to reduce the mortalities. A field contact representative
(FCR) shall be responsible for maintaining the records of perimeter fence
inspections and repair, and shall have authority to direct the repair of
damaged or destroyed fences. The FCR may be a project manager, company
environmental coordinator, contract biologist, or other person identified
as responsible by the Applicant.
- 4.1.5-2: Applicant shall prohibit cross-country use of vehicles and
equipment except within those portions of the Project mine and process
area subject to surface disturbance.
- 4.1.5-3: Applicant shall cover the pregnant and barren
solution ponds with either small-mesh nets; a solid, 40-mil, HDPE/polypropylene
cover; floating plastic balls; or equivalent cover acceptable to the BLM to keep wildlife out of the ponds. Applicant
shall maintain the cover over the life of the Project. Applicant shall
keep records of all wildlife kills which may be associated with the use
of cyanide by the Project, including all dead wildlife found in or adjacent
to the ponds or heap. Individual threatened and endangered species found
dead on the Project mine and process area shall be sent for necropsies.
Observations of wildlife killed in the ponds or on the heap shall be reported
to the BLM, CDFG, and the U.S. Fish and Wildlife
Service (USFWS) monthly for evaluation and, if determined necessary, for
possible imposition of additional mitigation requirements.
- 4.1.5-4: Applicant shall advise Project employees, contractors, and
visitors of the need to adhere to speed limits and to avoid any animals,
including the desert tortoise, flat-tailed horned lizard, and deer which
may be encountered on or crossing roads to and from the Project area. Applicant
shall also require Project employees, contractors, and visitors to report
all incidences of wildlife injury or mortality resulting from Project-related
vehicle traffic on roads used to access the Project to the FCR, who shall
monthly report these incidences to the BLM and
the CDFG. Applicant shall participate in agency efforts to reduce mortality
of wildlife on the roads used as access to the Project when so requested
by the BLM.
- 4.1.5-5: Prior to completion of mining, Applicant shall conduct an
assessment of the potential for a pit lake to form in the East Pit. If
the assessment indicates a reasonable potential for a pit lake to form,
Applicant shall backfill the East Pit to
an elevation higher than the level of any pit lake which may be predicted
to form from the inflow of ground water and, thereby, prevent the creation
of an attractive nuisance for wildlife. The findings of the pit lake assessment
shall be completed and submitted for approval by the BLM
prior to the completion of mining activities. Applicant shall monitor open
pit areas monthly during the duration of post-mining reclamation for any
evidence of the formation of a pit lake. The results of this monitoring
shall be reported monthly to the BLM. Should
the BLM determine that the monitoring indicates
that a pit lake is forming or may form, the Applicant may be required to
conduct an additional study or place additional backfill
material into the bottom of the East Pit.
- 4.1.5-6: Before removal of the perimeter fence at the end of the active
life of the Project, Applicant shall regrade haul roads within the open
pit such that wildlife or humans may still use them to exit the residual
open pit should they pass the barricade around the rim.
The following additional measures have been incorporated into the
Project design to reduce the impacts on microphyll woodland habitat and
associated wildlife which utilize this habitat.
- 4.1.5-7: Applicant shall construct a fence, no less than four (4) feet
in height with 3-strands of smooth wire, or equivalent, around the approximately
40-acre south-central portion of the central wash internal to the Project
mine and process area which is not intended to be disturbed by Project
operations to prevent accidental surface disturbance of the microphyll
woodland habitat in this area during mine construction and operation.
- 4.1.5-8: Applicant shall provide periodic slug irrigation to enhance
the establishment of ironwood and deer browse vegetation within the surface
drainage identified by Mitigation Measure 4.1.5-7 to enhance the quality
of habitat and provide established deer browse which would be immediately
available at the end of the active life of the mine. Vegetation selected
for enhanced deer browse establishment shall be comprised of species known
to occur in the Project area. The irrigation shall be reduced and then
ceased once the vegetation is established. The composition of the seed
mix and the design of the vegetation enhancement measures shall be submitted
to the CDFG for approval prior to implementation.
- 4.1.5-9: Applicant shall construct and maintain during the life of
the Project three (3) big game guzzlers in a design and location acceptable
to the BLM and the CDFG in the general vicinity
of the Project mine and process area to provide for more intensive use
of the existing habitat by deer and other wildlife. Within one (1) year
of approval of the ROD, the Applicant shall have either: provided sufficient
funds to a third party (acceptable to BLM and
CDFG) which shall construct, own, and operate the guzzler; or completed
construction of the guzzler. Applicant or the acceptable third party shall
obtain the required permits from the BLM prior
to guzzler construction. The guzzler shall remain after reclamation.
- 4.1.5-10: Applicant shall provide periodic slug irrigation to enhance
the establishment of ironwood and deer browse vegetation along the western
slopes and banks of the approximately 3,000-foot section of the existing
ephemeral stream channel immediately adjacent to, but outside of, the east-southeast
boundary of the Project mine and process area. Vegetation selected for
enhanced deer browse establishment shall be comprised of species known
to occur in the Project area. Supplemental watering shall only be conducted
for the first few years to allow the plants to become established. Water
shall be reduced over a period of time to enable the plants to acclimate
to natural moisture conditions. The composition of the seed mix and the
design of the vegetation enhancement measures shall be submitted to and
approved by the CDFG prior to implementation.
- 4.1.5-11: Applicant shall conduct annual transect surveys in the spring
season of the ephemeral washes which flow out of the Project mine and process
area, the principal washes which flow into the Project mine and process
area upstream of the Project mine and process area to serve as a control,
and the undisturbed ephemeral washes within the Project mine and process
area, for the purpose of determining if Project construction and/or operations
are having an indirect adverse effect on microphyll woodland habitat not
directly impacted by surface disturbance. The surveys shall document the
diversity, density, and cover of the vegetation directly associated with
the washes, and shall include observations regarding the general "health"
of the vegetation. The surveys shall also document any observations regarding
sediment transport processes within the washes any incidental sightings
of deer fawn, bighorn sheep, bobcat, kit fox, mountain lion, or other species
specified by the BLM. An annual report of the
results of the surveys shall be prepared and submitted to the BLM and CDFG in a form acceptable to the BLM.
If, as a result of these surveys, microphyll woodland habitat downstream
of the Project mine and process area is determined to be adversely impacted
by the Project, appropriate additional mitigation measures may be required
by the BLM and shall be implemented by the Applicant.
BLM may require the Applicant to acquire title
to off-site private lands with comparable microphyll woodland habitat,
in a location acceptable to the BLM and the
Applicant, to compensate at a 3:1 ratio for adverse impacts to microphyll
woodland habitat not otherwise compensated for which cannot be mitigated
through application of these additional mitigation measures.
- 4.1.5-12: Applicant shall construct all stream channel diversions to
divert flows back into the same major wash system and ensure the continuing
flow of an equivalent pre- and post-Project quantity of water through the
major drainages to preserve the downstream microphyll woodland habitat
within the drainages (see also Mitigation Measure 4.1.5-15 and mitigation
measures provided for surface hydrology in Section 4.1.3.1.3).
- 4.1.5-13: Applicant shall implement the Project Reclamation Plan in
conformance with the requirements of the BLM
and Imperial County. The Reclamation Plan shall include a program for revegetation
of the permanent diversion channels, including the planting of seedlings
of young ironwood and palo verde at a density approximating that of the
displaced washes and seeding of the pre-Project wash habitat (see also
Mitigation Measure 4.1.5-17). The transplanted seedlings shall be
protected from browsing or trampling by wire cages for the first two (2)
years and from excessive sun by shade material, if necessary, or native
nurse plants, if available and necessary, to facilitate transplant success.
Microphyll woodland vegetation within the permanent diversion channels
shall be established during early mining operations and managed and monitored
throughout the life of the Project. Applicant shall conduct annual transect
surveys in the spring season of the diversion channels for the purpose
of determining revegetation success. The surveys shall document the diversity,
density, and cover of the vegetation directly associated with the washes,
and shall include observations regarding the general "health"
of the vegetation. An annual report of the transect surveys shall be prepared
and submitted to the BLM, Imperial County and
CDFG in a form acceptable to the BLM and Imperial
County. Should the surveys indicate that the revegetation of the diversion
channels may not meet the standards required by the approved Reclamation
Plan, the BLM and Imperial County may require
appropriate additional revegetation measures to be implemented by the Applicant.
- 4.1.5-14 Applicant shall construct and maintain as a part of final
reclamation, one or more big game and/or small game guzzlers within the
Project mine and process area in a design and location acceptable to the
BLM and the CDFG to enhance the area as habitat
for deer and other wildlife. Final Project reclamation bond(s) shall not
be released until either: the Applicant has provided sufficient funds to
a third party (acceptable to BLM and CDFG) which
shall construct, own, and operate the guzzler(s); or the Applicant has
completed construction of the guzzler(s). Applicant or the acceptable third
party shall obtain the required permit from the BLM
prior to guzzler construction. The guzzler(s) shall remain after reclamation.
The guzzler(s) shall be designed and constructed in a manner which allows
desert tortoise to readily exit the guzzler(s).
- 4.1.5-15: Project actions would require the realignment of sections
of washes. Applicant shall develop a specific plan for approval of the
BLM that ensures maintenance of intermittent
flood water flow down these realigned wash channels into unmodified drainage
boundaries outside of the Project in order to preserve vegetation and wildlife
habitat. Design of these sections of realigned wash shall also include
appropriate dimensions and slopes to accommodate continued use by wildlife
during mining operations and to facilitate revegetation. A specific plan
shall be prepared by Applicant and submitted to the ICPWD and BLM for review, and approval of the BLM,
prior to the onset of any activities that would result in disturbance to
these drainages. Plan design shall include the vegetation of channel diversions
with native species that include ironwood and palo verde in order to maintain
continuity of washes and enhance wildlife habitat, in conformance with
the approved Reclamation Plan. Unless explicitly directed otherwise by
the BLM (in consultation with the CDFG), all
diversion channel lining materials and rip rap shall be removed from the
diversion channels.
The following measures have been incorporated into the Project design
to reduce the long-term impacts of the Project on plant and wildlife habitat
and to enhance reclamation of plant and wildlife habitat.
- 4.1.5-16: Upon completion of mining activities, Applicant shall remove
all equipment and materials from the Project area. Unless explicitly directed
otherwise by the BLM (in consultation with the
CDFG), all diversion channel lining materials and rip rap shall be removed
from the diversion channels and any necessary reclamation completed by
the Applicant, consistent with the approved Reclamation Plan.
- 4.1.5-17: The Project Reclamation Plan shall include the collection
of both fairy duster seeds and winged cryptantha seeds and distribution
of the collected seeds of both species within appropriate microhabitats
within the Project mine and process area. During Project operations, the
Applicant shall experiment with the seeds (and transplants if reseeding
is not successful), of both species to assure plant success and survival.
Recovery of these two (2) species shall be considered successful when species
density meets or exceeds the criterion set forth in the Approved Reclamation
Plan.
- 4.1.5-18: Applicant shall stockpile available soil from the wash channels
to be disturbed within the Project mine and process area and store the
soil for subsequent use during reclamation activities. Soil stockpiles
shall be located away from washes and other areas prone to erosion and
consolidated as appropriate to reduce disturbance to undisturbed areas
within the Project mine and process area. Stockpiles shall be kept shallow
and dry, if not to be used within one (1) year of initial placement, to
protect seeds entrained in the soil.
- 4.1.5-19: Applicant shall salvage specimens of selected plant species
from the Project mine and process area prior to construction to be utilized
during habitat enhancement activities or other Project reclamation needs.
Plant species may include cactus, ocotillo, ironwood, palo verde, or other
appropriate species identified by the BLM.
- 4.1.5-20: Applicant shall implement weed control measures such that
all introduced plants (e.g., salt cedar (tamarisk species), mustard,
and other noxious weeds) will not become established within the Project
area. Manual or mechanical means of control shall be the preferred methods
employed. Use of other methods (e.g., herbicides) shall require approval
by the BLM. The weed control measures shall
be implemented within six (6) months of when noxious weeds are visually
identified within the Project area and shall continue over the life of
the Project. Tamarisk species shall be actively controlled throughout the
life of the Project by eradication of any seedlings or growth observed.
If tamarisk is determined to be a continuing problem after the completion
of reclamation, a portion of the reclamation bond in an amount determined
appropriate by the BLM and Imperial County shall
be retained to fund an eradication program to eliminate factor(s) conducive
to tamarisk growth (e.g., moist areas).
- 4.1.5-21: Applicant shall implement the revegetation program contained
in the Project Reclamation Plan approved by Imperial County and the BLM. The revegetation program shall include a test
plot program, surface contouring and shaping, salvage and distribution
of stockpiled soils, collection of a seedbank of seeds from within and
in the vicinity of the Project area, preparation of seedbeds, seeding with
approved mixtures of native plant species endemic to the area, planting
of the plants salvaged from the area prior to mine construction, monitoring
for invasion of noxious weeds or salt cedar, and vegetation success monitoring.
The standards for revegetation success shall be specific to each vegetation
type and based on reasonably achievable results that shall provide a plant
cover and density sufficient to support long-term revegetation. Final bond
release shall occur when the vegetation success criteria set forth in the
Reclamation Plan have been met and the reestablishment of vegetation is
confirmed.
- 4.1.5-22: Applicant shall integrate the revegetation program activities
with other stabilization and reclamation activities required by the approved
Reclamation Plan (see also Mitigation Measures 4.1.5-12 and 4.1.5-13).
- 4.1.5-23: Access roads which are created, or any other areas which
are disturbed for the construction of the transmission line, pipeline,
and well field, shall be reclaimed when they are not needed for ongoing
maintenance. Reclamation methods shall include regrading, surface preparation,
and revegetation either through seeding or natural processes.
- 4.1.5-24: To compensate for those lands not reclaimed within the East
Pit, Applicant shall perform reclamation activities on one or more off-site
locations on land in the vicinity of the Project acceptable to Applicant
and the BLM, as appropriate, to reclaim habitat
which has been adversely impacted by previous actions unrelated to the
Project.
- 4.1.5-25: Applicant shall repair any detected leak in the water pipeline
along Indian Pass Road as soon as reasonably possible in order to prevent
tamarisk invasion and eliminate an attractive nuisance to wildlife.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.5-26: Applicant shall enter into a Stream Alteration Agreement
with the California Department of Fish and Game (CDFG) as required pursuant
to California Fish and Game Code Section 1603 which shall contain those
measures which CDFG and Applicant agree may be necessary, or appropriate,
to mitigate, and compensate for, the impacts of the Project on the stream
channels and associated microphyll woodland habitat and wildlife. The October 31,
1997 draft of the Stream Alteration Agreement for the Imperial Project
includes the following substantive requirements, which are subject to modification
until agreed to by both parties:
(1) "For impacts to approximately 90 acres of microphyll woodlands,
the Operator shall mitigate, through the purchase of off site lands,
at a 3:1 ratio. The location of the mitigation area shall be subject to
review and approval of the Department. The mitigation lands shall be deeded
to the Department."
(2) "The Operator shall install and maintain for the life of the project,
three (3) big game guzzlers at locations tp be approved by the Department.
One additional guzzler shall be installed within the off-site mitigation
land addressed ... above. One guzzler will also be constructed within the
project site prior to final reclamation."
(3) "As addressed within the DEIS/EIR ..., Operator shall; fence the
approximately 40 acres contained within the central wash to prevent
human intrusion, enhance the surrounding microphyll woodland habitat within
the Central Wash area shall be fenced to prevent human intrusion, enhance
the surrounding microphyll woodland habitat through various methods, implement
and maintain a vigorous exotic and invasive weed control program, maintain
all setbacks, berms, and erosion control features within the project."
(4) "In those project areas where active nesting birds occur, the
Operator shall flag or stake a minimum of five (5) yards in all directions.
This flagged zone shall not be disturbed until the nest becomes inactive,
or unless otherwise directed by the Department."
- 4.1.5-27: Applicant shall comply with all of the terms and conditions
of the Biological Opinion prepared for the Project by the U.S. Fish and
Wildlife Service in response to the BLM request
for formal consultation pursuant to Section 7 of the Endangered Species
Act of 1973, as amended.
- 4.1.5-28: Project actions may require either an individual dredge and
fill permit (404 permit) from the U.S. Army Corps of Engineers (ACOE) or one or more Nationwide Permits. Applicant
shall obtain the appropriate authorization from the ACOE
prior to the onset of any actions that would disturb drainages within the
Project area.
- 4.1.5-29: The California Regional Water Quality Control Board, Colorado
River Basin Region (CRWQCB ) shall be notified
by the Applicant of Project actions, and Applicant shall comply with CRWQCB requirements for obtaining Waste Discharge
Requirements and Certification under Section 401 of the Clean Water
Act for proposed discharges to land and a general Storm Water Permit.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
The following measures were identified to mitigate the effects of
the Proposed Action on the Desert tortoise. These, or similar, mitigation
measures, have been required by the Biological Opinions issued by the U.S.
Fish and Wildlife Service for nearby projects, including the American Girl
Mine, the Mesquite Mine, and the Mesquite Regional Landfill. Each of these
measures would be required by the BLM for the
Proposed Action:
- 4.1.5-30: Applicant shall designate a field contact representative
(FCR) who shall be responsible for overseeing compliance with protective
stipulations for listed species. The FCR shall have authority to halt all
activities that are in violation of the stipulations. The FCR shall have
a copy of all appropriate stipulations when work is being conducted within
the Project area. The FCR may be a project manager, company environmental
coordinator, contract biologist, or other person identified as responsible
by the Applicant. Applicant shall provide the name and contact information
of the FCR to the BLM and applicable responsible
agencies prior to construction.
- 4.1.5-31: During the life of all Project activities, stockpiling of
equipment and vehicles shall utilize only those portions of the Project
area that would be subject to permanent disturbance. Temporary or inadvertent
disturbance of remaining portions of the area should be minimized by: staking,
"flagging," or otherwise clearly marking the boundaries of the
alignment; notifying employees of the specific areas, boundaries of the
areas, and the need to avoid disturbance to remaining areas; and posting
signs or erecting temporary fencing at access points to limit access to
authorized vehicles and equipment only.
All employees shall be instructed that their activities shall be confined
to locations within flagged or otherwise marked areas.
The area of disturbance shall be confined to the smallest practical area,
considering extent and location of ore bodies, topography, placement of
facilities and access roads, locations of sensitive
species , public health and safety, and other limiting factors. To
the extent practical, previously disturbed areas within the Project mine
and process area shall be used for the placement of equipment, work staging
sites, or parking of vehicles.
- 4.1.5-32: Open pipeline trenches, test holes, or test trenches shall
be regularly inspected by the FCR, or qualified biologist acceptable to
the BLM, a minimum of three (3) times per
day. During excavation of trenches or holes, escape ramps consisting of
loose earth deposited in the test hole or trench shall be placed to facilitate
the escape of any wildlife species that may enter the excavations. Any
animals discovered shall either be allowed to escape before activities
resume or carefully removed from the pit or trench and allowed to escape.
A final inspection of the open trench segment or hole shall also be made
by the FCR, or qualified biologist acceptable to the BLM,
immediately prior to backfilling. Arrangements shall be made prior to the
onset of maintenance or construction to ensure that listed wildlife species
can be removed from the trench without violating any requirements of the
federal or California Occupational Safety and Health Administration. All
test holes shall be immediately capped or abandoned upon completion of
drilling to prevent access of wildlife.
- 4.1.5-33: Toxic materials maintained on the Project area shall be stored
and used in a manner that prevents harm to desert tortoises and other wildlife
species. Methods of containment shall be approved by the BLM.
- 4.1.5-34: Nets or other suitable coverings shall be placed over all
ponds containing toxic solutions to prevent contact by area wildlife species,
including bats. These coverings shall be regularly inspected and maintained
by Applicant for the duration of the Project. Methods of cover, inspection,
and maintenance shall be approved by the BLM.
- 4.1.5-35: Project employees involved with regular activities shall
be required to take a threatened and endangered species education training
program which shall include a discussion of both endangered and threatened
species and species that are not endangered or threatened. The program
shall include information on the biology of listed, sensitive and unlisted
species as well as the desert tortoise, flat-tailed horned lizard, mule
deer, big horn sheep, and bats and their occurrence in the Project area.
The discussion shall include information on the measures being implemented
for the protection of these species and their habitats during Project activities
and means by which individual employees can facilitate this process.
A program approved by BLM shall be employed
and taught by a qualified individual acceptable to the BLM.
Wallet-size cards signifying completion of training shall be issued to
employees. All employees shall participate in the education program prior
to commencing Project activities. New employees shall receive formal approved
training prior to working on-site. The program shall typically last from
between one and two hours and shall cover the following topics at
a minimum:
- Distribution in general and in the Project area;
- General behavior and ecology;
- Sensitivity to human activities;
- Legal protection;
- Penalties for violation of State and federal laws;
- Reporting requirements; and
- Project mitigation measures.
- 4.1.5-36: Incidences of observations of desert tortoises and their
sign during activities shall be conveyed to the FCR during all Project
activities. Employees shall be notified that they are not authorized to
handle or otherwise move any desert tortoises encountered.
- 4.1.5-37: Tortoises commonly seek shade during the hot portions of
the day. During mine project activities, employees shall be required to
check under equipment and vehicles prior to moving such. If tortoises are
encountered, the vehicle shall not be moved until such animals have voluntarily
moved to a safe distance away from the parked vehicle.
- 4.1.5-38: If desert tortoises must be moved during any Project activities,
the following procedures shall be implemented by persons authorized by
the USFWS to handle desert tortoises:
(1) Desert tortoises shall be handled only by an authorized tortoise handler
and only when necessary. New latex gloves shall be used when handling each
desert tortoise to avoid the transfer of infectious diseases between animals.
Desert tortoises shall be moved the minimum distance possible within appropriate
habitat to ensure their safety. In general, desert tortoises shall not
be moved in excess of 1,000 feet for adults and 300 feet for
hatchlings. An authorized tortoise handler should follow the general handling
methods contained in the "Protocols for Handling Live Tortoises"
(USFWS 1990).
(2) Desert tortoises that are found above ground and need to be moved shall
be placed in the shade of a shrub. All desert tortoises removed from burrows
shall be placed in an unoccupied burrow of approximately the same size
as the one from which it was removed. All excavation of desert tortoise
burrows shall be done using hand tools, either by, or under the direct
supervision of, an authorized tortoise handler. If an existing burrow is
unavailable, an authorized tortoise handler shall construct or direct the
construction of a burrow of similar shape, size, depth, and orientation
as the original burrow. Desert tortoises moved during inactive periods
shall be monitored for at least two days after placement in the new burrows
to ensure their safety. An authorized tortoise handler shall be allowed
some judgement and discretion to ensure that survival of the desert tortoise
is likely.
(3) If desert tortoises need to be moved at a time of the day when ambient
temperatures could harm them (less than 40 degrees F or greater than
90 degrees F), they shall be held overnight in a clean cardboard
box. These desert tortoises should be kept in the care of an authorized
tortoise handler under appropriate controlled temperatures and released
the following day when temperatures are favorable. All cardboard boxes
shall be appropriately discarded after one use.
(4) All desert tortoises moved shall be marked for future identification.
An identification number using the acrylic paint/epoxy covering technique
should be placed on the fourth costal scute (USFWS 1990). No notching should
be authorized.
To facilitate clearing the area of desert tortoises, excavation of burrows
should begin no more than fourteen (14) days prior to the onset of
surface disturbing activities, as long as a final survey is conducted within
24 hours of the onset of activities to ensure that desert tortoises
have not returned to the work area.
- 4.1.5-39: In order to minimize any exposure risk to desert tortoises,
a specially designed fence shall be constructed around all portions of
the Project area containing pits, ponds, waste rock stockpiles, ore processing
areas, maintenance areas, and surface facilities. The final fence design
shall be discussed with and found acceptable to the USFWS, BLM,
and CDFG. The desert tortoise exclusion fence must meet the following preliminary
design specifications:
(1) Fencing shall result in a non-breachable barrier, and its support structure
may be comprised of a variety of materials;
(2) Galvanized 2-inch diameter mesh and 36-inch wide hardware cloth shall
be used; and
(3) The hardware cloth shall be buried 12 inches underground, extend
at least 24 inches above the ground, and be firmly attached to the
bottom of the perimeter fence and other wildlife exclusion fences.
- 4.1.5-40: Following fence installation, and prior to initiation of
mining, authorized biologists under the supervision of an authorized tortoise
handler shall conduct a complete (i.e., 100%) survey for desert tortoises
within the fenced area. All tortoises found shall be marked and removed
from the fenced mine area for safe off-site release within 1,000 feet
of the outside of the Project fence using protocols acceptable to the BLM, USFWS, and the CDFG. Prior to release, a total
of up to ten (10) of these tortoises (consisting, insofar as possible,
of equal sex ratios of adult animals) shall be equipped with radio transmitters,
and an equal number of individual additional tortoises (consisting, insofar
as possible, of equal sex ratios of adult animals) from the "resident"
tortoise population outside of the Project mine and process area shall
also be equipped with radio transmitters. For a three-year period, the
specific locations of all telemetered tortoise will be rechecked at monthly
intervals by the FCR and mapped and recorded. Once each year, an qualified
biologist will examine telemetered tortoises and record data relative to
the animal's location, movements, health, and any changes noted. Data from
these surveys will be used to assess the effects of relocation on both
the tortoises relocated from the Project mine and process area and those
resident tortoises present within the relocation area.
- 4.1.5-41: At the conclusion of Project pre-activity surveys and the
relocation of any desert tortoises outside of the Project fence, Applicant
and an authorized tortoise handler shall prepare a summary report documenting
the desert tortoise protection measures implemented. The summary report
shall be submitted to the BLM.
- 4.1.5-42: Pipeline placement design outside of tortoise-proof fenced
project boundaries shall allow for the unimpeded movement of tortoises
and other small terrestrial wildlife species.
- 4.1.5-43: That portion of the transmission line corridor extending
outside of the fenced Project mine and process area boundary shall be re-surveyed
for desert tortoise burrows and pallets within fourteen (14) days preceding
line upgrading/construction. Tortoise burrows and pallets encountered within
the construction zone (if any) shall be conspicuously flagged by the surveying
biologist(s) and avoided during power pole placement or existing line upgrading.
Contingent upon the findings of the pre-survey for the transmission line
upgrade/construction, a determination shall be made by the BLM
as to whether or not on-site desert tortoise monitoring would be required
during the transmission line upgrade/construction activities.
- 4.1.5-44: Transmission and distribution pole design shall prevent nesting
or perching by ravens, a major predator of young desert tortoises (see
also Mitigation Measure 4.1.5-54).
- 4.1.5-45: As an alternative to the use of speed bumps, notification
signs for the desert tortoise and speed limit signs shall be placed and
maintained within the Project boundary by Applicant to reduce chances for
inadvertent vehicle-induced injury or mortality to desert tortoises and
other wildlife species. Applicant, with the concurrence of Imperial County,
shall also place these signs along Indian Pass Road leading to the Project
mine and process area.
- 4.1.5-46: Applicant shall participate in the BLM
desert tortoise program for acquiring offsetting lands in compensation
for adverse modification of desert tortoise habitat. Under the BLM policy, undesignated lands such as the Project area,
where tortoises or tortoise sign are located, become Class III tortoise
habitat. Within Class III habitat, an offsetting ratio of 1:1 (e.g., one (1)
acre of land secured and protectively managed for each acre affected) is
applied. Lands shall be first considered in Imperial County and will include
87 acres of habitat within microphyll woodland.
- 4.1.5-47: For any well field changes or drilling activities subsequently
proposed for the Project, Applicant shall comply with the relevant terms
and conditions of the Biological Opinion for Small Mining and Exploration
Operations in the California Desert, dated June 1, 1992, prepared
with respect to desert tortoise by the USFWS, and amended as necessary
to be consistent with the desert tortoise protection measures prescribed
in the USFWS Biological Opinion for the Project.
The following measures were developed to mitigate the effects of the
Proposed Action on wildlife and wildlife movements should mining be suspended
or terminated prior to either partial or complete backfilling of the West
Pit and Singer Pit:
- 4.1.5-48: Should mining be terminated prior to backfilling of the West
Pit above the ground water level, Applicant shall conduct an assessment
of the probability of the formation of a pit lake after mining. Any evaluation
of the potential for the formation of a pit lake in an open pit shall consider
the quantity of surface flow runon and direct precipitation. If the assessment
reasonably indicates that ground water encountered in the West Pit may
enter the pit in sufficient quantity, considering evaporation, to create
a pit lake, the Applicant shall place sufficient backfill
into the open portion of the West Pit to raise the floor of the pit to
a level higher than the level of any pit lake which the study indicates
may form.
- 4.1.5-49: Any pit left open following the completion of mining shall
be left in a condition which minimizes the potential for, and quantity
of, water which may enter the pit through surface water runon. In addition,
the bottom of any pit left open after the completion of mining shall be
composed of a layer of loose rubble to minimize the potential for the formation
of standing water in the bottom of the pit from either precipitation or
surface water runon.
- 4.1.5-50: Before removal of the perimeter fence, Applicant shall regrade
haul roads within the open pit(s) such that wildlife or humans may still
use them to exit the residual open pit(s).
Other Mitigation Measures (These are measures which may further
reduce the impacts of certain effects which are below the level of significance
without mitigation):
- 4.1.5-51: A Revegetation and Monitoring Review Committee shall be formed
to serve in an advisory capacity to the BLM
and Imperial County. The committee shall review the annual vegetation monitoring
reports filed by the Applicant for the purpose of interpreting the information
contained in the reports, advising the Applicant of actions it might take
to improve the success of its revegetation efforts, and advising the BLM and Imperial County as to adjustments which
should be made to the revegetation success standards. The composition of
the committee shall be proposed by the Applicant and approved by the BLM and Imperial County.
- 4.1.5-52: Chuckwallas shall be moved away from any threats during construction
activity and if found within the Project mine and process area during mining
operations (approximately 100 meters outside the perimeter fence).
- 4.1.5-53: To prevent the inadvertent electrocution of raptors, unless
otherwise agreed to by the authorized officer in writing, transmission
and distribution lines shall be constructed in accordance with standards
outlined in the publication "Suggested Practices for Raptor Protection
on Power Lines" (Raptor Research Foundation, Inc., 1996). The right-of-way
holder shall assume the burden and expense of proving that pole designs
not shown in this publication are "raptor safe." Such proof shall
be provided by a raptor expert approved by the authorized officer. The
BLM reserves the right to require modifications
or additions to all power line structures placed on these rights-of-way
should they be necessary to ensure the safety of large perching birds.
Such modifications and/or additions shall be made by the holder without
liability or expense to the United States.
- 4.1.5-54: Trash and food items shall be contained in closed containers
to reduce attractiveness to opportunistic predators such as ravens, coyotes,
and kit foxes.
- 4.1.5-55: Recreational firearms and pet dogs shall be prohibited from
the Project mine and process area.
- 4.1.5-56: Applicant shall contact local animal control agents to remove
feral dogs that are observed within the Project area.
4.1.5.5. Unavoidable Adverse Effects and Level
of Significance After Mitigation
The Proposed Action would result in the unavoidable loss of approximately
87 acres of tree/shrub vegetation habitat (desert wash microphyll woodland
habitat) and approximately 1,215 acres of shrub/scrub vegetation habitat
(desert succulent scrub habitat) within the Project mine and process area
over the life of the Project. A total of 1,137 acres of this area would
be subject to reclamation measures at the end of the Project life to reestablish
the vegetation and wildlife habitat, including 33 acres in the bottom
of the open East Pit. Approximately 165 acres on the slopes of the
East Pit would not be reclaimed, but the Applicant has agreed to reclaim
an equal number of acres disturbed by others located outside of the Project
area. Approximately 198 acres, comprising the remnant East Pit, would
be barricaded to discourage pit access by terrestrial species. Approximately
one-half (2) of the disturbed microphyll woodland habitat would be
lost and not reclaimed at the completion of reclamation. An additional 36 acres
of shrub/scrub vegetation (desert succulent scrub habitat) and approximately
2 acres of tree/shrub vegetation (desert wash microphyll woodland habitat)
would be lost within the Project ancillary area; and approximately 21 acres
of shrub/scrub vegetation (desert succulent scrub habitat) and 1 acre
of tree/shrub vegetation (desert wash microphyll woodland habitat) would
be lost within the overbuilt 92 kV/34.5 kV transmission line corridor,
although all of this would be subject to reclamation. Resident and non-resident
wildlife species dependent on this habitat would be subject to displacement
and increased mortality.
The Proposed Action would result in the unavoidable "incidental take"
of an estimated 33 to 57 desert tortoises (a federal- and state-listed
threatened species) currently occupying the Project area, principally through
harassment and some through direct mortality. Mitigation measures are proposed
in this EIS/EIR in addition to those of the Proposed Action which would
reduce the effects to below the level of significance.
If mining is suspended or terminated prior to backfilling of the West Pit,
the West Pit would remain as an open excavation and could produce adverse
effects on wildlife. Mitigation measures are proposed in this EIS/EIR which
would reduce these effects to below the level of significance.
The mitigated effects of the Proposed Action on biological resources are
below the levels of significance.
4.1.6. Cultural and Paleontological Resources
This section is based on the cultural resource report prepared for the
area of the Proposed Action by KEA Environmental, Inc. (Pigniolo et al.
1997), which summarizes the results of the ethnohistoric research conducted
by Tierra Environmental Services (Baksh 1997). The non-confidential portions
of the KEA report are provided as Appendix L of this EIS/EIR. The Tierra
report is included as an appendix to the KEA report.
4.1.6.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Disrupt or adversely affect a historic property, including a property
with traditional cultural significance (as determined by the NRHP and implementing
regulations); or
- Disrupt or adversely affect a significant paleontological site except
as part of a scientific study.
Implementation of the Proposed Action would require local and state agencies
to demonstrate compliance with CEQA, for which specific guidance regarding
cultural resources is presented in Appendix K of the CEQA Guidelines.
Federal agencies must demonstrate compliance with the National Historic
Preservation Act (Public Law 89-665); 80 Stat 915; 16 USC 470;
as amended) [NHPA], which requires actions similar to CEQA for the protection
of significant cultural resources. Local agencies may use the NHPA process
to demonstrate compliance with CEQA.
Section 106 of NHPA requires a federal agency with jurisdiction over
a project to evaluate the effect of the proposed project on properties included
on, or eligible for, the National Register of Historic Places (NRHP). Federal
agencies must also provide the Advisory Council on Historic Preservation
(ACHP) an opportunity to comment on the effects
of the proposed project to these properties. The 1992 amendments to the
law particularly strengthened Indian Tribe involvement in the process. Specific
guidance for these actions are found in federal regulations at 36 CFR
Part 800, and in the programmatic agreement between BLM,
ACHP, and the California State Historic Preservation
Officer (SHPO).
The basic steps in the Section 106 process are:
Step 1 - Identification and Evaluation of Historic Properties (Cultural
Resources). Properties within a project's area of potential effect (APE) are identified and, in consultation with the
SHPO, evaluated through application of NRHP criteria for eligibility for
listing (found at 36 CFR Part 60.4), in conformance with the Secretary
of the Interior's Standards and Guidelines for Evaluation (48 Federal
Register 44723-44726). The full content of the eligibility criteria
are provided as follows:
"The quality of significance in American history, architecture, archeology,
engineering, and culture is present in districts, sites, buildings, structures,
and objects that possess integrity of location, design, setting, materials,
workmanship, feeling and association and:
"A. That are associated with events that have made a significant contribution
to the broad patterns of our history; or
"B. That are associated with the lives of persons significant in our
past; or
"C. That embody the distinctive characteristics or a type, period,
method of construction, or that represent the work of a master, or that
possess high artistic values, or that represent a significant and distinguishable
entity whose components may lack individual distinction; or
"D. That have yielded, or may likely yield, information important in
prehistory or history."
Step 2 - Assessment of Effects. The project's effects on cultural resources
listed or determined eligible for listing on the NRHP are assessed through
application of the Criteria of Effect found at 36 CFR Part 800.9(a).
If no effect is found, the federal agency consults with the SHPO and
provides documentation in support of the No Effect Determination. If no
objection occurs during a 15-day review and comment period, the project
can proceed.
If an effect is found, the Criteria of Adverse Effect found at 36 CFR
Part 800.9(b) are applied. The results could include: no adverse effect
where, while an effect could occur, it would not be harmful to those characteristics
that qualify the cultural resource for NRHP listing; or adverse effect where
an effect could occur that would diminish the integrity of those characteristics
that qualify the cultural resource for NRHP listing.
In the case of the Proposed Action, an Adverse Effect finding is probable.
The Area of Potential Effect (APE) contains cultural
resources of high religious and heritage significance that cannot be avoided.
Step 3 - Consultation. BLM and the SHPO consult
and notify the ACHP, whose participation is
optional. The purpose of the consultation is to develop a Memorandum of
Agreement (MOA) or to determine that no MOA is needed. Interested parties,
including Indian Tribes (as appropriate), are invited to participate in
the consultation.
Step 4 - ACHP Comment. The ACHP
reviews the MOA and, following the incorporation of proposed changes, accepts
and signs it. In the absence of an MOA, the ACHP
issues written comments, which BLM considers
and then notifies the ACHP of its decision.
4.1.6.2. Impacts of the Proposed Action
In addition to other changes, this section has been substantially modified
from the November 1996 Draft EIR in response to comments to: assess the
impacts to cultural resources and features identified during the intensive
cultural resource resurvey of all areas of potential surface disturbance
with the involvement of the Quechan Tribe; and undertake meaningful consultation
with the Quechan Tribe and other Native American tribes.
Since no paleontological resources have been found within the Project area,
and none are believed present, implementation of the Proposed Action would
not have an effect on any paleontological resources, and would produce no
significant impacts.
As stated in Section 3.6.2.3, an intensive Class III pedestrian
survey and cultural resources inventory of the Project area, the overbuilt
92 kV/34.5 kV transmission line corridor, and additional buffer
areas, has been completed. The field investigators evaluated 55 archaeological
sites and the Indian Pass-Running Man ATCC as
eligible for the NRHP (see Appendix L). The Indian Pass-Running Man
ATCC and large multi-component sites in the
Project mine and process area are evaluated as eligible under Criteria "A,"
"C" and "D" (see 36 CFR 60.4). Prehistoric
geoglyphs along the overbuilt 92 kV/34.5 kV transmission line
corridor are evaluated as eligible under Criteria "C" and
"D." Most prehistoric trails are evaluated as eligible under Criterion "D"
only, but named trails, those associated with a concentration of cultural
features, and those that are particularly well preserved are evaluated as
eligible under Criteria "C" and "D". Camp Pilot
Knob is evaluated as eligible under Criteria "A" and "D."
Ceramic scatters and several other prehistoric sites along the transmission
line are eligible under Criterion "D."
Impacts to the cultural resources ultimately determined eligible for the
NRHP under criterion "D" would be considered significant
unless a treatment program to recover the scientific information and other
NRHP-qualifying values of each resource is successfully implemented before
the Proposed Action proceeds with the activities which would impact that
resource. If cultural resources determined to be significant under Criterion "A,"
"B" or "C" are adversely affected by the Proposed Action,
a determination of adverse effect would need to be made by the BLM, and the resulting impacts would be significant.
Much of the Project mine and process area is expected to undergo direct
impacts from excavation of the open pits and construction and operation
of the leach pad, waste rock stockpiles, soil stockpiles, diversion channels,
haul and access roads, and associated processing and support facilities.
The remaining undisturbed acres within the Project mine and process area
are principally the throughgoing ephemeral stream channels and isolated
areas located between areas of disturbance. Given the intensive nature of
the Proposed Action, essentially all of the cultural resources within the
Project mine and process area are expected to experience either direct or
indirect impacts without special mitigation. Glamis Imperial has adjusted
the layout of several Project facilities within the Project mine and process
area since November 1996 to avoid direct impacts to certain culturally significant
features within the large multi-component sites. The Project mine and process
area boundary has been moved and the size of the Project mine and process
area reduced to avoid a trail and geoglyph system. One (1) waste rock
stockpile and two (2) soil stockpiles have been eliminated, and the
configuration of the remaining waste rock stockpiles, soil stockpiles, haul
roads, and the heap leach pad have been adjusted to avoid several trails,
geoglyphs, and other culturally significant features. However, it is not
economically feasible to avoid all of the features that contribute to the
significance of these cultural resource sites, and the direct and indirect
impacts to these eligible cultural resources within the Project mine and
process area would be significant.
Because the entire Project mine and process area is completely fenced, no
direct impacts are expected from operations conducted within the Project
mine and process area to identified cultural resource sites located outside
of the fence. However, indirect impacts to identified cultural resources
located adjacent to, but outside of, the Project mine and process area may
occur if more intense recreational use occurs in these areas as a result
of these uses being excluded from the Project mine and process area. These
indirect impacts to eligible cultural resources would be significant.
Project facilities constructed or operated within the Project ancillary
area are either narrow, linear features (such as the transmission line,
water pipeline, and Indian Pass Road realignments), or features of relatively
small surface area (such as the water well pad areas and well pump generator
area). Because there is generally more flexibility regarding the actual
siting of each of these Project components, avoidance of NRHP-eligible cultural
resources within the Project ancillary area is possible, although not completely
certain. Indirect impacts to identified cultural resources located adjacent
to the Project ancillary area may also occur, either as the result of increased
use of these areas by Project workers and service personnel, or if more
intense recreational use occurs in these areas. These potential direct and
indirect impacts to eligible cultural resources would be significant.
Surface disturbance associated with the construction of the overbuilt 92 kV/34.5 kV
transmission line is estimated at a maximum of 22 acres. This consists
of redisturbance of many of those areas disturbed during original construction
of the 34.5 kV transmission line in the mid-1960's (pole access trails,
construction areas, cable pulling stations, etc.) and some new disturbance
associated with the pole access trails, pole construction areas, cable pulling
stations, and construction staging areas. Because there is substantial flexibility
regarding the location of those overbuilt 92 kV/34.5 kV transmission
line facilities which produce the new surface disturbance, and because most
of the significant cultural features are located in portions of the cultural
sites outside of the actual overbuilt 92 kV/34.5 kV transmission
line corridor, it is possible, but not certain, that all of the identified
NRHP-eligible cultural resources within the overbuilt 92 kV/34.5 kV
transmission line corridor would be avoided. However, the direct and indirect
impacts of the construction of the overbuilt 92 kV/34.5 kV transmission
line on eligible cultural resources would be significant prior to mitigation.
Because of the large size of Camp Pilot Knob (CA-IMP-[TL-35]), complete
avoidance of this cultural resource site by construction of the overbuilt
92 kV/34.5 kV transmission line would not be possible. However,
relatively little ground disturbance to this property would occur because
most of the pole locations are immediately adjacent to the existing Sidewinder
Road. Therefore, the field investigators have concluded that the values
that make the property eligible for the NRHP would not be adversely affected
by the construction (see Appendix L), and thus this would not result
in a significant impact. Indirect adverse affects to significant historic
cultural resources associated with Camp Pilot Knob located adjacent to the
overbuilt 92 kV/34.5 kV transmission line corridor may occur if
these properties are incidentally disturbed by transmission line construction
workers. This potential indirect impact to this eligible historic cultural
property would be significant.
The Indian Pass-Running Man ATCC, including
the affected section of the Trail of Dreams, is evaluated as eligible under
Criteria "A," "C" and "D." The Project
mine and process area cannot avoid impacts to the Indian Pass-Running Man
ATCC. According to knowledgeable Quechan representatives,
development of the Project would destroy their ability to use the Indian
Pass-Running Man ATCC for religious and educational
purposes, which would have a "devastating" impact on their cultural
heritage. Between fifteen (15) and twenty (20) percent of the
Indian Pass-Running Man ATCC would be physically
disturbed by the Project mine and process area. The Quechan have stated
that construction of the Project would permanently cut-off their ability
to use the Trail of Dreams to travel physically and spiritually to the sacred
Newberry Mountain. Additionally, because views into and from the Indian
Pass-Running Man ATCC contribute to the significance
of the Indian Pass-Running Man ATCC, the construction
of the waste rock stockpiles and heap would cause a permanent, out-of-character
visual intrusion that would severely disrupt cultural use of the Indian
Pass-Running Man ATCC. Similarly, solitude is
an important contributing characteristic of the Indian Pass-Running Man
ATCC, and operation of the Project would cause
substantial aural impacts to the Indian Pass-Running Man ATCC.
Aural impacts would be long-term, but not permanent, as they would cease
upon completion of mining and reclamation. Some of the Project ancillary
facilities are also located within the Indian Pass-Running Man ATCC, and would adversely affect the character of the
Indian Pass-Running Man ATCC, although to a
relatively minor degree when compared to the impact of the Project mine
and process area on the Indian Pass-Running Man ATCC.
These impacts to the Indian Pass-Running Man ATCC
are considered significant.
4.1.6.3. Measures Incorporated by Project Design
and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.6-1: To reduce Project impacts on identified cultural resources,
Project facilities associated with the Project mine and process area shall
be located consistent with those presented in the Plan of Operations (Revised
September 1997). This shall include all of the Project revisions included
since the previous Plan of Operation (Revised October 1996), including
the revised boundary of the Project mine and process area, the reduction
in the height of the waste rock stockpiles, the elimination of one (1)
waste rock stockpile and two (2) soil stockpiles, and the reconfiguration
of the remaining waste rock stockpiles, soil stockpiles, haul roads, and
the heap leach pad.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
No specific measures.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
- 4.1.6-2: Applicant shall designate a project contact representative
(PCR) who would be responsible for overseeing Project compliance with the
conditions and stipulations for cultural resources. The PCR shall have
authority to halt all activities that are in violation of the stipulations.
The PCR may be a project manager, company environmental coordinator, or
other person identified as responsible by the Applicant. Applicant shall
provide the name and contact information of the PCR to the BLM
prior to construction.
- 4.1.6-3: Should previously unidentified cultural resources be discovered
during project construction or operations, Applicant shall immediately
cease all activities in the immediate vicinity of the discovery and notify
the BLM. Activities shall not be reinitiated
in the vicinity of the discovery until authorized by the BLM.
The following mitigation measures were identified by KEA Environmental,
Inc. (Pigniolo et al. 1997) as a result of the inventory and evaluation
of cultural resources that may be affected by the Proposed Action. These
mitigation measures have not been incorporated in the Project by the Applicant,
but may be incorporated, in whole or in part, into BLM's
Record of Decision for the Proposed Action following completion of on-going
consultation with the SHPO and ACHP pursuant
to Section 106 of the National Historic Preservation Act, and on-going
Government-to-Government consultation with the Quechan Tribe as required
by President Clinton's directive of April 29, 1994:
The following measures are proposed to mitigate the physical disturbance
within the Project mine and process area which will occur to the features
of religious-symbolic significance within the Indian Pass-Running Man ATCC:
- 4.1.6-4: Extant cultural features in the Indian Pass-Running Man ATCC should be avoided to the extent possible.
KEA's GPS data base should be provided to Glamis Imperial to determine
whether additional features can be avoided.
- 4.1.6-5: A professional archaeologist should flag or fence avoided
features near construction areas prior to initial site preparation. Environmental
inspectors should monitor avoidance. Flags outside of the perimeter fence
should be removed immediately after construction of that fence.
- 4.1.6-6: An archaeological data recovery program conforming to that
recommended in Chapter 9 of the KEA report should be implemented and
should include a description and analysis of the features and artifacts
that would be destroyed by the project and a technical archaeological report.
The following measures are proposed to mitigate the physical disturbance
within the Project mine and process area which will occur to significant
Native American trails and will cut-off the ability of the Quechan to travel
physically and spiritually along the Trail of Dreams:
- 4.1.6-7: In consultation with the Quechan, extant trails in the Indian
Pass-Running Man ATCC should be field mapped
and their significance to Native Americans ascertained. Low-level aerial
photography and video photography should be used to document trails that
will be destroyed. It appears from present information that certain trail
corridors through the Indian Pass-Running Man ATCC
west of the mine and process area can be preserved, including routes to
Avikwaame. Preserved segments with high Native American sensitivity
should be nominated to the NRHP and a preservation plan prepared and adopted
by the BLM.
The following measures are proposed to mitigate the physical disturbance
and visual and aural intrusions in and from the Project mine and process
area into the Indian Pass-Running Man ATCC which
will conflict with the Quechan traditional practices and inhibit the Quechan's
ability to conduct traditional religious activities at the Indian Pass-Running
Man ATCC:
- 4.1.6-8: In accordance with the current Plan of Operations, the height
of the waste rock stockpiles and heap should be restricted to 300 feet.
- 4.1.6-9: The BLM should continue consultation
with the Quechan to ensure continued access to the Indian Pass-Running
Man ATCC during Project implementation and
after Project closure.
The following measures are proposed to mitigate the disturbance created
within the Project mine and process area which will inhibit or destroy the
Quechan's ability to use the Indian Pass-Running Man ATCC
for traditional cultural education programs:
- 4.1.6-10: Provide for a cultural educational program which would include
a professional-quality video documentary of the Indian Pass-Running Man
ATCC prior to disturbance; a full or part-time
teaching/curatorial position for a Quechan tribal member for a period of
three (3) to five (5) years; preconstruction cultural educational
classes in the Indian Pass-Running Man ATCC;
and a comprehensive report documenting Quechan history and prehistory written
in part or in its entirety by the Quechan.
- 4.1.6-11: Delay or phase construction activities to allow the Quechan
the opportunity to conduct traditional cultural education in the Indian
Pass-Running Man ATCC prior to their loss of
this resource.
- 4.1.6-12: A non-technical report should be written based on the archaeological
and ethnographic studies written for the Quechan tribe, addressing the
part of Quechan history that would be destroyed by the mine.
- 4.1.6-13: Provide for the expansion plan for the Quechan Museum and
curation of artifacts from the Project in this facility.
The following measures are proposed to mitigate the cumulative adverse
effects that the disturbance created by the Project mine and process area
will have on traditional cultural sites in Quechan territory:
- 4.1.6-14: The Indian Pass-Running Man ATCC,
the Trail of Dreams, Pilot Knob, Muggins Peak, and the Picacho Basin should
be nominated to the NRHP as traditional cultural properties.
- 4.1.6-15: A recording and protection program for the concentration
of scratched petroglyphs at Indian Pass should be implemented.
- 4.1.6-16: Consultation should be initiated with the Quechan to identify
a site of traditional concern that could be acquired and protected.
In addition to the measures listed above to mitigate the adverse effects
on the Indian Pass-Running Man ATCC, the following
measures are proposed to mitigate the physical disturbance created by the
Project mine and process area to all or parts of seven (7) multicomponent
and twelve (12) trail sites, which will result in data loss and the
destruction of historic context:
- 4.1.6-17: An archaeological data recovery program (in accordance with
the recommendations provided in Chapter 9 of KEA's cultural resource
report) should be implemented at sites that cannot be avoided.
The measures listed above to mitigate the adverse effects on the Indian
Pass-Running Man ATCC within the Project mine
and process area will also mitigate the physical disturbance and out-of-character
visual and aural intrusions to the Indian Pass-Running Man ATCC
created by the construction of facilities within the Project ancillary area.
In addition, the following measures are proposed to mitigate the physical
disturbance to significant archaeological sites created by construction
within the Project ancillary area.
- 4.1.6-18: No ground disturbance should be allowed within features that
contribute to the significance of the Indian Pass-Running Man ATCC. In site CA-IMP-2727, the water pipeline should
be rerouted to the area already disturbed by Indian Pass Road. Alternatively,
boring could be utilized to avoid impacts to contributing features. All
NRHP-eligible archaeological sites outside of the Indian Pass-Running Man
ATCC should be avoided. Flagging and monitoring
should be done in accordance with mitigation measure 4.1.6-5.
The following measures are proposed to mitigate the disturbance which
could occur to features that contribute to the NRHP-eligibility of Camp
Pilot Knob.
- 4.1.6-19: Prior to construction, a professional historical archaeologist
should flag all features in the vicinity of existing poles that contribute
to the NRHP eligibility of Camp Pilot Knob. Periodic archaeological monitoring
should be conducted to ensure avoidance. In case of accidental damage,
BLM should consult with SHPO regarding an appropriate
mitigation program. Oral history and archival research should be considered
along with archaeological data recovery in case of such an eventuality.
- 4.1.6-20: If adverse effects cannot be avoided, an interpretive display
should be developed to supplement the E Clampus Vitus sign that
already exists on-site. This display should address the relationship of
Camp Pilot Knob to the overall Desert Training Center operations and include
historical photos of the camp during its period of significance.
The following measure is proposed to mitigate the disturbance which
could occur to significant archaeological sites during the construction
of the overbuilt 92 kV/34.5 kV transmission lines.
- 4.1.6-21: All NRHP-eligible sites should be flagged for avoidance of
direct impacts prior to construction of the transmission line. Avoidance
of flagged archaeological sites should be part of the overall environmental
monitoring program for the Project. In addition, periodic monitoring by
a professional archaeologist and Quechan representative should be conducted
to ensure avoidance. In case of accidental damage, BLM
should consult with SHPO regarding an appropriate mitigation program. Oral
history archival research, and ethnographic research should be considered
as appropriate along with archaeological data recovery in case of such
an eventuality.
4.1.6.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
The Indian Pass-Running Man ATCC, including
the Trail of Dreams; seven (7) multi-component archaeological sites;
and twelve (12) prehistoric trail sites in the Project mine and process
area, each of which have been evaluated as eligible for the NRHP under Criteria "A,"
"C" and/or "D, " would not be avoided under the Proposed
Action. If SHPO and the ACHP concur in the NRHP
evaluation, adverse affects to each of these cultural resources would occur,
and the impact of the Proposed Action would be considered significant and
unavoidable, even after implementation of the mitigation measures specified
in this EIS/EIR.
4.1.7. Visual Resources
4.1.7.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Have a substantial, demonstrable negative aesthetic effect.
- Substantially interfere with activities intolerant of bright lighting.
4.1.7.2. Impacts of the Proposed Action
In addition to other changes, this section has been substantially modified
from the November 1996 Draft EIR in response to comments to: better analyze
the visual impacts of the Proposed Action, including an additional KOP,
and analyze the Proposed Action in light of the revised regrading/reclamation
procedures.
Impacts to visual resources from the Proposed Action would result from:
lighting of mine and process areas so that mining can occur during nighttime
hours; visibility reduction resulting from the emission of particulate matter;
and visual contrasts created by changes in line and form from the creation
of new structures and facilities (such as the transmission line), altered
surface colors, textures and vegetation cover (through surface disturbance)
and changes in topography (waste rock stockpile, heap, and open pit landforms).
Lighting:
Project lighting used during nighttime operations at the administrative
offices, shop area, lime silo, heap leach processing facility; portable
light plants used at the active pits, waste rock stockpiles and heap leach;
and head lights from mobile vehicles would produce "sky glow"
and/or direct light which would be visible to some viewers, such as campers,
hikers, and other nighttime dispersed recreation users in the vicinity of
the Project mine and process area, including the adjacent wilderness areas,
but should not be visible to developed recreation areas, such as Glamis
or Gold Rock Ranch, because of distance and blocked line-of-sight. The Proposed
Action includes restricting exterior night lighting to the minimum necessary,
consistent with safety requirements and 24-hour-per-day operations. These
effects of night lighting would not be significant.
The USMC has established a flight corridor (VFR-299) which occupies air
space directly above the Project area. The Project area is currently used
by the USMC for military overflights and for nighttime military operations
using Night Vision Devices (NVDs). These devices can detect light at levels
much lower than those that are detectable by the unaided human eye and,
as such, Project lighting could pose a significant hazard to pilots during
use of the NVDs, especially if the lighting is directed upward or is unexpected.
Although the Proposed Action represents only a small portion of the available
flight corridor, there would also be a small potential for significant interference
with overflight operations from Project lighting during nighttime.
Visibility Reduction
The Proposed Action is a source of particulate matter (principally fugitive
dust generated by travel on unpaved roads, blasting of rock in the pit(s),
loading and unloading of ore and waste rock, combustion of diesel fuels
in large engines, and wind erosion of exposed surfaces) and oxides of nitrogen
(almost exclusively from the combustion of diesel fuels in large engines),
both of which can contribute to the reduction in overall visibility (visual
distance) in certain circumstances. In addition, particulate matter emitted
in some circumstances can result in a visible "plume." No quantitative
assessment of possible visibility (visual distance) reductions from the
Proposed Action have been undertaken. However, computer modeling of the
ambient concentrations of particulate matter and nitrogen oxides (see Section 4.1.4.2)
indicate that the Proposed Action would comply with the applicable ambient
air quality standards, and that ambient concentrations of these pollutants
would be very low only short distances from the Project mine and process
boundary. Experience at other mines in the region indicates that although
there would be some circumstances where "plumes" (from blasting,
or from diesel engine exhaust in certain circumstances) may be locally visible
for short periods of time, substantial visibility reduction is not occurring
as a result of project activities. The Proposed Action contains measures
(such as dust control on unpaved roads) which substantially reduce the emissions
of particulate matter and the resulting potential for visibility reduction.
These impacts are judged to be below the threshold of significance.
Visual Contrast
The heap, waste rock stockpiles, and open pits constructed as part of the
Proposed Action would represent a substantial visual contrast for viewers
of the Project during the life of Project activities. The South Waste Rock
Stockpile and the heap would both be constructed to a maximum height of
300 feet above existing grade, and would, therefore, be approximately
100 to 150 feet higher than any existing landform immediately adjacent
to the Project mine and process area. The East Pit would remain open under
the Proposed Action. The new transmission line and water wells in the Project
ancillary area would also present a visual contrast, although to a much
smaller degree. Following the completion of construction, the overbuilt
92 kV/34.5 kV transmission line would present little contrast
over the existing 34.5 kV transmission line.
Implementation of the Reclamation Plan would reduce some of the impacts
associated with the surface disturbance and new landforms associated with
the Proposed Action over the long term. Following completion of Project
operations, all structures constructed within the Project area as part of
the Proposed Action (buildings, water wells, haul and maintenance roads,
92 kV/13.2 kV transmission line and substation, etc.) would be
removed and the disturbed areas recontoured as necessary and seeded. The
waste rock stockpiles and the heap would be recontoured, seeded, and would
ultimately resemble smooth, rounded mounds. This would minimize the contrast
of color and lines that would result from the Proposed Action post-mining
but pre-final reclamation. However, the open pit, waste rock stockpiles
and heap would remain as a permanent, substantial change to the line and
form of the area.
The West Pit and Singer Pit would each be entirely backfilled under the
Proposed Action. Some subsequent backfill
may be necessary to raise the floor of the East Pit to a level higher than
the level of any pit lake which may be eventually predicted to form from
the inflow of ground water. All disturbed areas except the pit slopes would
be regraded and revegetated, when no longer required for mine operations.
This reclamation would create undulating land forms that are stable, do
not allow for any pooling or ponding of water, and blend in with the surrounding
undisturbed topography. Sharp edges would be rounded and straight lines
altered to provide contours which are visually and functionally compatible
with the surrounding terrain. The regrading would entail the construction
of small "catchment" basins to collect precipitation and, thus,
facilitate the revegetation of the disturbed areas. Other areas disturbed
by facilities and roads, and the areas adjacent to diversions, would be
fine graded to enhance moisture retention for reclamation and revegetation.
Revegetation activities in the disturbed areas immediately adjacent to the
diversion channels and washes would include redistribution of soil, direct
transplantation of trees and shrubs, seeding, monitoring and reporting.
In all other areas, revegetation would include salvaging and stockpiling
available soil, contouring and shaping accessible disturbed areas, reapplying
soil materials as necessary, preparing seedbeds, seeding and transplanting,
optimizing seed mixtures and rates, and monitoring and reporting.
Rough grading would be utilized to blend the top edges and crests of waste
rock stockpiles and the heap and to construct the permanent diversion channels.
Final grading would be utilized to construct small catchment basins for
the collection and concentration of precipitation for revegetation of the
waste rock stockpiles and leach pads. The waste rock stockpiles would have
surfaces of mixed rock substrates and coarse alluvium with little developed
soil or highly weathered material. The top surfaces of waste rock stockpiles
would be rounded and contoured to form undulating land forms to blend with
the surrounding terrain. Side slopes of waste rock stockpiles would be rough
graded and small catchment basins installed. The configured surfaces and
catchment basins would then be sown with seed or spread with stockpiled
soil. During final reclamation, the small catchment basins (in which the
plants can become established) would be constructed at varying intervals.
In addition, scattered vegetation would naturally become established within
a short time depending on local climatic conditions (rainfall events), softening
the visual contrast with surrounding areas.
Although the Project facilities would be clearly visible from Indian Pass
Road and other routes of travel in the immediate vicinity of the Project
mine and process area, Project facilities in the Project mine and process
area would not be easily viewable to most passersby from common viewing
points in the surrounding, more distant, areas. There would be a limited
view of the Project area from KOP #1, located on Ogilby Road (see Figure 4.2),
the major access road in the vicinity of the Project area. The Project area
would also be visible from KOP #2, located at the southern end of the
top of Black Mountain (see Figure 4.4); from KOP #3, located
on the top of a hill within the Picacho Peak Wilderness Area (see Figure 4.6);
from KOP #4, an informal overnight camping area located along Indian
Pass Road (see Figure 4.8). The Project area would also be visible
from other elevated areas in the adjacent mountains, although the potential
number of viewers from any of these locations would be very limited in number.
In accordance with BLM Visual Manual Section
8400, analyses of the visual effects of the Proposed Action following completion
of Project mining and reclamation activities have been conducted. Photosimulations
were prepared to simulate the post-mining, post-reclamation view from each
of the same four (4) KOPs. These photosimulations were prepared on
digitized versions of the views shown in Figure 4.2, Figure 4.4,
Figure 4.6, and Figure 4.8. To ensure proper location
and scaling of the landforms which make up the Proposed Action within the
Project mine and process area, USGS digital elevation maps (DEMs) were combined
into a single base map on which was electronically placed the Project mine
and process area boundary and the final contours for each of the major Project
landforms (waste rock stockpiles, heap, and open pit) (see Figure 2.4).
This information was used to create computer-generated, three-dimensional
views of the topography of the Project mine and process area following the
completion of final reclamation from each of the four (4) KOPs. The
computer-generated images were scaled and printed to match each of the views
shown in Figure 4.2, Figure 4.4, Figure 4.6,
and Figure 4.8, then used to check final form and placement
of the simulated views so that they were created as accurately as possible.
Using images of similar reclaimed areas in similar rock types from the Picacho
Mine and the Mesquite Mine to match colors and textures, photosimulations
were created for each KOP.
Figure 4.3 shows the view of the Project features after the
completion of reclamation from KOP #1, on Ogilby Road. From this viewpoint,
only the uppermost portions of the southern end of the South Waste Rock
Stockpile and the heap would be visible, at a distance of approximately
four (4) miles, over the slightly elevated terrain in the immediate
foreground. These Project landforms would be viewed against the darker forms
of Black Mountain and the Chocolate Mountains on the horizon.
The photosimulated view of the Project area after the completion of reclamation
from KOP #2, the top of Black Mountain, and from KOP #3, the top
of the hill immediately south of Indian Pass in the Picacho Peak Wilderness
Area, are presented in Figure 4.5 and Figure 4.7,
respectively. The view from these viewpoints looks down on the Project mine
and process area from distances of five (5) miles and two (2)
miles, respectively. From KOP #2, there is an unobstructed view of
the waste rock stockpiles and the top of the heap. From KOP #3, all
of the principal Project facilities are completely visible except the East
Pit, which is partially hidden by the East Waste Rock Stockpile.
The photosimulation of the view toward the Project mine and process area
after the completion of reclamation from KOP #4, the informal overnight
camping area adjacent to Indian Pass Road, is presented in Figure 4.9.
From this viewpoint, only the uppermost portions of the southern end of
the South Waste Rock Stockpile and the heap would be visible, at a distance
of approximately two (2) miles, over the slightly elevated terrain
in the immediate foreground. These Project landforms would be viewed against
the sky, with the darker forms of Black Mountain and Picacho Peak flanking
the view.
To simulate views of the Project area following the completion of mining
but prior to the completion of reclamation, additional photosimulations
were constructed from each of these same four (4) KOPs. Post-mining, pre-final
reclamation photosimulations of the view of the Project area are presented
in Figure 4.10 from KOP #1, from KOP #2 in Figure 4.11,
from KOP #3 in Figure 4.12, and from KOP #4 in Figure 4.13.
Each of these views differ from the post-final reclamation views principally
by the "stepped" slopes and flat tops of the waste rock stockpiles
and the heap, and the reduced level of revegetation. Consistent with BLM Visual Manual Section 8400, since these
photosimulations show the visual effects at an interim stage and not following
the completion of the Proposed Action, they have not be used in the analysis
of the long-term impacts of the Proposed Action.
The level of impact to visual resources would depend upon the number of
viewers of the project, the viewers= observation point, and the duration
of the disturbance from the Proposed Action. Visual effects of the Proposed
Action were analyzed using the standard procedures presented in Section 8400
of the BLM Manual. The potential number of daily
viewers from KOP #1 (Ogilby Road) may number up to 1,000 (see 3.15).
The potential number of viewers from KOP #2 would be small, averaging
only a few per day, while the number of viewers from KOP #3 is likely
to be very small, less than a few per month. The potential number of viewers
from KOP #4 would vary depending on the season; during the winter months
the number may reach several hundred per month, whereas in the summer months
the number may be only a few per week.
The line of the reclaimed Project features within the Project mine and process
area would approach undulating, but would remain somewhat discontinuous
and have some areas with an angular line. The color of the reclaimed Project
features would approach tan to brown, and would generally be lighter than
much of the surrounding surface rock, which is coated with a desert varnish.
The form would be rounded and rhomboid in the near ground and conical in
the middle ground. The texture would approach a middle patchy. The Proposed
Action would result in the permanent placement of certain line and form
features in an area of the landscape that did not otherwise have those line
and form features, and the overall color, line, form, and texture of the
post-reclamation Project mine and process area features would not be reasonably
consistent with the surrounding area. Accordingly, the post-reclamation
visual impacts of the Proposed Action are determined to be above the level
of significance.
Conformance with Class II Visual Objectives
Landforms constructed under the Proposed Action would contrast visually
with the surrounding land even after completion of final reclamation. The
Project area is located in an area of the California
Desert Conservation Area (CDCA) designated Class L (Limited Use).
Class L areas are generally managed to conform to the BLM
Class II visual objectives (see Section 3.7.1). Based upon
the visual effects of the Proposed Action described above and the BLM Class II visual objectives (i.e., to retain
the existing character of the landscape) which have generally been applied
to this area, the Proposed Action does not conform to the visual objectives.
This lack of conformance is a significant impact.
4.1.7.3. Measures Incorporated by Project Design
and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.7-1: Following completion of Project mining activities, all buildings,
equipment, supplies, and debris shall be removed to improve the visual
appearance of the Project area.
- 4.1.7-2: Dust suppressants shall be utilized, as necessary and in accordance
with ICAPCD permit requirements, on haul roads to minimize fugitive airborne
dust generation on the Project mine and process area.
- 4.1.7-3: In conformance with the Reclamation Plan as approved by the
BLM and Imperial County, all disturbed areas
shall be recontoured and reseeded or revegetated with native or indigenous
species complementary to vegetation found in the surrounding area.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
No specific measures.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
- 4.1.7-4: High intensity lighting used for mining and processing operations
at night shall be directed downward to reduce fugitive light. Lighting
shall have reflectors or shields to further minimize fugitive light. Light
stanchions shall be no higher than necessary for safe and efficient lighting.
- 4.1.7-5: Applicant shall establish a working relationship with the
U.S. Marine Corps (USMC) to ensure that nighttime lighting of the Project
mine and process area does not substantially interfere with the use of
Night Vision Devices (NVD) in the vicinity of the Project area or nighttime
overflight operations within flight corridor VFR-299. As part of this mitigation
measure, Applicant shall provide the USMC Air Station, Yuma, Arizona, with
a detailed, to-scale, map of the Project area identifying the principal
surface facilities, transmission lines, and locations of potential light
sources to enable the USMC to avoid or accommodate these areas during nighttime
flight activities.
4.1.7.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
The Proposed Action would result in unavoidable physical changes in the
existing contour and character of the Project area. These changes would
be visibly most apparent over the active life of the Project, but would
diminish through the completion of reclamation and revegetation activities
contained as part of the Proposed Action. These physical changes to the
area would be permanent, but would continue to lessen following the completion
of final reclamation as natural processes continued to soften the line and
form to and match the surrounding landscape. These residual impacts to the
visual character of the Project area are judged to be significant and unmitigatable.
The Proposed Action would result in a visual contrast with the surrounding
area and would change the existing character of the landscape to a degree
which would not conform with the BLM Class II
visual objectives which have been applied to this Class L-designated
area. This lack of conformance is a significant, unmitigatable impact.
4.1.8. Noise
4.1.8.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Would have the potential to result in a significant increase in noise
levels to sensitive receptors in the area; or
- Conflict with any applicable noise restrictions imposed by regulatory
agencies.
4.1.8.2. Impacts of the Proposed Action
The Proposed Action would not conflict with any applicable noise restrictions
imposed by regulatory agencies.
The noise generated by the proposed mining operations would be typical of
most construction and mining projects, and could be intense for short intervals.
Ore loading and handling, and other mining processes, can generate noise
levels up to 95 dB(A) at 25 feet, although typical average noise
levels generated by Project operations (which continue 24 hours per
day, seven (7) days per week) could be substantially lower. Safety
backup alarms on haul truck and other major equipment may generate 100 dBA
at 25 feet, and blasting (which the Proposed Action restricts to daylight
hours) can cause very short-duration noise levels in excess of 140 dBA
at 25 feet.
Noise is attenuated by distance, atmospheric conditions, and topography.
Sound wave divergence typically results in a six (6) dBA decrease for
every doubling of distance from a noise source (ICPBD 1978). This assumption
is conservative since it does not account for noise attenuating factors
such as topography, wind, temperature gradients, atmospheric pressure, and
other site-specific factors, such as the upward deflection of noise generated
down in the bottom of a pit. Assuming a typical peak noise levels from the
day-to-day Project activities within the Project mine and process area of
95 dBA, and assuming a typical noise source location near a point of
public access (the center of the South Waste Rock Stockpile, approximately
1,600 feet from Indian Pass Road), then the peak ambient background
noise at the nearest point of public access would be approximately 60 dBA.
Peak ambient background noise levels (50 dBA to 30 dBA) would
be expected to be approached at a distance of approximately one-half (2)
to five (5) miles, respectively, from the Project mine and process
area from these activities. Typical average noise levels generated by Project
operations would be expected to be substantially lower. Substantially higher
level noise values would be expected during the instant when blasting occurs.
There are no permanent noise-sensitive receptors (i.e., residences, schools,
hospitals, etc.) located in the vicinity of the Project area. The nearest
permanent noise-sensitive receptors are located at the Gold Rock Ranch,
approximately seven (7) miles southwest of the Project mine and process
area. Based upon the projected attenuation of noise with distance, sound
pressure levels generated from all normal operating activities at the Project
mine and process area should not be audible at this receptor. However, the
short term, higher level, noise values generated by blasting may be audible
and distinguished from natural noise sources, but would be similar to those
generated from the existing military overflights. While some Project-generated
noise levels may be discernable, the projected noise levels would not be
intrusional and noise impacts would be below levels of significance.
Temporary or transient noise receptors, such as dispersed recreational uses
in the area around the Project mine and process area, including portions
of the Indian Pass Wilderness Area and the Picacho Peak Wilderness Area,
would be exposed to audible noises generating by Project activities, depending
on their distance from the Project mine and process area, their location,
local conditions, and the specific activities being undertaken by the Project.
While some Project-generated noise levels may be barely discernable, other
noises and noise levels would likely be judged intrusional, and some of
these receptors may decide to avoid the areas surrounding the Project mine
and process area, and instead use other recreational areas, during the life
of the Project, especially during weekends of heavy recreational use. The
effects of Project noise alone on dispersed recreational users are judged
significant because of blasting on weekends of heavy recreational use; however,
see Section 4.1.9.2 for the assessment of all Project effects
on recreational use.
The effects of project generated noise on wildlife is discussed in further
detail in Section 4.1.5.3.
4.1.8.3. Measures Incorporated by Project Design
and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.8-1: All heavy equipment, drilling rigs, and other internal combustion
engines shall be equipped with mufflers to minimize noise generated during
construction, operation and reclamation activities.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.8-2: Applicable Occupational Safety and Health Administration (OSHA)
worker noise protection requirements, as set forth in 29 CFR 1910.95,
et seq, and California Occupational Safety and Health Administration
(Cal-OSHA ) requirements, as set forth
in 8 CCR 5095, et seq, shall be implemented by the Applicant.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
- 4.1.8-3: Blasting shall only be conducted during daylight hours unless
required for safety reasons. During the months of October through March,
the Applicant shall take all reasonable steps to avoid blasting on weekend
days (Saturday and Sunday), and shall not blast on the following major
recreational holidays (Thanksgiving [Thursday through Sunday]; Christmas
[Christmas day and all associated weekend days]; New Years [New Years eve,
New Years day, and all associated weekend days]; and President's Day [and
associated weekend days]) unless required for safety reasons or necessary
to maintain production due to the mechanical breakdown of production equipment
or other unforseen circumstances. Prior to conducting blasting on any of
these designated weekend days or major holidays, Applicant shall on that
day notify the BLM and take reasonable steps
to notify those recreational users of the public lands located along Indian
Pass Road or within one (1) mile of the boundary of the Project mine
and process area boundary of the approximate time that blasting will occur.
4.1.8.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
The Proposed Action would result in unavoidable increases in ambient
noise levels within a conservatively estimated five-mile radius of the Project
mine and process area over the life of the Project. Noise levels would diminish
with distance from Project noise sources, and ambient noise would decrease
with time as the pit walls, heap, and waste rock stockpiles provide increasing
topographic attenuation of sound levels from noise sources within the Project
mine and process area.
Based on the absence of sensitive noise receptors in the vicinity of the
Project area, the effects of noise from the Proposed Action would be below
the level of significance.
4.1.9. Land Use
4.1.9.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
This land use impact assessment evaluates the potential effects of the Proposed
Action on existing and planned land uses in the vicinity of the Project
area. It also evaluates the effects of the Proposed Action on wilderness
and recreational resources in the Project area and vicinity. The Proposed
Action would normally have a significant effect on the environment if it
would:
- Conflict with adopted environmental plans and goals of the community
where it is located;
- Disrupt or divide the physical arrangement of an established community;
- Conflict with established recreational, educational, religious or scientific
uses of the area;
- Result in nonconformance with the Wilderness Act of 1964 or the BLM Interim Wilderness Management Policy;
- Substantially degrade or reduce the quantity or quality of the area
available for existing or future recreational opportunities; or
- Result in the unmitigated loss of a unique recreational resource.
The effects of the Proposed Action would also be significant if the Project
was incompatible with existing land uses in the vicinity, or if the effects
of the Proposed Action would not be in conformance with the applicable land
use plans and policies described in Section 3.9.1.
4.1.9.2. Impacts of the Proposed Action
In addition to other changes, this section has been modified from the
November 1996 Draft EIR in response to comments to: provide additional information
regarding the impacts of the Proposed Action on recreational uses in the
area, including recreational use of the wilderness areas.
Compatibility with Existing Land Uses:
The Project area is undeveloped and the area surrounding the Project area
is occupied by large expanses of public land administered by the BLM. The area is relatively isolated and remote from
concentrated land uses. The area is generally regarded as open space, providing
desert habitat for wildlife and dispersed recreational opportunities. The
principal land uses in the vicinity of the Project area include: dispersed
recreation (hunting, camping, rock collecting, etc.); military aircraft
overflight training; and commercial mineral exploration. Two (2) wilderness
areas (Indian Pass Wilderness Area and Picacho Peak Wilderness Area) are
located approximately one and one-half (12) miles north and one-half
(2) mile northeast, respectively, of the Project mine and process area at
their closest points; compatibility of these wilderness areas with the Proposed
Action is discussed in the subsection entitled "Wilderness Areas,"
below. Indian Pass ACEC is located approximately
three-quarters (3/4) of a mile north of the Project mine and process
area; compatibility of the cultural resource values for which the Indian
Pass ACEC was established is discussed in Section
4.1.6.2. The impact of the Proposed Action on dispersed recreation within
the area is discussed in the subsection titled "Recreational Resources,"
below. There are no current plans to include the Project area in any park
system.
Three (3) precious metal mines (American Girl/Oro Cruz Mine, Mesquite
Mine, and Picacho Mine) are located within ten (10) miles the Project
mine and process area; the Proposed Action would have no impact on these
existing mines. The nearest residence and area of concentrated public activity
is the Gold Rock Ranch, located approximately seven (7) miles southwest
of the Project mine and process area. The Proposed Action is compatible
with this existing use, since the Project would result in negligible increases
in noise and traffic along Ogilby Road, and would result in negligible decreases
in air quality, for the residents and visitors at Gold Rock Ranch. No other
residences exist within ten (10) miles of the Project mine and process
area.
The new transmission lines could pose a potential physical hazard to low-flying
military aircraft, especially during nighttime exercises when pilots are
training with night vision devices (NVD) which substantially amplify the
available light; the Proposed Action includes the installation of special
devices which are visible only at night with the use of NVD (see Section 2.1.9.3.1).
Project night lighting could present a similar hazard to the use of NVD;
a mitigation measure to reduce the impact of this lighting to below the
level of significance is provided in Section 4.1.7.3. However,
Project blasting during mining operations could be a significant potential
hazard to low-flying military aircraft using the general area for training
exercises.
Expanded discussions of the potential effects of the Project on surrounding
area are provided in the other sections of this Chapter 4 of
the EIS/EIR.
Compatibility with Adopted Land Use Plans and Policies:
In passing the Federal Land Policy and Management Act of 1976 (FLPMA), "...
Congress declared that the policy of the United States would be to manage
public lands to protect the quality of various natural resources, outdoor
recreation and human occupancy and uses." (Section 102(a)(8))
The policy statement went on to include "... (12) the public lands
[shall] be managed in a manner which recognizes the Nation's need for domestic
sources of minerals, food, timber, and fiber from the public lands including
implementation of the Mining and Mineral Policy Act of 1970 ... as it pertains
to the public lands; ...." [Section 102(a)(12)].
FLPMA defines multiple use as "... management of the public lands and
their various resource values so that they are utilized in the combination
that would best meet the present and future needs of the American people;
making the most judicious use of the land for some or all of these resources
or related services over areas large enough to provide sufficient latitude
for periodic adjustments in use to conform to changing needs and condition;
...." The definition goes on to allow some areas to be managed for
less than all the resources. "... a combination or balanced and diverse
resource uses that takes into account the long-term needs of future generations
for renewable and nonrenewable resources, including, but not limited to,
recreation, range, timber, minerals, watershed, wildlife and fish, and natural
scenic, scientific and historical values ..." is also a part of a multiple
use. [Section 103 ©].
Primary or major uses are defined as those which A... includes and is limited
to domestic livestock grazing, fish and wildlife development and utilization,
mineral exploration and production, rights-of-way, outdoor recreation, and
timber production. [FLPMA Section 103(1)].
The California Desert
Conservation Area (CDCA) Plan is a multiple use, sustained yield plan
developed to manage various resources including mineral development [FLPMA
Section 601(d)]. The Proposed Action is consistent with the CDCA Plan.
Therefore, it is consistent with Section 601(a)(4) and Section 601(b)
of FLPMA. In addition, Section 601(f) of FLPMA did not amend the 1872
Mining Law to preclude mineral development or production within the CDCA.
The development of locatable minerals on mining claims in areas designated
by the BLM as Class L is authorized subject
to applicable federal regulations (43 CFR 3809) and state and
local laws.
The overbuilding of the existing 34.5 kV transmission line is in conformance
with the respective goals and objectives set forth in both the Land Use
Element and the Conservation and Open Space Element to the General Plan.
The County has also zoned the entire area
of the Proposed Action as S-Open Space, which permits multiple uses
consistent with the Conservation and Open Space Element and the General
Plan.
The proposed Project is in conformance with the Southern California Association
of Governments (SCAG) Regional Comprehensive Plan and Guide (RCPG) (SCAG
1997).
Wilderness Areas:
The northern boundary of the Project mine and process area is located approximately
one-half (2) mile southwest of Picacho Peak Wilderness Area, and approximately
one and one-half (12) miles south of Indian Pass Wilderness Area. The
Proposed Action would not result in any surface disturbance within, or other
direct impacts to, either wilderness area. However, major facilities within
the Project mine and process area would be visible from some elevated areas
within both Indian Pass Wilderness Area and Picacho Peak Wilderness Area
(see Section 4.1.7). Minor increases in annual ambient levels
of particulate matter would result in the wilderness areas from Project
emissions (see Section 4.1.4). Blasting and other noises generated
by Project operations within the Project mine and process area would be
audible within those portions of the wilderness areas nearest the Project
mine and process area (see Section 4.1.8.2). Indian Pass Road,
the primary access to these wilderness areas from the west, would be realigned
around the Project mine and process area over the life of the Project, and
would be returned to approximately its original location after the completion
of mining activities. However, the road would be kept open and would not
restrict travel to the wilderness areas.
Section 103(d) of the California
Desert Protection Act of 1994, which created both Indian Pass Wilderness
Area and Picacho Peak Wilderness Area, reads:
"No Buffer Zones.--The Congress does not intend for the designation
of wilderness areas in section 102 of this title to lead to the creation
of the protective perimeters or buffer zones around any such wilderness
area. The fact that nonwilderness activities or uses can be seen or heard
from areas within a wilderness area shall not, of itself, preclude such
activities or uses up to the boundary of the wilderness area."
Accordingly, only the direct effects of the Proposed Action on these
wilderness areas can be assessed for their effects on wilderness values
themselves; the indirect effects of the Proposed Action on these wilderness
areas must be evaluated without reference to the areas= wilderness characteristics
and values. Based upon the lack of direct impacts to these wilderness areas
from the Proposed Action, the impacts to wilderness areas from the Proposed
Action are below the level of significance.
Recreational Resources:
The entire Project mine and process area (approximately 1,571 acres)
would be fenced and closed to the public during the entire operating life
of the Project, which would eliminate these lands from any recreational
use during this period. Following the completion of mining operations, surface
facilities (buildings, roads, process facilities and ponds, etc.) and foundations
would be removed, and final reclamation activities (grading and rounding
of waste rock stockpiles and the heap, revegetation, installation of guzzlers,
etc.) commenced. With the completion of final reclamation, the perimeter
fence would be removed and public access to the area reestablished, except
for the 198-acre area of the open East Pit, which would be surrounded by
a rock boulder barrier to prevent vehicle access and discourage pedestrian
access. As discussed in Section 4.1.5, both vegetation and wildlife
habitat values would slowly recover, and opportunities for hunting, hiking,
camping and other dispersed recreational activities would again be available
in the Project mine and process area (with the exception of the 198-acre
open East Pit).
Construction and operation of Project facilities within the Project mine
and process area would not prevent camping, hunting or other dispersed recreation
activities in areas outside of the fenced boundary of the Project mine and
process area. Most recreational activities in the immediate vicinity of
the fenced Project mine and process area would, however, be affected by
Project activities conducted during the projected 20-year life of the Project
within the Project mine and process area. Dispersed recreation would be
affected by emissions of air pollutants (see Section 4.1.4),
visibility of the mine components (see Section 4.1.7), noise
generated by mine operations (see Section 4.1.8.2), and Project-related
traffic on Indian Pass Road (and possibly Ogilby Road) (see Section 4.1.11.1.2),
even though mitigation measures to reduce the effects of these air emissions,
visibility, noise, and traffic impacts are presented in the respective sections
of the EIS/EIR. As a result of these effects of the project, dispersed recreational
use of the areas adjacent to the Project mine and process area would likely
be reduced during the life of the Project. Environmental education activities
currently conducted in the vicinity of the Project mine and process area,
specifically the viewing of cultural resources, would likely also be substantially
reduced or displaced by the Project during the life of the project and after
because some of the cultural resources would be inaccessible, while others
would be permanently lost.
Recreational users of those portions of Picacho Peak Wilderness Area and
Indian Pass Wilderness Area closest to the Project mine and process area
would almost certainly hear noises generated by the Project and see the
major features of the Project during the day (and lights from the Project
mine and process area during the night). Although the noise and lights would
last only through the estimated 20-year life of the Project, the daytime
views of the (reclaimed) Project features (waste rock stockpiles, heap,
and open pit) would be permanent. People who go into wilderness areas such
as these usually go there because of the solitude and the lack of human-related
distractions. Noise and lights, especially at night, from the Project mine
and process area would likely reduce the use of these wilderness areas by
people seeking this solitude. Other recreational users of the area may not
be as adversely affected by the Project noise and lights as the wilderness
users.
Project facilities constructed outside of the Project mine and process area,
including the buried water pipeline, water wells, and the new transmission
line, would not affect public access to the primitive campsites along the
washes adjacent to Indian Pass Road in the Indian Pass recreational corridor,
and Project operations would not encourage or overly restrict recreational
traffic traveling on Indian Pass Road to or from the wilderness areas or
other potential recreation areas located north of the Project mine and process
area. However, vehicle campers along the Indian Pass recreation corridor
adjacent to Indian Pass Road and the Project ancillary area would be most
affected by Project-related noise, lights, and Project-related vehicle traffic
along Indian Pass Road, as well as the loss of access to the microphyll
woodland habitat located within the Project mine and process area. As a
result, informal overnight camping in the Indian Pass recreation corridor
would probably diminish during the projected 20-year life of the Project,
especially for those people with two-wheel drive vehicles that cannot travel
far from Indian Pass Road. Campers would also likely be displaced and disturbed
by the noise and activities created during pre-mining construction activities
associated with the new transmission line and ground water system. Following
the completion of reclamation activities within the Project mine and process
area, the new transmission line would be removed, the water wells would
be abandoned in conformance with agency requirements, and the buried water
pipeline would be abandoned in place. As a result, little residual effect
on vehicle camping within the Indian Pass recreational corridor would be
likely beyond the life of the Project.
There are no unique recreational resources within the Project area, and
comparable recreational opportunities would still be available in large
areas of public land similar to, but outside of, the Project area. There
are no current plans for the Project area to be incorporated into either
the state or federal park system. There are approximately 4.4 million
acres of BLM Class L lands in the CDCA which
are generally available for dispersed recreation. Given the availability,
both nearby and in other areas of eastern Imperial County, of large areas
with similar, although not identical, opportunities for dispersed recreation,
the effects of the Project on recreation resources would be below the level
of significance.
While not intended, the proximity of the Project mine and process area to
Indian Pass Road could attract some visitors to the area as sightseers to
observe the large mine equipment and active mining operations.
4.1.9.3. Measures Incorporated by Project Design
and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.9-1: At the conclusion of mining activities, consistent with the
approved Reclamation Plan, Applicant shall recontour all disturbed areas
except the pit slopes as appropriate to create undulating land forms that
are stable, safe, do not allow for any pooling or ponding, and blend with
the surrounding undisturbed topography. Applicant shall also construct
a loose rock barricade comprised of large boulders to prevent vehicle access
and restrict public entry into the open pit area(s).
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.9-2: Applicant shall conduct mining operations in conformance with
the Class L BLM multiple land use guidelines
outlined in the CDCA Plan for mining in the area. The Applicant shall also
comply with the federal land use requirements prescribed in 43 CFR 3809.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
- 4.1.9-3: Applicant shall keep the USMC air station in Yuma, Arizona
apprized of the current schedule and location for blasting at Project mine
and process area to minimize the potential for low-flying military aircraft
to be over the Project mine and process area during blasting activities.
4.1.9.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
The Proposed Action would result in an unavoidable change to the existing
land use in the Project mine and process area from open space to mining
over the 20-year life of the Project. Following completion of mining and
reclamation activities, the majority of the Project mine and process area
would be available again as open space. However, public access to the 198-acre
open East Pit area would be indefinitely restricted by a loose rock-rubble
barricade.
The Proposed Action would reduce the area otherwise available for use by
low-flying military aircraft, especially during nighttime exercises when
pilots are training with night vision devices (NVD), during the life of
the Project; mitigation measures are available to reduce this impact to
a level which is less than significant, and this effect would be eliminated
following the completion of final reclamation.
Areas in the immediate vicinity of the Project mine and process area, including
some portions of the nearby wilderness areas, would be unavoidably affected
by emissions of air pollutants and noise from the Proposed Action, and portions
of the Proposed Action would be easily visible from immediately adjacent
or elevated locations. Project-related traffic would also unavoidably affect
users of the land in the immediate vicinity of the Project area. These effects
would be less than significant on the nearby wilderness areas, and would
also be less than significant on the dispersed recreational resources.
4.1.10. Socioeconomics
4.1.10.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Induce substantial growth or concentration of population;
- Displace a large number of people;
- Cause a substantial reduction in employment;
- Substantially reduce wage and salary earnings; or
- Cause a substantial net increase in County expenditures.
4.1.10.2. Impacts of the Proposed Action
A net beneficial socioeconomic effect is projected from the construction
and operation of the Proposed Action.
The Proposed Action is expected to create jobs for 120 full-time employees,
as many as 40 of which could be filled by the current employees of the Picacho
Mine, which would be closing. Initial construction may require as many as
225 workers, although only a portion of these would be working on the
Project at any single time. During the Project life, additional construction
projects (such as the construction of an additional phase of the heap leach
pad) may require up to 40 workers. Construction of the overbuilt 92 kV/34.5 kV
transmission line would require up to 30 workers.
Indirect employment opportunities generated by the Proposed Action were
estimated by applying multipliers commonly used in the mining industry.
Dobra (1988) assumes that for every job created in the mining industry,
an additional 1.25 job opportunities are created in other sectors of
the economy. Using this factor, the Project is estimated to create, or continue
in existence, 150 jobs. The majority of these jobs would be expected to
be filled by current residents of Imperial County, California or Yuma County,
Arizona, although there may be a very small increase in demand for housing
and community services in these areas over the life of the Project if some
of the jobs are filled by workers from outside these areas. Based exclusively
on the distance required to drive from the Project mine and process area
to Yuma (35 miles) versus Holtville (52 miles), Brawley (56 miles),
and El Centro (65 miles), it is likely that more workers would
eventually reside in Yuma, Arizona over locations in the Imperial County.
The following estimates of Project expenditures and estimated tax revenues
from the Project were provided by Glamis Imperial (Personal Communication,
C.K. McArthur, Chemgold, Inc., 1995; Personal Communication, Steve
Baumann, Glamis Imperial, 1996).
- Project annual payroll, including benefits, is estimated to be approximately
$7 million for 120 employees.
- Approximately $48 million in capital would be expended for the Project
during 1998. Sales tax on these capital expenditures would amount to approximately
$3.72 million. For each year thereafter, average annual capital expenditures
would amount to approximately $1.7 million, generating approximately
$0.13 million per year in sales tax for capital expenditures only.
- Annual non-capital expenditures are estimated to total $26 million
(including payroll).
- Geographic distribution of annual non-capital expenditures have been
estimated using data derived from the Picacho Mine operations. It is estimated
that 37.1 percent ($9.65 million) of non-capital expenditures would
be made in California and 38.1 percent ($9.9 million) would be made
in Arizona, for an estimated total of 75.2 percent ($19.55 million)
in local non-capital expenditures. The remaining 24.8 percent ($6.45
million) of non-capital expenditures would be made in areas outside of
California and Arizona.
- Property taxes in Imperial County are assessed at approximately 1.1 percent
per year of the total assessed value. Depending on the assessed valuation
of the Project property, projected property taxes are estimated to range
between $250,000 and $600,000 per year.
Based upon the information provided above, the Proposed Action would
not induce substantial growth or concentration of population; displace a
large number of people; cause a substantial reduction in employment; or
substantially reduce wage and salary earnings, and thus the Proposed Action
would not result in a significant adverse socioeconomic effect. Based on
the analyses presented in Section 4.1.11.1.2 and Section 4.1.11.3.2,
the Proposed Action would also not cause a substantial net increase in County
expenditures, and would not be considered significant.
4.1.10.3. Measures Incorporated by Project
Design and Regulation and Mitigation Measures
No mitigation measures are proposed or recommended.
4.1.10.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
There would be no unavoidable adverse socioeconomic effects from the
Proposed Action. Beneficial socioeconomic effects would result from the
Proposed Action in the form of employment opportunities, tax revenues and
increased spending in the local region for goods and services by Project
employees and contractors. The adverse socioeconomic effects of the Proposed
Action would be below the level of significance.
4.1.11. Roads and Public Services
4.1.11.1. Road and Transportation System
4.1.11.1.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Cause an increase in traffic which is substantial in relation to the
existing traffic load and capacity of the street system; or
- Prevent or substantially reduce public access through the elimination
of important existing routes of travel.
4.1.11.1.2. Impacts of the Proposed Action
The Proposed Action would require the realignment of an approximate 6,000-foot
section of Indian Pass Road around the western perimeter of the Project
mine and process area to allow for excavation of the West Pit in the current
road location. The relocated road would cross the adjacent "West Pit
West" wash "at-grade" at two (2) locations; one (1)
upstream and one (1) downstream of the Project mine and process area;
to allow for the safe passage of traffic during mine operations.
The Proposed Action includes maintaining Indian Pass Road open to the public
during construction of the relocated portion of the road; posting signs
at the two (2) wash crossings along the relocated portion of Indian
Pass Road warning drivers not to cross the wash when flooded; and undertaking
emergency repairs or maintenance if Indian Pass Road is damaged by flooding
where it crosses these washes.
Because "West Pit West" wash is subject to infrequent flooding,
Indian Pass Road would be subject to temporary closure during the period
that Indian Pass Road is realigned and this wash is flowing. An alignment
of Indian Pass Road which does not cross the wash (that is, which is entirely
on the east side of the wash) is the best location to minimize long-term
maintenance costs and environmental effects. Accordingly, at the request
of the ICPWD, the Proposed Action includes returning the realigned section
of Indian Pass Road to a location within the Project mine and process area
east of and approximately parallel to the diverted "West Pit West"
diversion channel. This location would be on land previously disturbed by
Project activities adjacent to the "West Pit West" diversion channel.
Once Indian Pass Road had been realigned and the reclamation bond for this
work released by the agencies, maintenance on Indian Pass Road reverts to
Imperial County. The impacts to Indian Pass Road, and to the public's use
of Indian Pass Road, from the road realignment and subsequent relocation
would be below the level of significance.
The Proposed Action would also result in the realignment of the intersection
of Indian Pass Road and Ogilby Road to change the acute angle of the intersection
to a right angle. The section of Indian Pass Road which would be replaced
would be reclaimed under the Proposed Action. The net effect to the road
system of realigning the road intersection would be beneficial, and any
adverse environmental effects resulting from realigning the intersection
would be below the level of significance.
Fencing of the Project mine and process area boundary, and construction
of the Project facilities within the Project mine and process area, would
necessitate the closure of several unmaintained dirt "routes"
identified on BLM Desert Access Guide 21
(Midway Well) which pass through the Project mine and process area (see
Figure 2.8), at least until the Project perimeter fence is removed
following the completion of final reclamation. However, as also shown on
Figure 2.8, alternative open routes are available in the immediate
vicinity of the Project mine and process area which would allow vehicles
to travel from Indian Pass Road to Hyduke Road, and to drive around the
Project mine and process area. Therefore, the closures of these routes,
either temporarily or permanently, would not result in a significant effect.
The Proposed Action would result in an estimated 47 light-weight vehicle
round-trips to the Project area daily, and an estimated average three and
one-half (32) heavy-weight vehicle round-trips per day. This represents
approximately a five (5) percent increase in the volume of traffic
currently observed on Ogilby Road south of its crossing of the Southern
Pacific railroad tracks and north of the exit off Interstate Highway 8.
This estimate assumes that approximately 25 percent of the estimated
64 workers which would be scheduled to work on any given day voluntarily
carpool to the Project area, which is consistent with the experience with
other mines in the area. Traffic volume could be higher if fewer workers
carpoolled, and would somewhat higher during the approximately six (6)
month construction period as a result of the additional workers and truck
traffic. Truck traffic on Ogilby Road associated with the Project would
not substantially increase degradation of the roadbed, nor result in a substantial
increase in maintenance costs for this road.
Although no traffic counts are available for either Ogilby Road in the vicinity
of the Project, or for Indian Pass Road, traffic volume is believed very
light on both roads. Project employees would work staggered shifts and different
work periods. This would result in dispersed traffic flow to and from the
Project area throughout the day. The Proposed Action also contains the realignment
of the intersection of Ogilby Road and Indian Pass Road to a right angle.
Thus, there is no reason to believe that the construction of either a right-
or left-hand turn pocket on Ogilby Road is necessary. The effects of traffic
associated with the Proposed Action would be below the level of significance.
Neither BLM Hyduke Road nor the open routes of
travel were constructed for heavy vehicle use, and moderate to extensive
upgrade of these roads would be required to permit heavy vehicle traffic.
The Proposed Action states that none of these roads in the vicinity of the
Project mine and process area would be used for heavy truck or equipment
traffic.
Fencing of the Project mine and process area (and construction of the Project
facilities) would close several BLM open routes
of travel currently located within the Project mine and process area. In
addition, the BLM would close those sections
of these same BLM open routes of travel located
outside the Project mine and process area which would be then end at the
Project mine and process area fence. However, public vehicular access to
all areas around the Project mine and process area is still available to
the public on all sides of the Project mine and process area from BLM routes of travel, Indian Pass Road, and Hyduke Road,
which would remain open (see Figure 2.8). During the life of
the Project, Glamis Imperial would be responsible, under the direction of
Imperial County, for the maintenance of Indian Pass Road from Ogilby Road
to a point beyond the Project mine and process area. Any costs associated
with possible increase in road repairs required as a result of increased
Project-related traffic on County-maintained paved roads would be off-set
by the additional property taxes and sales taxes provided to the County
by the Project. Thus, the level of impacts to roads, and the impacts to
public access in the vicinity of the Project, would be below the level of
significance.
Construction of the water wells, water pipeline, and new transmission line
in the Project ancillary area would require the construction of some new
access roads and "spur" roads. Following the completion of final
Project reclamation, Project facilities constructed within the Project ancillary
area would be removed (or, in the case of the buried pipeline, buried in
place), and these access and "spur" roads reclaimed. In addition,
the haul and maintenance roads within the Project mine and process area
to the open pit would be reclaimed. However, the contrast between the reclaimed
roadbeds and the surrounding areas may encourage public use of these closed
roads in areas where darkly "varnished" desert pavement was disturbed.
This is considered to be an insignificant effect, although a measure is
proposed to mitigate the impact further.
4.1.11.1.3. Measures Incorporated by Project
Design and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.11.1-1: Applicant shall realign an approximate 6,000-foot section
of Indian Pass Road around the Project mine and process area prior to surface
disturbance which would impede through traffic on this road, and shall
maintain Indian Pass Road open to the public during construction of the
relocated portion.
- 4.1.11.1-2: Applicant shall not route heavy traffic over Hyduke Road.
- 4.1.11.1-3: That section of Indian Pass Road realigned prior to mine
construction shall be realigned to a location east of and approximately
parallel to the diverted West Pit West diversion channel as soon as practicable,
but prior to the completion of final reclamation and release of the physical
reclamation bond.
- 4.1.11.1-4: Applicant shall post warning signs at the two (2)
wash crossings along the relocated portion of Indian Pass Road warning
drivers not to cross the wash when flooded, and shall undertake repairs
or maintenance, as may be necessary and authorized by Imperial County,
if Indian Pass Road is damaged by flooding where it crosses these washes.
- 4.1.11.1-5: Applicant shall apply water and/or dust suppressants (chemical
treatments acceptable to all appropriate agencies) to Indian Pass Road
from its intersection with Ogilby Road to the boundary of the Project mine
and process area.
- 4.1.11.1-6: Applicant shall acquire the necessary approvals of the
BLM and Imperial County to construct the relocated
section of Indian Pass Road and the realigned intersection of Indian Pass
Road and Ogilby Road, and shall design, construct and maintain these facilities
in accordance with the permit conditions which are applicable at the time
of construction.
- 4.1.11.1-7: Applicant shall encourage employees and construction workers
to carpool to the Project area.
- 4.1.11.1-8: Applicant shall maintain Indian Pass Road from the intersection
with Ogilby Road to the point immediately northeast of the Project mine
and process area, including the section of the road relocated by the Project,
during the active life of the Project in consultation with the Imperial
County Public Works Department.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
No specific measures.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
No mitigation measures are proposed.
Other Mitigation Measures (These are measures which may further reduce
the impacts of certain effects which are below the level of significance
without mitigation):
- 4.1.11.1-9: To reduce the potential that access and "spur"
roads constructed to provide temporary access to the new transmission line,
water pipeline, and water wells may continue to be used by the public following
the completion of Project reclamation, these roads, when constructed in
areas of dark "desert varnished" desert pavement, shall be reclaimed
in a manner, such as the application of Permeon, to reduce the visual contrast
between the disturbed area and the surrounding undisturbed dark desert
pavement.
4.1.11.1.4. Unavoidable Adverse Effects and
Level of Significance After Mitigation
The Proposed Action would result in a slight, unavoidable, and less than
significant increase in traffic on, and traffic-generated fugitive dust
from, public roads in the vicinity of the Project area over the 20-year
life of the Project. The Proposed Action would also result in the closure
of several currently open "routes" in the immediate vicinity of
the Project mine and process area, which would also not result in a significant
effect. When mitigated, the effects of the Proposed Action on traffic and
the local transportation system in the vicinity of the Project area would
not exceed levels of significance.
4.1.11.2. Utilities
4.1.11.2.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Encourage activities requiring large amounts of fuel, water, or energy;
- Use fuel, water, or energy in a wasteful manner;
- Breach published national, state, or local standards relating to solid
waste or litter control; or
- Extend a sewer trunk line with capacity to serve new development.
4.1.11.2.2. Impacts of the Proposed Action
Extending utility electrical service to the Project area would require
the "overbuilding" of approximately sixteen (16) miles of
existing IID 34.5 kV transmission line with a new 92 kV/34.5 kV
transmission line in the corridor from Interstate Highway 8 to the
existing transmission line's intersection with Indian Pass Road. In addition,
in the Project ancillary area, approximately 3.7 miles of new 92 kV
transmission line, underbuilt with a 13.2 kV distribution line, would
be constructed from the intersection with the overbuilt 92 kV/34.5 kV
transmission line to a step-down substation to the constructed in the Project
mine and process area. The existing 34.5 kV transmission line would
remain in service while the overbuilt 92 kV/34.5 kV transmission
line was being built, so there would be no interruption of service for existing
customers. Following the completion of mining and reclamation, the 92 kV/13.2 kV
transmission line would be removed, but the overbuilt 92 kV/34.5 kV
transmission line would remain under the ownership of the local utility.
Because there would be no interruption in service, and the electrical utility
system would be upgraded, there would be a net positive effect on the electric
utility system.
During periods of utility service interruption, an on-site, $750 kW, diesel-powered
generator would be used to provide emergency power for essential loads and
services.
No telephone utility services are directly available to the Project area.
A telephone communications relay to existing Black Mountain communication
facilities would be installed to provide telephone service to the offices
and maintenance shop via a microwave system which would be located within
the Project area. Field communications would be provided by an FM mine communication
system. The use of the microwave system and/or the FM mine communication
system should not interfere with pilot communications during military overflights
of the Project area and vicinity since these systems would be on different
frequencies. This would not be a significant effect of the Proposed Action.
No utility-provided natural gas service is available to the Project area,
nor would the existing system be adversely affect in other areas by the
Proposed Action.
No utility-provided water services are available to the Project area. Water
for mine operations and fire protection requirements would be produced from
ground water wells constructed southwest of the Project area and piped in
a buried pipeline to the Project area. The produced water would be stored
in an on-site water storage tank for mining and fire protection requirements.
Water collected in the open pits would be used where possible for roadway
dust suppression purposes. Accordingly, there would be no adverse effect
on water utility systems as a result of the Proposed Action.
The Proposed Action is not expected to generate significant population growth
(see Section 4.1.10.2), and therefore any significant demand
for local utility services, in the communities in which any Project employees
and/or contractors, and their respective families, who may relocate for
their job with the Project.
All portable and salvageable structures would be removed and taken off-site.
Any permanent below-grade structures and all foundations would be removed,
except the buried water pipeline and the process pond liners, and disposed
of in a landfill authorized to accept these materials. All surplus materials,
storage containers and trash would be transported to a landfill authorized
to accept this material. The remaining waste products, and all surplus fuel
oil and other materials, would be removed from the Project area and disposed
of according to then-current state and federal regulations. Given the relatively
small volumes of waste to be disposed of off-site, the Proposed Action would
not result in a significant effect on the local and regional landfills and
regulated or hazardous waste treatment or disposal facilities.
4.1.11.2.3. Measures Incorporated by Project
Design and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.11.2-1: Applicant shall make available an on-site, diesel-fuel
generator to meet emergency power needs for essential loads and services
during periods of utility-provided electrical service interruption.
- 4.1.11.2-2: Applicant shall, at the end of the active life of the Project,
remove all below-grade structures and all foundations, including the process
pond liners; transport all surplus materials, storage containers and trash
to a reuse or recycle facility, or to a landfill, authorized to accept
this material; remove all remaining non-mining waste products, all surplus
fuel oil, and other materials from the Project mine and process area and
dispose of them according to then-current state and federal regulations.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.11.2-3: Applicant shall acquire the necessary approvals of the
BLM, Imperial Irrigation District, and other
appropriate agencies to construct the 92 kV transmission line over
the existing 34.5 kV transmission line, and shall design, construct
and maintain this transmission line in accordance with the conditions of
these permits, including avoiding the disturbance of any new surface areas
during construction.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
No measures are proposed or recommended.
Other Mitigation Measures (These are measures which may further
reduce the impacts of certain effects which are below the level of significance
without mitigation):
- 4.1.11.2-4: Applicant shall work with the USMC to ensure that neither
the microwave communication system nor the Project FM mine communication
system interfere with military overflight communications.
4.1.11.2.4. Unavoidable Adverse Effects and
Level of Significance After Mitigation
The Proposed Action would result in the consumption of utility-provided
electrical power, which would not be adverse or significant. No other public
utility services (except utility-provided telephone service, once connected
with the microwave communication system) would be utilized by the Project,
and the potential adverse effects of the Project communication systems on
USMC use of the Project area would be mitigated to insignificance. Therefore,
the effects of the Proposed Action on utility services would not exceed
the level of significance.
4.1.11.3. Public Services
4.1.11.3.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Create a substantial demand for public services.
4.1.11.3.2. Impacts of the Proposed Action
No public or community services are available in the Project area. Septic
treatment systems with leach drain fields would be constructed near the
office and shop facilities, near the processing and laboratory facilities,
and near the lime storage facilities. Produced ground water stored on the
Project mine and process area would be used for commodes and hand-washing.
Bottled water would be provided for drinking water.
The Project mine and process area is located on the township line between
T.13S., R.21E. and T.14S., R.21E., and between eight (8) and nine (9)
GLO/BLM Cadastral Survey monuments are likely
located within the Project mine and process area along the township line.
(None of the sections adjoining the township line within the Project mine
and process area are surveyed or monumented.) Although some of these township
line monuments may be able to be protected and maintained, damage or destruction
to others within the Project mine and process area is inevitable since several
are located within the projected pit or waste rock stockpile boundaries.
The few Project employees and contractors, and their respective families,
who may relocate to regional communities would produce a very small increase
in the demand for public and community services. Most of these families
would be expected to reside in either Imperial County, California or Yuma
County, Arizona. Any costs associated with these minor increases in demand
for public or community services would be off-set by the additional property
taxes and sales taxes provided to the communities and counties by the Project
and Project employees. The Proposed Action would thus not result in a significant
increase in population nor generate significant new demand for public or
community services.
4.1.11.3.3. Measures Incorporated by Project
Design and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.11.3-1: Applicant shall provide an on-site septic system for wastewater
treatment, which shall be removed upon completion of Project activities.
- 4.1.11.3-2: When no longer required for Project operations, Applicant
shall remove that portion of the 92 kV/13.2 kV transmission line
owned by the Project.
- 4.1.11.3-3: Applicant shall provide potable water for hand washing
and drinking purposes.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.11.3-4: Applicant shall obtain necessary permit(s) for on-site
sanitary facilities from the Imperial County Department of Health Services.
- 4.1.11.3-5: To the extent feasible, all GLO/BLM
Cadastral Survey monuments shall be avoided and protected from any accidental
damage or destruction. All monuments which may be subject to either intentional
or accidental damage or destruction within the Project mine and process
area shall be perpetuated by the installation and survey of witness monuments,
subject to the prior approval of the survey by the BLM
Cadastral Survey and conformance with the applicable California codes,
and documented with a record of survey.
Incorporated to Avoid or Reduce Potentially Significant Effects:
No measures are proposed or identified.
4.1.11.3.4. Unavoidable Adverse Effects and
Level of Significance After Mitigation
The Proposed Action would result in a very small increase in demand for
public services, but these effects would be far below the level of significance.
4.1.12. Emergency Services and Public Safety
4.1.12.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Create a potential health hazard or involve the use, production, or
disposal of materials which pose a hazard to people or animal or plant
populations in the area affected;
- Interfere with emergency response plans or emergency evacuation plans.
4.1.12.2. Impacts of the Proposed Action
Design elements of the Project would minimize the need for off-site emergency
services. The Proposed Action would not require routine patrol services
by the police, as on-site personnel would patrol the Project mine and process
area 24-hours per day, providing security. The Project heap leach pad, process
facility, and solution ponds would be fenced with chain-link and barbed
wire to prevent unlawful access. "No trespassing" signs and other
warnings would be strategically located along the fenced perimeter of the
Project mine and process area and the fenced ground water well sites. The
"No trespassing" signs and fences would be removed following release
of the reclamation bond. If needed, police services would be provided by
the Imperial County Sheriff's Department. The nearest sheriff's substation
is located in Winterhaven, approximately 30 road miles from the Project
mine and process area.
Project facilities would be equipped with on-site fire protection systems.
Fire services would also be available from the Imperial County Fire Department
station at Winterhaven.
Mine chemicals/blasting agents and associated explosives would be stored
in locked magazines in compliance with ATF and
MSHA safety standards.
Relatively large volumes of hazardous, and potentially hazardous, chemicals
would be transported to, and stored within, the Project mine and process
area, including: blasting agents and explosives; solid sodium cyanide (during
transportation) and liquid sodium cyanide (stored on-site); sodium hydroxide;
hydrochloric acid; polymaleic acid; ammonium nitrate; diesel fuel; unleaded
gasoline; and motor oil. The transport, storage, and handling of these materials
have the potential to create adverse effects from spills into the environment
and impact the safety of the public and Project employees.
Some of the chemicals and hazardous materials to be stored in the Project
mine and process area are incompatible and reactive substances. In particular,
a spill or mixing of sodium cyanide with an acid would result in the release
of toxic hydrogen cyanide gas. The Proposed Action states that cyanide chemicals
and acids would never be stored near each other, and the Project would implement
triple-redundant procedures to ensure an event would not happen (Personal
Communication, Steve Baumann, Glamis Imperial, 1997). Further, the use of
these chemicals is a standard and common practice and a recognized potential
hazard at precious metal mines using the heap leach process, and a potential
hazard which employee training and good handling practices would be expected
to prevent. It is extremely unlikely that the use of these chemicals within
the Project mine and process area would pose any risk to individuals off-site.
Therefore, the potential for the Proposed Action to create a hydrogen cyanide
gas health hazard would be below the level of significance.
There would be a potential for public safety-related impacts due to the
transport of hazardous chemicals to the Project area via public highways
and access roads. The probability of hazardous chemical spillage occurring
due to a transport accident is considered low, but the potential for occurrence
cannot be entirely eliminated. The potential for a spill of sodium cyanide
during transportation to the Project mine and process area to create result
in a substantial hazard to public safety or the environment is extremely
low since the sodium cyanide would be transported to the Project in a solid,
briquette form in sealed tanker trucks. A hazardous material spill contingency
plan would be prepared by the Applicant to respond to potential hazardous
material and chemical spills within the Project area. All transporters of
hazardous materials for the Project are governed by State and federal regulations
regarding the transportation of hazardous materials on public highways.
Hazardous materials transporters are required to have special permits and
licenses, and receive extensive hazardous materials (HAZMAT) training which
prepares them to effectively manage spill incidents. Trucks which transport
hazardous materials are equipped with safety equipment and comprehensive
emergency response instructions to ensure proper action is taken in the
event of an emergency. Although the transporter is responsible for managing
and cleaning up any spill incidents, the California Highway Patrol would
respond to and provide assistance for any spill incidents which occur on
highways or roads in unincorporated portions of the Imperial County. Additionally,
the nearest District Fire Station would initially respond to a hazardous
material spill incident to provide immediate assistance, with follow-up
response provided by the Imperial County Fire Department HAZMAT Team. The
potential risk of a public safety hazard resulting from spills of hazardous
chemicals being transported to the Project area would be below the level
of significance.
Following completion of mining and final reclamation, the East Pit would
remain open, and the steep sidewalls of the open pit would result in a continuing
potential public safety risk. This public safety risk would be increased
if the open pit contained a pit lake, which might attract the public to
attempt to enter the pit. However, the Proposed Action includes measures
to reduce or eliminate the formation of a pit lake (see Section 2.1.3
and Section 4.1.3.1.2), and states that the open East Pit would
be barricaded with large boulders around the rim to prevent vehicular access
and discourage pedestrian access by the public over slopes which could constitute
a hazard (see Section 2.1.11.2.2). The barricade would consist
of boulders averaging approximately four (4) feet in diameter, which
would be stacked into a continuous wall no less than eight (8) feet
high. This "wall" would be set back from the edge of the pit by
no less than 100 feet. In addition, the uppermost ten (10) feet
of the pit slope would slope no greater than 2H:1V (30 degrees), and
would terminate at its lower side into a horizontal bench no less than ten (10)
feet wide. With this construction, the effects of the Project on public
safety from the remnant open pit would be below the level of significance.
Should mining be terminated prior to the complete backfilling of either
the West Pit or the Singer Pit, these pits would not be barricaded under
the Proposed Action, and no measures would be taken to reduce or eliminate
the formation of a pit lake in the West Pit. This would constitute a significant
effect on public safety.
4.1.12.3. Measures Incorporated by Project
Design and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.12-1: Applicant shall provide appropriate levels of on-site security,
fire protection services, and emergency first-aid medical services.
- 4.1.12-2: Applicant shall construct and maintain a fence around the
perimeter of the Project mine and process area over the life of the Project,
and a chain-link fence, no less than six (6) feet in height, with
one (1) foot of barbed wire at the top, around the ore leach pad,
process facilities, to prevent the public from accessing these facilities.
- 4.1.12-3: Sodium cyanide shall be shipped to, and received at, the
Project mine and process area in solid, briquette from in the manufacturer's
dry bulk trucks, and be put into solution directly from the dry bulk trucks
at the Project mine and process area process facility.
- 4.1.12-4: Before removal of the perimeter fence at the end of the active
life of the Project, Applicant shall construct around the rim of the open
East Pit a barricade with large boulders to prevent vehicular access and
discourage pedestrian access by the public over slopes which could constitute
a hazard. The barricade shall consist of boulders averaging approximately
four (4) feet in diameter, which shall be stacked into a continuous
wall no less than eight (8) feet high. This "wall" shall
be set back from the edge of the pit by no less than 100 feet. In
addition, the uppermost ten (10) feet of the pit slope shall slope
no greater than 2H:1V (30 degrees), and shall terminate at its lower
side into a horizontal bench no less than ten (10) feet wide.
- 4.1.12-5: Applicant shall post no trespassing and hazardous chemical
signs, in both English and Spanish, at strategic locations along perimeter
locations of the Project mine and process area perimeter fence and the
process facilities barbed wire-topped chain-link fence, respectively.
- 4.1.12-6: Applicant shall prepare a hazardous material spill/release
contingency plan and provide appropriate training to all Project employees
on the proper response to potential chemical releases.
- 4.1.12-7: Applicant shall prepare an emergency response contingency
plan which provides for actions to be taken in the event of an injury accident,
hazardous materials release, fire, flash flooding on Indian Pass Road,
or other emergency situation. The emergency response contingency plan shall
include emergency phone numbers and services available for both surface
and air transport of injured employees. The emergency contingency response
plan shall incorporate protocols acceptable to the BLM,
ICPWD, and the Imperial County Sheriff's Office for dealing with flash
floods and public safety on Indian Pass Road. The protocols shall address
notification of agencies and closures of Indian Pass Road.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.12-8: Applicant shall prepare and maintain a hazardous material
business plan in conformance with the requirements of Imperial County.
- 4.1.12-9: Applicant shall conform with all applicable safety regulations
required by the Mine Safety and Health Administration (MSHA), Occupational
Safety and Health Administration (OSHA), and California Occupational Safety
and Health Administration (Cal-OSHA ).
Incorporated to Avoid or Reduce Potentially Significant Effects:
See also those measures described in Section 4.1.5.4 designed
to eliminate the possibility of a pit lake to mitigate potential impacts
to wildlife.
- 4.1.12-10: Before removal of the perimeter fence at the end of the
active life of the Project, Applicant shall construct around the rim of
the all open pit(s) a barricade with large boulders to prevent vehicular
access and discourage pedestrian access by the public over slopes which
could constitute a hazard. The barricade shall consist of boulders averaging
approximately four (4) feet in diameter, which shall be stacked into
a continuous wall no less than eight (8) feet high. This "wall"
shall be set back from the edge of the pit by no less than 100 feet.
In addition, the uppermost ten (10) feet of the pit slope shall slope
no greater than 2H:1V (30 degrees), and shall terminate at its lower
side into a horizontal bench no less than ten (10) feet wide.
4.1.12.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
The Proposed Action would have the unavoidable indirect potential to
adversely effect worker and/or public safety through the accidental spill
or release of hazardous substances either in transport to the Project area
or from activities within the Project area. This unavoidable potential
effect is considered less than significant.
The mitigated effects of the Proposed Action on all emergency services and
public safety is below the level of significance.
4.1.13. Other Resources
4.1.13.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Convert prime agricultural land to non-agricultural use or impair the
agricultural productivity of prime or unique agricultural land.
- Result in a substantial adverse impact to a designated wild or scenic
river.
- Result in a substantially disproportionate share of the negative environmental
impacts of a project on minority populations and low-income populations.
4.1.13.2. Impacts of the Proposed Action
Because neither the Project area nor the overbuilt 92 kV/34.5 kV
transmission line corridor is in or adjacent to an area of prime or
unique farmland or a designated wild or scenic river, the Proposed
Action would have no impacts to either of these resources.
Environmental Justice and Sacred Sites:
Environmental Justice Executive Order: Executive Order 12898
(Federal Actions to Address Environmental Justice in Minority Populations
and Low-Income Populations) was signed by President Clinton on February 11,
1994 and became effective on that date. This Executive Order required each
federal agency to make achieving "environmental justice" part
of its mission by identifying and addressing, as appropriate, disproportionately
high and adverse human health or environmental effects on minority populations
and low-income populations in the United States and its territories and
possessions. Agency responsibilities under the Executive Order apply equally
to Native American programs.
Relevant to Environmental Justice is the nature of the proposed action and
requisite law involved. A mining project such as the Imperial Project allows
for limited agency discretion, practically as well as regulatorally (see
Section 1.6.1). The location and layout of a mine is a consequence
of the nature and formation of mineral ore body. Section 3 of the 1872
Mining Act (30 USC 26) gives exclusive right of "possession
and enjoyment" of the surface within the boundaries of a valid mining
claim to the mining claimant. The right of the United States to manage surface
resources but not locatable minerals on a valid mining claim was also authorized,
as long as such management did not materially interfere with the operation
of the mining claim (30 USC 612(b)).
Population in the Affected Area: The Project area lies within an
unpopulated, unincorporated area of Imperial County. The nearest residence
is located at Gold Rock Ranch, a mobile home (21 sites)/RV park (14 sites)
located approximately seven (7) miles southwest of the Project mine
and process area (see Section 5.2.2.2). No other residences
exist within ten (10) miles of the Project mine and process area. The
Project mine and process area is ten (10) miles from the closest point of
the Ft. Yuma Indian Reservation, and the principal concentrations of
housing on the reservation are over sixteen (16) miles away.
Impact: Quechan tribal members expressed concern that construction
and operation activities in the Project mine and process area would impact
an area of religious, cultural, and educational value, which has been termed
the Indian Pass-Running Man ATCC (see Section 3.6.2.4).
This area was used as recently as the 1940's for specific religious observances
that can only occur in this place, and Quechan tribal members have stated
that they plan to conduct such observances at this location in the future.
The Indian Pass-Running Man ATCC is viewed as
necessary for religious practitioners to gain requisite knowledge for continuation
of Quechan religious beliefs and practices, and necessary for teaching Indian
youth about tribal history, religion, and culture. Quechan tribal members
have stated that the development of the Project pits, heap, and waste rock
stockpiles would destroy the ability of the Quechan to perform their religious,
cultural and educational practices.
Quechan tribal members have also expressed concern for the cumulative impacts
of both recent developments and historic activities on sites of cultural
and religious significance (see Section 5.3.4 for a discussion
of cumulative impacts to cultural sites and religious values).
The environmental consequences of the Proposed Action (see Section 4.1.1
through Section 4.1.12) will not result in any conditions, such
as reduced air quality, noise exposure, or transportation of hazardous or
other materials, which could produce a substantial direct or indirect impact
to human health or environmental effects to any population residing at the
distances identified above from the Project area.
Consultation with Native American Pursuant to Executive Order 12898:
The BLM, through the El Centro Resource Area
Manager, initiated an extensive consultation process with the Quechan Tribe
in 1996 in conformance with NHPA, AIRFA, and
the Executive Order 13007 (Sacred Sites). Based upon comments, particularly
those by the Quechan Tribe, the November 1996 Draft EIS was withdrawal and
a new Draft EIS prepared (see Section 1.5 and Chapter 7).
As part of the process to prepare this new Draft EIS, the Quechan were requested
to participate in resurveying the area
of the Proposed Action, and an extensive effort to document Quechan
concerns was initiated through the Tribal Cultural Committee. Particular
individuals identified by the Tribal Cultural Committee provided cultural
and religious information (see Section 3.6).
4.1.13.3. Measures Incorporated by Project
Design and Regulation and Mitigation Measures
No mitigation measures are required.
4.1.13.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
The Proposed Action would have no unavoidable adverse effects on other
resources.
4.2. West Pit Alternative
As discussed in Section 2.2.1, the West Pit Alternative would
eliminate the East Pit, the East Waste Rock Stockpile, and the East Pit
West and East Pit East drainage diversions within the Project mine and process
area. The size of the leach pad, the process area, and the haul and maintenance
roads would also be reduced. Only 150 million tons of material would
be mined. The total surface area of disturbance within the Project mine
and process area would be reduced from 1,302 acres under the Proposed
Action to approximately 795 acres (see Table 2.6),
and the Project life would be decreased from the approximately twenty (20)
years under the Proposed Action to about ten (10) years under the West
Pit Alternative. Under the West Pit Alternative, the Singer Pit would not
be backfilled, and the West Pit would only be partially backfilled with
waste rock from the Singer Pit. Both the South Waste Rock Stockpile and
the heap would be constructed to a height of approximately 300 feet,
the same height as under the Proposed Action. All environmental protection
measures and reclamation activities would be conducted as under the Proposed
Action.
4.2.1. Geology and Mineral Resources
4.2.1.1. Impacts of the West Pit Alternative
The West Pit Alternative would leave the precious metal resources in
the East Pit area unmined and undeveloped. Because the West Pit would only
be partially backfilled, any residual potential mineral resources remaining
in the West Pit would be more available to be developed in the future than
were the pit to be completely backfilled. Neither of these differences create
a significant environmental effect. Other than these, there would be no
substantive difference in the impacts of the West Pit Alternative on geology
and mineral resources from those identified for the Proposed Action (see
Section 4.1.1.2). The effects of the West Pit Alternative on
geology and mineral resources would be below the levels of significance.
4.2.1.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on geology and mineral resources would be the same as those identified for
the Proposed Action (see Section 4.1.1.3). No other measures
would be necessary to reduce impacts of the West Pit Alternative below the
level of significance. The effects of the West Pit Alternative on geology
and mineral resources would remain below the level of significance.
4.2.2. Soil Resources
4.2.2.1. Impacts of the West Pit Alternative
The West Pit Alternative would decrease the total area of surface disturbance
from the 1,362 acres under the Proposed Action to 853 acres,
an approximate 37 percent reduction. This would translate to an approximate
37 percent reduction in the loss of soil resources (see Section 4.1.2.2).
Other potential impacts, such as erosion within the West Pit Alternative
project mine and process area, would be the same in effect, although slightly
reduced in magnitude, as those identified for the Proposed Action in Section 4.1.2.2.
There would be a two (2) acre (six [6] percent) reduction in the
acreage of soils disturbed in the West Pit Alternative project ancillary
area because only two (2) ground water wells would be drilled, but
no change in the overbuilt 92 kV/34.5 kV transmission line corridor.
The effects of the West Pit Alternative on soil resources would also be
below the levels of significance.
4.2.2.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on soil resources would be the same as those identified for the Proposed
Action (see Section 4.1.2.3). No other measures would be necessary
to reduce impacts of the West Pit Alternative below the level of significance.
The effects of the West Pit Alternative on soil resources would remain below
the level of significance.
4.2.3. Hydrologic Resources
4.2.3.1. Impacts of the West Pit Alternative
Surface Water
The West Pit Alternative would eliminate the need to construct the East
Pit West and East Pit East diversion channels, and would eliminate any impact
to these existing surface drainage channels. The remaining impacts to surface
water diversions would not be significant. The East Pit would not be mined,
the East Waste Rock Stockpile would not be built, and the heap would be
reduced in size, so there would be less precipitation contained within the
West Pit Alternative project mine and process area and not discharged into
surface runoff. The impact to sediment production of the facilities constructed
under the West Pit Alternative would be less than significant. Since the
East Pit would not be mined, the potential for seeps or a pit lake in the
East Pit would be completely eliminated. However, since the West Pit would
not be completely backfilled under the West Pit Alternative, and the West
Pit is projected to be mined to a depth below the existing ground water
level, seeps, and possibly (but not likely) a pit lake, could form in the
West Pit. Since the Singer Pit would not be mined below the elevation of
the ground water table , no pit lake
could form from ground water inflows as a result of not backfilling the
Singer Pit. The impacts of the West Pit Alternative from ground water inflows
would be below the level of significance. The West Pit Alternative would
also result in a reduction of 29 percent, to 55.2 acres (LSA 1997b),
in the area of "waters of the United States" which would be dredged
or filled over the Proposed Action. This impact would also be below the
level of significance (see Section 4.1.3.1.2).
Ground Waters
The West Pit Alternative would produce ground water for operations at a
rate somewhat less than that under the Proposed Action, and from a maximum
of only two (2) ground water wells. Also, since the West Pit Alternative
would have an estimated life of only half that of the Proposed Action, the
total amount of water produced would be substantially less than half of
that produced under the Proposed Action. However, because most of the ground
water table drawdown occurs early in
the ground water production process, the ground water table drawdown in
the area surrounding the ground water production wells would be only slightly
reduced from the Proposed Action. Recovery to pre-project levels would be
substantially earlier, however, because pumping would cease sooner. Neither
impact would be above the level of significance. The effects of the West
Pit Alternative on ground water quality and pit water quality would not
be different than that of the Proposed Action, although the likelihood of
any impacts to ground water quality or pit water quality would be further
reduced because of the reduction in size of the heap pad and the elimination
of the East Pit (see Section 4.1.3.2.2).
4.2.3.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on surface water and ground water resources would be the same as those identified
for the Proposed Action (see Section 4.1.3.1.3 and Section 4.1.3.2.3).
No other measures would be necessary to reduce impacts of the West Pit Alternative
below the level of significance. The effects of the West Pit Alternative
on surface water and ground water resources would remain below the level
of significance.
4.2.4. Air Resources
4.2.4.1. Impacts of the West Pit Alternative
The impacts of the West Pit Alternative on air resources would be very
similar to, but slightly reduced from, the impacts to air resources which
would result from the implementation of the Proposed Action. The biggest
difference would be that the impacts from the West Pit Alternative would
be reduced in duration to only ten (10) years from twenty (20)
years under the Proposed Action (see Section 4.1.4.2). The effects
of the West Pit Alternative on air resources would be below the level of
significance except for PM10. Although the effects of the West
Pit Alternative would be mitigated to below the level of significance, the
West Pit Alternative would still contribute to exceedences of the 24-hour
CAAQS for PM10 which may continue
to occur in the future during periods of high wind. This would be a cumulatively
significant effect.
4.2.4.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on air resources would be the same as those identified for the Proposed
Action (see Section 4.1.4.3). No other measures are proposed
to reduce impacts of the West Pit Alternative below the level of significance.
The effects of the West Pit Alternative on air resources would remain below
the level of significance except for PM10. Although the effects
of the West Pit Alternative would be mitigated to below the level of significance,
the West Pit Alternative would still contribute to exceedences of the 24-hour
CAAQS for PM10 which may continue
to occur in the future during periods of high wind. This would remain a
cumulatively significant effect.
4.2.5. Biological Resources
4.2.5.1. Impacts of the West Pit Alternative
Vegetation and Plant Habitat
The West Pit Alternative would reduce the total surface disturbance from
1,362 acres under the Proposed Action to 853 acres, a reduction
of 37 percent. The loss of shrub/scrub vegetation habitat would be
reduced from approximately 1,260 acres under the Proposed Action to
approximately 719 acres, and the loss of shrub/tree vegetation habitat
would be reduced from approximately 87 acres under the Proposed Action
to approximately 52 acres. In addition, the amount of surface area
not reclaimed (the West Pit slopes not covered by backfill)
would decrease from 165 acres under the Proposed Action to approximately
88 acres, a reduction of 47 percent. The time required to complete
final reclamation would also be reduced to approximately ten (10) years.
Although the magnitude of the impacts to vegetation and plant habitat from
this reduced surface disturbance would be reduced by 37 percent, the
impacts themselves would be the same as the Proposed Action, and would remain
below the level of significance. Other impacts to vegetation and plant habitat
(from dust, ground water pumping, surface channel diversions, and sensitive
plants) would also be reduced proportionately from those of the Proposed
Action (see Section 4.1.5.2), and would remain below the level
of significance.
Wildlife, Wildlife Habitat and Wildlife Movement
The reduced area of surface disturbance resulting from the West Pit Alternative
would also reduce the amount of wildlife habitat lost over that of the Proposed
Action. Approximately 719 acres of desert succulent scrub habitat and
52 acres of microphyll woodland habitat would be lost. Approximately
152 acres of the 947-acre West Pit Alternative project mine and process
area would be undisturbed. Most of this habitat loss would be temporarily,
until the completion of final reclamation (and subsequent vegetation recovery).
However, approximately one-half (2) of the disturbed microphyll woodland
habitat would be reclaimed not as microphyll woodland habitat but as desert
succulent scrub habitat, and the 88 acres of the West Pit slopes would
not be reclaimed.
Although the magnitude of the impacts to wildlife and wildlife habitat from
this reduced surface disturbance would be reduced by 37 percent, the
impacts themselves would be the same as the Proposed Action, and would remain
below the level of significance. Other impacts from the West Pit Alternative
on wildlife and wildlife habitat (from ground water pumping, surface channel
diversions, and sedimentation) would also be reduced proportionately from
those of the Proposed Action (see Section 4.1.5.3), and would
remain below the level of significance.
The West Pit Alternative would mine and leave open or partially open the
33-acre Singer Pit and the 110-acre West Pit. This would reduce the potential
area over which wildlife could be killed or injured by falls or opportunistic
predators from the 198-acres left open under the Proposed Action. This impact
would be below the level of significance.
The West Pit Alternative would have a life of only approximately ten (10)
years, which would reduce the exposure of wildlife and wildlife habitat
to impacts from vehicles, hazardous materials, noise, human presence, etc.,
by about one-half (2) over the Proposed Action. These effects would
be below the level of significance.
Although reduced from the Proposed Action, the impacts of the West Pit Alternative
on the desert tortoise would remain above the level of significance.
4.2.5.2. Mitigation Measures
Measures to reduce the effects of the West Pit Alternative on biological
resources would be the same as those measures identified for the Proposed
Action (see Section 4.1.5.4), except as altered to reflect the
reduction in area or time from the Proposed Action. With implementation
of the identified measures, the mitigated effects of the West Pit Alternative
on biological resources would be below the level of significance.
4.2.6. Cultural and Paleontological Resources
4.2.6.1. Impacts of the West Pit Alternative
The West Pit Alternative would create approximately 38 percent less
surface disturbance than the Proposed Action within the Project area, and
identical surface disturbance within the overbuilt 92 kV/34.5 kV
transmission line corridor. However, the density of cultural resource features
determined eligible for the NRHP and identified within the Project mine
and process area is substantially higher on the west side, in the area of
the West Pit and South Waste Rock Stockpile, than on the east side, in the
area of the East Pit and the heap leach pad and process facilities. Consequently,
the impacts of the West Pit Alternative on cultural resources determined
eligible for the NRHP appear to be only slightly less than the impacts to
these same type of cultural resources which would result from the implementation
of the Proposed Action. The impacts of the West Pit Alternative would remain
above the level of significance. The West Pit Alternative would do little
to reduce the adverse effects on the Indian Pass-Running Man ATCC,
and remaining impacts would be above the level of significance. The effects
of the West Pit Alternative on those cultural resources identified within
the overbuilt 92 kV/34.5 kV transmission line corridor would be
identical to the Proposed Action, and above the level of significance.
4.2.6.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on cultural resources would be the same as those identified for the Proposed
Action (see Section 4.1.6.3). Measures to reduce the significant
effects of the West Pit Alternative on cultural resource features identified
within the overbuilt 92 kV/34.5 kV transmission line corridor,
or within the West Pit Alternative project area, which were determined eligible
for the NRHP under criterion "D" would be identical to those
identified for the Proposed Action. The mitigated impacts would be reduced
below the level of significance. Measures to reduce the significant effects
of the West Pit Alternative on cultural resource features determined eligible
for the NRHP under criteria "A", "B," or "C"
which were identified within the West Pit Alternative project area, or to
reduce the significant effects of the West Pit Alternative on the Indian
Pass-Running Man ATCC, would be identical to
those identified for the Proposed Action. The mitigated effects of these
impacts would remain above the level of significance and be unavoidable.
4.2.7. Visual Resources
4.2.7.1. Impacts of the West Pit Alternative
The West Pit Alternative would result in visual contrasts created by
changes in line and form from the creation of new structures and facilities,
altered surface colors, textures and vegetation cover, and changes in topography
similar to the Proposed Action (see Section 4.1.7.2). Because
of the smaller area of surface disturbance, the elimination of one waste
rock stockpile, and the smaller size (but not height) of the remaining waste
rock stockpile and heap, the magnitude of these effects would be reduced
from some viewpoints, but not from others. The view of the West Pit Alternative
project mine and process area from KOP #1 and KOP #4 would be
very similar to the view of the Proposed Action from these same points (see
Figure 4.3 and Figure 4.9, respectively) since the
view of the West Pit Alternative is principally of the upper portions of
the south ends of the South Waste Rock Stockpile and the heap, which change
very little from the Proposed Action. The view of the West Pit Alternative
project mine and process area from KOP #2 and KOP #3 (see Figure 4.5
and Figure 4.7, respectively) would show the reduced surface
disturbance and the elimination or reduction of each of the features within
the West Pit Alternative project mine and process area over the Proposed
Action. However, the effects of the West Pit Alternative on line and form
would remain, like the Proposed Action, above the level of significance.
Impacts to visual resources from the West Pit Alternative from the lighting
of mine and process areas and visibility reduction would remain essentially
identical to the Proposed Action (see Section 4.1.7.2), except
that they would be shorter in duration by about ten (10) years. Like
the Proposed Action, the impacts of visibility reduction would be below
the level of significance, while the impacts of lighting would be above
the level of significance.
4.2.7.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
which eliminate potentially significant effects on visual resources would
be the same as those identified for the Proposed Action (see Section 4.1.7.3).
Measures to reduce the significant effects of the West Pit Alternative on
lighting would also be the same as those measures identified for the Proposed
Action. With implementation of the identified measures, the mitigated effects
of the West Pit Alternative on visual resources from visibility reduction
and lighting would be below the level of significance. The mitigated effects
of the West Pit Alternative on visual resources from changes in line and
form would remain above the level of significance.
4.2.8. Noise
4.2.8.1. Impacts of the West Pit Alternative
The noise generated by the West Pit Alternative would be essentially
identical to the noise generated by the Proposed Action, except that the
noise would cease earlier. The impacts of the generated noise on receptors
would also be essentially the same as that described for the Proposed Action
(see Section 4.1.8.2), except that the impacts would also cease
earlier. The noise impacts of the West Pit Alternative would be below the
levels of significance.
4.2.8.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
of noise would be the same as those identified for the Proposed Action (see
Section 4.1.8.3). No other measures would be necessary to reduce
impacts of the West Pit Alternative below the level of significance. The
noise effects of the West Pit Alternative would remain below the level of
significance.
4.2.9. Land Use
4.2.9.1. Impacts of the West Pit Alternative
The compatibility of the West Pit Alternative with existing land uses
and adopted land use policies and plans would be essentially identical to
that of the Proposed Action (see Section 4.1.9.2). Blasting
during mining operations could be a significant potential hazard to low-flying
military aircraft using the general area for training exercises (although
this impact would end in approximately ten (10), rather than twenty (20),
years). The West Pit Alternative's impact on recreational use of the area,
including wilderness use, would be essentially identical in type, but slightly
reduced in scale and duration, from that of the Proposed Action, since the
West Pit Alternative would exclude recreational use only over 947 acres
for approximately ten (10) years instead of 1,571 acres for approximately
twenty (20) years. These impacts would be below the level of significance.
4.2.9.2. Mitigation Measures
Measures to ensure the compatibility of the West Pit Alternative with
existing land uses, adopted land use policies and plans, and recreational
use of the area would be the same as those measures identified for the Proposed
Action (see Section 4.1.9.2). With implementation of the identified
measures, the mitigated level of compatibility of the West Pit Alternative
with existing land uses, adopted land use policies and plans, and recreational
use of the area, would be below the level of significance.
4.2.10. Socioeconomics
4.2.10.1. Impacts of the West Pit Alternative
The West Pit Alternative would have a net beneficial socioeconomic effect
which would be reduced from the net beneficial socioeconomic effect of the
Proposed Action (see Section 4.1.10.2). These effects would
be below the level of significance. Although the number of jobs created
under the West Pit Alternative would be approximately the same as the Proposed
Action, the length of these jobs would be decreased from approximately twenty (20) years
to ten (10) years. Initial capital expenditures for (and thus sales
taxes paid under) the West Pit Alternative would be approximately the same
as the Proposed Action. Recurrent, annual expenditures (such as annual capital
expenditures of approximately $1.7 million (and $0.13 million
in sales taxes), non-capital expenditures of approximately $26 million,
and property taxes of between $200,000 and $600,000) would be reduced by
one-half (2) from that of the Proposed Action because of the decreased operating
life.
4.2.10.2. Mitigation Measures
No mitigation measures are proposed or recommended.
4.2.11. Roads and Public Services
4.2.11.1. Impacts of the West Pit Alternative
The West Pit Alternative would result in an essentially identical increase
in traffic as the Proposed Action (see Section 4.1.11.1.2),
except that the effects would occur for only ten (10), rather than
twenty (20), years. These effects would be below the level of significance.
The West Pit Alternative would require the realignment of Indian Pass Road
to the identical degree and timing as the Proposed Action. These impacts
would also be below the level of significance. The West Pit Alternative
would also create a potential impact from "spur" roads, to a similar
extent and degree as the Proposed Action. This impact would be below the
level of significance.
The West Pit Alternative would have a similar impact on utilities as the
Proposed Action. Because of the reduced size of the project, less non-mining
waste would be generated (see Section 4.1.11.1.2). All impacts
on utilities would be below the level of significance. The West Pit Alternative
would also produce impacts on public services similar to the Proposed Action
(see Section 4.1.11.3.2). Because of the reduced surface area
to be disturbed, there would be fewer cadastral monuments which may be destroyed.
These impacts would be below the level of significance.
4.2.11.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on roads, utilities and public services would be the same as those measures
identified for the Proposed Action (see Section 4.1.11.1.3,
Section 4.1.11.2.3, and Section 4.1.11.3.3). No
other measures would be necessary to reduce impacts of the West Pit Alternative
below the level of significance. The effects of the West Pit Alternative
on roads, utilities and public services would remain below the level of
significance.
4.2.12. Emergency Services and Public Safety
4.2.12.1. Impacts of the West Pit Alternative
The West Pit Alternative would have essentially identical impacts on
emergency services and public safety as would the Proposed Action (see Section 4.1.12.2),
although the life of the West Pit Alternative would be ten (10), rather
than twenty (20), years. Instead of the East Pit being left open following
the completion of mining and reclamation, under the West Pit Alternative
the Singer Pit and the West Pit would be left open. The effects of the West
Pit Alternative on emergency services and public safety would be less than
significant.
4.2.12.2. Mitigation Measures
Mitigation measures incorporated into the West Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on emergency services and public safety would be the same as those measures
identified for the Proposed Action (see Section 4.1.12.3). No
other measures would be necessary to reduce impacts of the West Pit Alternative
below the level of significance. The effects of the West Pit Alternative
on emergency services and public safety would be below the level of significance.
4.2.13. Other Resources
4.2.13.1. Impacts of the West Pit Alternative
The West Pit Alternative would have essentially identical impacts on
other resources as would the Proposed Action (see Section 4.1.13),
although the life of the West Pit Alternative would be ten (10), rather
than twenty (20), years. The effects of the West Pit Alternative on
other resources would be less than significant.
4.2.13.2. Mitigation Measures
No mitigation measures are proposed or recommended.
4.3. East Pit Alternative
As discussed in Section 2.2.2, the East Pit Alternative would
eliminate the West Pit, the West Soil Stockpile, the West Pit West and West
Pit East drainage diversions, and the relocation of Indian Pass Road within
the Project mine and process area. The size of the leach pad, the South
Waste Rock Stockpile, the associated areas of disturbance, and the haul
and maintenance roads would also be reduced. Only 300 million tons
of material would be mined. The total surface area of disturbance within
the Project mine and process area would be reduced from 1,302 acres
under the Proposed Action to approximately 1,126 acres (see Table 2.7), and the Project life would be decreased
from the approximately twenty (20) years under the Proposed Action
to about fourteen (14) years under the East Pit Alternative. Under
the East Pit Alternative, the Singer Pit would be completely backfilled,
and the East Pit would not be backfilled. The South Waste Rock Stockpile
and the East Waste Rock Stockpile would still be constructed to approximately
the same height (300 feet) as under the Proposed Action, but the heap
would be constructed to a height of approximately 250 feet.
4.3.1. Geology and Mineral Resources
4.3.1.1. Impacts of the East Pit Alternative
The East Pit Alternative would leave the precious metal resources in
the West Pit area unmined and undeveloped. This would not be a significant
environmental effect. Other than this, there would be no substantive difference
in the impacts of the East Pit Alternative on geology and mineral resources
from those identified for the Proposed Action (see Section 4.1.1.2).
The effects of the East Pit Alternative on geology and mineral resources
would be below the levels of significance.
4.3.1.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on geology and mineral resources would be the same as those identified for
the Proposed Action (see Section 4.1.1.3). No other measures
would be necessary to reduce impacts of the East Pit Alternative below the
level of significance. The effects of the East Pit Alternative on geology
and mineral resources would remain below the level of significance.
4.3.2. Soil Resources
4.3.2.1. Impacts of the East Pit Alternative
The East Pit Alternative would decrease the total area of surface disturbance
from the 1,362 acres under the Proposed Action to 1,126 acres,
an approximate 19 percent reduction. This would translate to an approximate
19 percent reduction in the loss of soil resources (see Section 4.1.2.2).
Other potential impacts, such as erosion within the East Pit Alternative
project mine and process area, would be the same in effect, although slightly
reduced in magnitude, as those identified for the Proposed Action in Section 4.1.2.2.
There would be a seven (7) acre (eighteen [18] percent) reduction
in the acreage of soils disturbed in the East Pit Alternative project ancillary
area because only three (3) ground water wells would be drilled and
Indian Pass Road would not be relocated. There would be no change in the
overbuilt 92 kV/34.5 kV transmission line corridor. The effects
of the East Pit Alternative on soil resources would also be below the levels
of significance.
4.3.2.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on soil resources would be the same as those identified for the Proposed
Action (see Section 4.1.2.3). No other measures would be necessary
to reduce impacts of the East Pit Alternative below the level of significance.
The effects of the East Pit Alternative on soil resources would remain below
the level of significance.
4.3.3. Hydrologic Resources
4.3.3.1. Impacts of the East Pit Alternative
Surface Water
The East Pit Alternative would eliminate the need to construct the West
Pit West and West Pit East diversion channels, and would eliminate any impact
to these existing surface drainage channels. The remaining impacts to surface
water diversions would not be significant. The West Pit would not be mined,
the West Soil Stockpile would not be built, and the heap would be slightly
reduced in size, so there would be slightly less precipitation contained
within the East Pit Alternative project mine and process area and not discharged
into surface runoff. The impact to sediment production of the facilities
constructed under the East Pit Alternative would be less than significant.
The impacts of the East Pit Alternative from ground water inflows would
be below the level of significance. The East Pit Alternative would also
result in a reduction of 17 percent, to 64.4 acres (LSA 1997b),
in the area of "waters of the United States" which would be dredged
or filled over the Proposed Action. This impact would also be below the
level of significance (see Section 4.1.3.1.2).
Ground Waters
The East Pit Alternative would produce ground water for operations at a
rate slightly less than that under the Proposed Action, and from a maximum
of three (3) ground water wells. Also, since the East Pit Alternative
would have an estimated life of approximately two-thirds (b) that of
the Proposed Action, the total amount of water produced would be less than
two-thirds (b) that produced under the Proposed Action. However, because
most of the ground water table drawdown
occurs early in the ground water production process, the ground water table drawdown in the area surrounding
the ground water production wells would be only slightly reduced from the
Proposed Action. Recovery to pre-project levels would be earlier, however,
because pumping would cease sooner. Neither impact would be above the level
of significance. The effects of the East Pit Alternative on ground water
quality and pit water quality would not be different than that of the Proposed
Action, although the likelihood of any impacts to ground water quality or
pit water quality would be slightly reduced because of the reduction in
size of the heap pad and the elimination of the West Pit (see Section 4.1.3.2.2).
4.3.3.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on surface water and ground water resources would be the same as those identified
for the Proposed Action (see Section 4.1.3.1.3 and Section 4.1.3.2.3).
No other measures would be necessary to reduce impacts of the East Pit Alternative
below the level of significance. The effects of the East Pit Alternative
on surface water and ground water resources would remain below the level
of significance.
4.3.4. Air Resources
4.3.4.1. Impacts of the East Pit Alternative
The impacts of the East Pit Alternative on air resources would be very
similar to, but slightly reduced from, the impacts to air resources which
would result from the implementation of the Proposed Action. The biggest
difference would be that the impacts from the East Pit Alternative would
be reduced in duration to only fourteen (14) years from twenty (20)
years under the Proposed Action (see Section 4.1.4.2). The effects
of the East Pit Alternative on air resources would be below the level of
significance except for PM10. Although the effects of the East
Pit Alternative would be mitigated to below the level of significance, the
East Pit Alternative would still contribute to exceedences of the 24-hour
CAAQS for PM10 which may continue
to occur in the future during periods of high wind. This would be a cumulatively
significant effect.
4.3.4.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on air resources would be the same as those identified for the Proposed
Action (see Section 4.1.4.3). No other measures are proposed
to reduce impacts of the East Pit Alternative below the level of significance.
The effects of the East Pit Alternative on air resources would remain below
the level of significance except for PM10. Although the effects
of the East Pit Alternative would be mitigated to below the level of significance,
the East Pit Alternative would still contribute to exceedences of the 24-hour
CAAQS for PM10 which may continue
to occur in the future during periods of high wind. This would remain a
cumulatively significant effect.
4.3.5. Biological Resources
4.3.5.1. Impacts of the East Pit Alternative
Vegetation and Plant Habitat
The East Pit Alternative would reduce the total surface disturbance from
1,362 acres under the Proposed Action to 1,126 acres, a reduction
of 19 percent. The loss of shrub/scrub vegetation habitat would be
reduced from approximately 1,260 acres under the Proposed Action to
approximately 1,064 acres, and the loss of shrub/tree vegetation habitat
would be reduced from approximately 87 acres under the Proposed Action
to approximately 62 acres. The amount of surface area not reclaimed
(the East Pit slopes not covered by backfill)
would remain unchanged from the Proposed Action at 165 acres. The time
required to complete final reclamation would also be reduced to approximately
fourteen (14) years.
Although the magnitude of the impacts to vegetation and plant habitat from
this reduced surface disturbance would be reduced by 19 percent, the
impacts themselves would be the same as the Proposed Action, and would remain
below the level of significance. Other impacts to vegetation and plant habitat
(from dust, ground water pumping, surface channel diversions, and sensitive
plants) would also be reduced proportionately from those of the Proposed
Action (see Section 4.1.5.2), and would remain below the level
of significance.
Wildlife, Wildlife Habitat and Wildlife Movement
The reduced area of surface disturbance resulting from the East Pit Alternative
would also reduce the amount of wildlife habitat lost over that of the Proposed
Action. Approximately 1,064 acres of desert succulent scrub habitat
and 62 acres of microphyll woodland habitat would be lost. Approximately
203 acres of the 1,276-acre East Pit Alternative project mine and process
area would be undisturbed. Most of this habitat loss would be temporarily,
until the completion of final reclamation (and subsequent vegetation recovery).
However, approximately one-half (2) of the disturbed microphyll woodland
habitat would be reclaimed not as microphyll woodland habitat but as desert
succulent scrub habitat, and the 165 acres of the East Pit slopes would
not be reclaimed.
Although the magnitude of the impacts to wildlife and wildlife habitat from
this reduced surface disturbance would be reduced by approximately 19 percent,
the impacts themselves would be the same as the Proposed Action, and would
remain below the level of significance. Other impacts from the East Pit
Alternative on wildlife and wildlife habitat (from ground water pumping,
surface channel diversions, and sedimentation) would also be reduced proportionately
from those of the Proposed Action (see Section 4.1.5.3), and
would remain below the level of significance.
The East Pit Alternative would mine and leave open the 198-acre East Pit,
which is the same potential area over which wildlife could be killed or
injured by falls or opportunistic predators as the Proposed Action. This
impact would be below the level of significance.
The East Pit Alternative would have a life of approximately fourteen (14)
years, which would reduce the exposure of wildlife and wildlife habitat
to impacts from vehicles, hazardous materials, noise, human presence, etc.,
by about one-third (a) over the Proposed Action. These effects would
be below the level of significance.
Although slightly reduced from the Proposed Action, the impacts of the East
Pit Alternative on the desert tortoise would remain above the level of significance.
4.3.5.2. Mitigation Measures
Measures to reduce the effects of the East Pit Alternative on biological
resources would be the same as those measures identified for the Proposed
Action (see Section 4.1.5.4), except as altered to reflect the
reduction in area or time from the Proposed Action. With implementation
of the identified measures, the mitigated effects of the East Pit Alternative
on biological resources would be below the level of significance.
4.3.6. Cultural and Paleontological Resources
4.3.6.1. Impacts of the East Pit Alternative
The East Pit Alternative would create approximately nineteen (19) percent
less surface disturbance than the Proposed Action within the Project area,
and identical surface disturbance within the overbuilt 92 kV/34.5 kV
transmission line corridor. The density of cultural resource features determined
eligible for the NRHP and identified within the Project mine and process
area is substantially higher on the west side, and specifically in the area
of the West Pit, than on the east side, in the area of the East Pit and
the heap leach pad and process facilities. Thus, the impacts of the East
Pit Alternative on cultural resources determined eligible for the NRHP appear
to be substantially less than the nineteen (19) percent reduction in
surface disturbance from the Proposed Action would imply. Although these
impacts of the East Pit Alternative on cultural resources determined eligible
for the NRHP are substantially reduced, the remaining effects would remain
above the level of significance.
The East Pit Alternative would reduce the adverse effects on the Indian
Pass-Running Man ATCC and the Native American
trail system through Indian Pass. Nonetheless, remaining impacts would be
above the level of significance. The effects of the East Pit Alternative
on those cultural resources identified within the overbuilt 92 kV/34.5 kV
transmission line corridor would be identical to the Proposed Action, and
above the level of significance.
4.3.6.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on cultural resources would be the same as those identified for the Proposed
Action (see Section 4.1.6.3). Measures to reduce the significant
effects of the East Pit Alternative on cultural resource features identified
within the overbuilt 92 kV/34.5 kV transmission line corridor,
or within the East Pit Alternative project area, which were determined eligible
for the NRHP under criterion "D" would be identical to those
identified for the Proposed Action. The mitigated impacts would be reduced
below the level of significance. Measures to reduce the significant effects
of the East Pit Alternative on cultural resource features determined eligible
for the NRHP under criteria "A", "B," or "C"
which were identified within the East Pit Alternative project area, or to
reduce the significant effects of the East Pit Alternative on the Indian
Pass-Running Man ATCC, would be identical to
those identified for the Proposed Action. The mitigated effects of these
impacts would remain above the level of significance and be unavoidable.
4.3.7. Visual Resources
4.3.7.1. Impacts of the East Pit Alternative
The East Pit Alternative would result in visual contrasts created by
changes in line and form from the creation of new structures and facilities,
altered surface colors, textures and vegetation cover, and changes in topography
similar to the Proposed Action (see Section 4.1.7.2). Because
of the slightly smaller area of surface disturbance, the smaller size of
the South Waste Rock Stockpile, and the slightly smaller height of the heap,
the magnitude of these effects would be slightly reduced from most viewpoints.
The view of the East Pit Alternative project mine and process area from
KOP #1 and KOP #4 would be very similar to the view of the Proposed
Action from these same points (see Figure 4.3 and Figure 4.9,
respectively) since the view of the East Pit Alternative from these points
is principally of the upper portions of the south ends of the South Waste
Rock Stockpile and the heap, which change little from the Proposed Action.
The view of the East Pit Alternative project mine and process area from
KOP #2 and KOP #3 (see Figure 4.5 and Figure 4.7,
respectively) would show the slightly reduced surface disturbance and the
elimination of the West Pit, West Pit West diversion channel, and Indian
Pass Road from within the East Pit Alternative project mine and process
area and ancillary area over the Proposed Action. However, the effects of
the East Pit Alternative on line and form would remain, like the Proposed
Action, above the level of significance.
Impacts to visual resources from the East Pit Alternative from the lighting
of mine and process areas and visibility reduction would remain essentially
identical to the Proposed Action (see Section 4.1.7.2), except
that they would be shorter in duration by about fourteen (14) years.
Like the Proposed Action, the impacts of visibility reduction would be below
the level of significance, while the impacts of lighting would be above
the level of significance.
4.3.7.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
which eliminate potentially significant effects on visual resources would
be the same as those identified for the Proposed Action (see Section 4.1.7.3).
Measures to reduce the significant effects of the East Pit Alternative on
lighting would also be the same as those measures identified for the Proposed
Action. With implementation of the identified measures, the mitigated effects
of the East Pit Alternative on visual resources from visibility reduction
and lighting would be below the level of significance. The mitigated effects
of the East Pit Alternative on visual resources from changes in line and
form would remain above the level of significance.
4.3.8. Noise
4.3.8.1. Impacts of the East Pit Alternative
The noise generated by the East Pit Alternative would be essentially
identical to the noise generated by the Proposed Action, except that the
noise would cease earlier. The impacts of the generated noise on receptors
would also be essentially the same as that described for the Proposed Action
(see Section 4.1.8.2), except that the impacts would also cease
earlier. The noise impacts of the East Pit Alternative would be below the
levels of significance.
4.3.8.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
of noise would be the same as those identified for the Proposed Action (see
Section 4.1.8.3). No other measures would be necessary to reduce
impacts of the East Pit Alternative below the level of significance. The
noise effects of the East Pit Alternative would remain below the level of
significance.
4.3.9. Land Use
4.3.9.1. Impacts of the East Pit Alternative
The compatibility of the East Pit Alternative with existing land uses
and adopted land use policies and plans would be essentially identical to
that of the Proposed Action (see Section 4.1.9.2). Blasting
during mining operations could be a significant potential hazard to low-flying
military aircraft using the general area for training exercises (although
this impact would end in approximately fourteen (14), rather than twenty (20),
years). The East Pit Alternative's impact on recreational use of the area,
including wilderness use, would be essentially identical in type, but slightly
reduced in scale and duration, from that of the Proposed Action, since the
East Pit Alternative would exclude recreational use over 1,276 acres
for approximately fourteen (14) years instead of 1,571 acres for
approximately twenty (20) years. These impacts would be below
the level of significance.
4.3.9.2. Mitigation Measures
Measures to ensure the compatibility of the East Pit Alternative with
existing land uses, adopted land use policies and plans, and recreational
use of the area would be the same as those measures identified for the Proposed
Action (see Section 4.1.9.2). With implementation of the identified
measures, the mitigated level of compatibility of the East Pit Alternative
with existing land uses, adopted land use policies and plans, and recreational
use of the area, would be below the level of significance.
4.3.10. Socioeconomics
4.3.10.1. Impacts of the East Pit Alternative
The East Pit Alternative would have a net beneficial socioeconomic effect
which would be reduced from the net beneficial socioeconomic effect of the
Proposed Action (see Section 4.1.10.2). These effects would
be below the level of significance. Although the number of jobs created
under the East Pit Alternative would be approximately the same as the Proposed
Action, the length of these jobs would be decreased from approximately twenty (20) years
to approximately fourteen (14) years. Initial capital expenditures
for (and thus sales taxes paid under) the East Pit Alternative would be
approximately the same as the Proposed Action. Recurrent, annual expenditures
(such as annual capital expenditures of approximately $1.7 million
(and $0.13 million in sales taxes), non-capital expenditures of approximately
$26 million, and property taxes of between $200,000 and $600,000) would
be reduced by approximately one-third (a) from that of the Proposed Action
because of the decreased operating life.
4.3.10.2. Mitigation Measures
No mitigation measures are proposed or recommended.
4.3.11. Roads and Public Services
4.3.11.1. Impacts of the East Pit Alternative
The East Pit Alternative would result in an essentially identical increase
in traffic as the Proposed Action (see Section 4.1.11.1.2),
except that the effects would occur for only fourteen (14), rather
than twenty (20), years. These effects would be below the level of
significance. The East Pit Alternative would not require the realignment
of Indian Pass Road, which would eliminate an impact otherwise judged below
the level of significance. The East Pit Alternative would also create the
potential for impacts from "spur" roads, which would be below
the level of significance.
The East Pit Alternative would have a similar impact on utilities as the
Proposed Action. Because of the reduced size of the project, less non-mining
waste would be generated (see Section 4.1.11.1.2). All impacts
on utilities would be below the level of significance. The East Pit Alternative
would also produce impacts on public services similar to the Proposed Action
(see Section 4.1.11.3.2). Because of the slightly reduced surface
area to be disturbed, there would likely be fewer cadastral monuments which
may be destroyed. These impacts would be below the level of significance.
4.3.11.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on roads, utilities and public services would be the same as those measures
identified for the Proposed Action (see Section 4.1.11.1.3,
Section 4.1.11.2.3, and Section 4.1.11.3.3). No other
measures would be necessary to reduce impacts of the East Pit Alternative
below the level of significance. The effects of the East Pit Alternative
on roads, utilities and public services would remain below the level of
significance.
4.3.12. Emergency Services and Public Safety
4.3.12.1. Impacts of the East Pit Alternative
The East Pit Alternative would have essentially identical impacts on
emergency services and public safety as would the Proposed Action (see Section 4.1.12.2),
although the life of the East Pit Alternative would be fourteen (14),
rather than twenty (20), years. The effects of the East Pit Alternative
on emergency services and public safety would be less than significant.
4.3.12.2. Mitigation Measures
Mitigation measures incorporated into the East Pit Alternative design
and incorporated by regulation which eliminate potentially significant effects
on emergency services and public safety would be the same as those measures
identified for the Proposed Action (see Section 4.1.12.3). No
other measures would be necessary to reduce impacts of the East Pit Alternative
below the level of significance. The effects of the East Pit Alternative
on emergency services and public safety would be below the level of significance.
4.3.13. Other Resources
4.3.13.1. Impacts of the East Pit Alternative
The East Pit Alternative would have essentially identical impacts on
other resources as would the Proposed Action (see Section 4.1.13),
although the life of the East Pit Alternative would be fourteen (14),
rather than twenty (20), years. The effects of the East Pit Alternative
on other resources would be less than significant.
4.3.13.2. Mitigation Measures
No mitigation measures are proposed or recommended.
4.4. Complete Pit Backfill Alternative
The Complete Pit Backfill Alternative would result in the complete backfilling
of all open pits, at least to original grade, concurrent with final reclamation
(see Section 2.2.3). It would consist of first implementing
the Proposed Action, then backfilling the East Pit with mined waste rock
material, which would be loaded back into haul trucks, driven to the edge
of the East Pit, and dumped into the pit until it is full. The Complete
Pit Backfill Alternative would use all of the waste rock available to completely
backfill all the mined pits, and leave all
of the heaped ore on the leach pad.
The Complete Pit Backfill Alternative would not result in any reduction
of the surface disturbance compared to the Proposed Action since the Complete
Pit Backfill Alternative begins with the implementation of the Proposed
Action. However, a substantial amount of the surface area disturbed by waste
rock stockpiles and the East Pit would be reclaimed "at grade"
because all the material in the waste rock stockpiles would be moved and
dumped into the open East Pit. It would take approximately 4.33 years (4 years,
4 months) beyond the end of mining to move enough waste rock back into
the East Pit to fill it to grade, although this would likely be accomplished
during the twenty (20)-year life of the Proposed Action, while neutralization
of the heap and final reclamation were being completed.
4.4.1. Geology and Mineral Resources
4.4.1.1. Impacts of the Complete Pit Backfill
Alternative
Except for the complete backfilling of the East Pit, there would be no
substantive difference in the impacts of the Complete Pit Backfill Alternative
on geology and mineral resources from those identified for the Proposed
Action (see Section 4.1.1.2). Under the Complete Pit Backfill
Alternative, potential mineral resources exposed at the bottom of the East
Pit which are not commercially minable under current economic conditions
would be unavailable for subsequent mining without potentially cost-prohibitive
removal of the backfilled waste rock. The effects of the Complete Pit Backfill
Alternative on geology and mineral resources would be below the level of
significance.
4.4.1.2. Mitigation Measures
Mitigation measures incorporated into the Complete Pit Backfill Alternative
design and incorporated by regulation which eliminate potentially significant
effects on geology and mineral resources would be the same as those identified
for the Proposed Action (see Section 4.1.1.3). No other measures
would be necessary to reduce impacts of the Complete Pit Backfill Alternative
below the level of significance. The effects of the Complete Pit Backfill
Alternative on geology and mineral resources would remain below the level
of significance.
4.4.2. Soil Resources
4.4.2.1. Impacts of the Complete Pit Backfill
Alternative
The impacts of the Complete Pit Backfill Alternative on soil resources
would be essentially the same as the Proposed Action (see Sectio 4.1.2.2),
except that with the complete backfilling of the East Pit with all of the
waste rock from the South Waste Rock Stockpile, the potential for erosion
within the Project area would decrease slightly. The effects of the Complete
Pit Backfill Alternative on soil resources would be below the levels of
significance.
4.4.2.2. Mitigation Measures
Mitigation measures incorporated into the Complete Pit Backfill Alternative
design and incorporated by regulation which eliminate potentially significant
effects on soil resources would be the same as those identified for the
Proposed Action (see Section 4.1.2.3). No other measures would
be necessary to reduce impacts of the Complete Pit Backfill Alternative
below the level of significance. The effects of the Complete Pit Backfill
Alternative on soil resources would remain below the level of significance.
4.4.3. Hydrologic Resources
4.4.3.1. Impacts of the Complete Pit Backfill
Alternative
The effects of the Complete Pit Backfill Alternative on surface and ground
water resources would be generally the same as the effects of the Proposed
Action (see Section 4.1.3.1.2 and Section 4.1.3.2.2).
Any analysis of pit lake potential after mining (as described under the
Proposed Action) would be unnecessary. All impacts on hydrologic resources
of the Complete Pit Backfill Alternative would be below the level of significance.
4.4.3.2. Mitigation Measures
Mitigation measures incorporated into the Complete Pit Backfill Alternative
design and incorporated by regulation which eliminate potentially significant
effects on surface water and ground water resources would be the same as
those identified for the Proposed Action (see Section 4.1.3.1.3
and Section 4.1.3.2.3), except that the measures regarding the
formation of a pit lake would be unnecessary. No other measures would be
necessary to reduce impacts of the Complete Pit Backfill Alternative below
the level of significance. The effects of the Complete Pit Backfill Alternative
on surface water and ground water resources would remain below the level
of significance.
4.4.4. Air Resources
4.4.4.1. Impacts of the Complete Pit Backfill
Alternative
The impacts of the Complete Pit Backfill Alternative on air resources
would be essentially identical to the impacts to air resource from the Proposed
Action (see Section 4.1.4.2), except that those impacts associated
with loading, hauling and dumping would continue after the completion of
mining for another approximately 4.33 years as the waste rock was backfilled
into the East Pit. The effects of the Complete Pit Backfill Alternative
on air resources would be below the level of significance except for PM10.
Although the effects of the Complete Pit Backfill Alternative would be below
the level of significance, the Complete Pit Backfill Alternative would still
contribute to exceedences of the 24-hour CAAQS
for PM10 which may continue to occur in the future during periods
of high wind. This would remain a cumulatively significant effect.
4.4.4.2. Mitigation Measures
Mitigation measures incorporated into the Complete Pit Backfill Alternative
design and incorporated by regulation which eliminate potentially significant
effects on air resources would be the same as those identified for the Proposed
Action (see Section 4.1.4.3). No other measures are proposed
to reduce impacts of the Complete Pit Backfill Alternative below the level
of significance. The effects of the Complete Pit Backfill Alternative on
air resources would remain below the level of significance except for PM10.
Although the effects of the Complete Pit Backfill Alternative would be mitigated
to below the level of significance, the Complete Pit Backfill Alternative
would still contribute to exceedences of the 24-hour CAAQS
for PM10 which may continue to occur in the future during periods
of high wind. This would remain a cumulatively significant effect.
4.4.5. Biological Resources
4.4.5.1. Impacts of the Complete Pit Backfill
Alternative
Vegetation and Plant Habitat
The impacts of the Complete Pit Backfill Alternative on vegetation and plant
habitat would be essentially identical to those under the Proposed Action.
The same amount of surface disturbance would occur as under the Proposed
Action. The time required to complete final reclamation would likely remain
the same, and the other impacts to vegetation and plant habitat (from dust,
ground water pumping, surface channel diversions, and sensitive plants)
would also be essentially identical to those of the Proposed Action (see
Section 4.1.5.2), and would remain below the level of significance.
The amount of surface area not reclaimed (pit slopes not covered by backfill) would decrease from 165 acres
under the Proposed Action to zero (0).
Wildlife, Wildlife Habitat and Wildlife Movement
The amount of wildlife habitat lost under the Complete Pit Backfill Alternative
would be the same as that under the Proposed Action. Most of this habitat
loss would be temporarily, until the completion of final reclamation (and
subsequent vegetation recovery). However, it is likely that a somewhat larger
percentage of the disturbed microphyll woodland habitat would be able to
be reclaimed within the Project mine and process area as microphyll woodland
habitat than the approximately one-half (2) reclaimed under the Proposed
Action because more of the land is being reclaimed at approximately natural
grade. There would be no open pit slopes which would not be reclaimed, and
there would be no open pit area over which wildlife could be killed or injured
by falls or from opportunistic. These impacts would be below the level of
significance.
The Complete Pit Backfill Alternative would expose wildlife and wildlife
habitat to the same impacts from vehicles, hazardous materials, noise, human
presence, etc., as the Proposed Action. These effects would be below the
level of significance. Other impacts from the Complete Pit Backfill Alternative
on wildlife and wildlife habitat (from ground water pumping, surface channel
diversions, and sedimentation) would also be essentially identical to those
of the Proposed Action (see Section 4.1.5.3). They would also
remain below the level of significance.
The impacts of the Complete Pit Backfill Alternative on the desert tortoise
would be the same as the Proposed Action, and would be above the level of
significance.
4.4.5.2. Mitigation Measures
Measures to reduce the effects of the Complete Pit Backfill Alternative
on biological resources would be the same as those measures identified for
the Proposed Action (see Section 4.1.5.4), except that the measures
to reclaim off-site lands for lands not reclaimed on-site and to backfill the East Pit to prevent the formation of
a pit lake are unnecessary. With implementation of the identified measures,
the mitigated effects of the Complete Pit Backfill Alternative on biological
resources would be below the level of significance.
4.4.6. Cultural and Paleontological Resources
4.4.6.1. Impacts of the Complete Pit Backfill
Alternative
The Complete Pit Backfill Alternative would result in impacts on cultural
resources which are identical to those created by the Proposed Action (see
Section 4.1.6.2), except that following backfilling of the East
Pit and final reclamation, the visual intrusion into the Indian Pass-Running
Man ATCC would be somewhat reduced. The Complete
Pit Backfill Alternative would still have a significant adverse impact on
cultural resources eligible for the NRHP, and on the Indian Pass-Running
Man ATCC.
4.4.6.2. Mitigation Measures
Measures to reduce the significant effects of the Complete Pit Backfill
Alternative on cultural resource features identified within the overbuilt
92 kV/34.5 kV transmission line corridor, or within the Project
area, which were determined eligible for the NRHP under criterion "D"
would be identical to those identified for the Proposed Action. The mitigated
impacts would be reduced below the level of significance. Measures to reduce
the significant effects of the Complete Pit Backfill Alternative on cultural
resource features determined eligible for the NRHP under criteria "A",
"B," or "C" which were identified within the Complete
Pit Backfill Alternative project area, or to reduce the significant effects
of the Complete Pit Backfill Alternative on the Indian Pass-Running Man
ATCC, would be identical to those identified
for the Proposed Action. The mitigated effects of these impacts would remain
above the level of significance and be unavoidable.
4.4.7. Visual Resources
4.4.7.1. Impacts of the Complete Pit Backfill
Alternative
The effect of the Complete Pit Backfill Alternative on visual resources
from the lighting of mine and process areas and visibility reduction from
the emission of dust would be identical to the Proposed Action (see Section 4.1.7.2).
These effects would be above the level of significance from mine and process
area lighting, and less than significant from visibility reduction.
The visual contrasts of the Complete Pit Backfill Alternative created by
changes in line and form from the creation of new structures and facilities,
altered surface colors, textures and vegetation cover, and changes in topography
would differ in both degree and extent from the Proposed Action because
of the backfilling of the East Pit with all of the waste rock from the waste
rock stockpiles. When viewed from KOP #1 (Ogilby Road) or from KOP #4
(the informal overnight camping area), the Complete Pit Backfill Alternative
would look like the view of the Proposed Action from the same point (see
Figure 4.3 and Figure 4.9), except that only the
heap would be visible, since the entire South Waste Rock Stockpile would
have been removed to backfill the East Pit.
The view of the Project mine and process area from KOP #2 (Black Mountain)
and from KOP #3 (a hill south of Indian Pass in the Picacho Peak Wilderness
Area) following the completion of final reclamation under the Complete Pit
Backfill Alternative would differ more from the Proposed Action because
of the backfilling of all of the pits and the elimination of all of the
waste rock stockpiles (see Figure 4.14 and Figure 4.15).
Because the heap would remain as a large alteration in the topography, the
effect of the Complete Pit Backfill Alternative on visual resources would
be above the level of significance.
4.4.7.2. Mitigation Measures
Mitigation measures incorporated into the Complete Pit Backfill Alternative
design which eliminate potentially significant effects on visual resources
would be the same as those identified for the Proposed Action (see Section 4.1.7.3).
Measures to reduce the significant effects of the Complete Pit Backfill
Alternative on lighting would also be the same as those measures identified
for the Proposed Action. With implementation of the identified measures,
the mitigated effects of the Complete Pit Backfill Alternative on visual
resources from visibility reduction and lighting would be below the level
of significance. The mitigated effects of the Complete Pit Backfill Alternative
on visual resources from changes in line and form would remain above the
level of significance.
4.4.8. Noise
4.4.8.1. Impacts of the Complete Pit Backfill
Alternative
Noise generated by the Complete Pit Backfill Alternative would be essentially
identical to the noise generated by the Proposed Action, and the effects
of this noise on potential noise receptors would also be essentially identical
as for the Proposed Action (see Section 4.1.8.2). However, the
Complete Pit Backfill Alternative would also continue the relatively greater
noise-producing operations (loading, hauling, and dumping, but not blasting)
for approximately 4.33 years longer than the Proposed Action. The impacts
of noise from the Complete Pit Backfill Alternative would be below the levels
of significance.
4.4.8.2. Mitigation Measures
Mitigation measures incorporated into the Complete Pit Backfill Alternative
design and incorporated by regulation which eliminate potentially significant
effects of noise would be the same as those identified for the Proposed
Action (see Section 4.1.8.3). No other measures would be necessary
to reduce impacts of the Complete Pit Backfill Alternative below the level
of significance. The noise effects of the Complete Pit Backfill Alternative
would remain below the level of significance.
4.4.9. Land Use
4.4.9.1. Impacts of the Complete Pit Backfill
Alternative
The compatibility of the Complete Pit Backfill Alternative with existing
land uses and adopted land use policies and plans would be essentially identical
to that of the Proposed Action (see Section 4.1.9.2). Blasting
during mining operations could be a significant potential hazard to low-flying
military aircraft using the general area for training exercises. The Complete
Pit Backfill Alternative's impact on recreational use of the area, including
wilderness use, would be essentially identical to that of the Proposed Action.
These impacts would be below the level of significance.
4.4.9.2. Mitigation Measures
Measures to ensure the compatibility of the Complete Pit Backfill Alternative
with existing land uses, adopted land use policies and plans, and recreational
use of the area would be the same as those measures identified for the Proposed
Action (see Section 4.1.9.2). With implementation of the identified
measures, the mitigated level of compatibility of the Complete Pit Backfill
Alternative with existing land uses, adopted land use policies and plans,
and recreational use of the area, would be below the level of significance.
4.4.10. Socioeconomics
4.4.10.1. Impacts of the Complete Pit Backfill
Alternative
The Complete Pit Backfill Alternative would have the same beneficial,
less-than-significant socioeconomic effects as the Proposed Action (see
Section 4.1.10.2). In addition, to complete the backfilling
of the East Pit, additional wages, purchases of fuel, replacement equipment
and maintenance, and other goods and services would be required, and this
would be additional money placed into the economy. These additional costs
have been estimated, using a conservative industry average of $0.40 to
$0.50 per ton of material loaded, hauled and dumped, at between $80 and
$100 million. The level of economic effect would remain less than significant.
4.4.10.2. Mitigation Measures
No mitigation measures are proposed or recommended.
4.4.11. Roads and Public Services
4.4.11.1. Impacts of the Complete Pit Backfill
Alternative
The Complete Pit Backfill Alternative would result in essentially identical
increases in traffic and realignment of Indian Pass Road as the Proposed
Action (see Section 4.1.11.1.2). The effects would be below
the level of significance. The Complete Pit Backfill Alternative would also
create the potential for impacts from "spur" roads, which would
be below the level of significance.
The Complete Pit Backfill Alternative would have an essentially identical
impact on utilities as the Proposed Action (see Section 4.1.11.1.2).
All impacts on utilities would be below the level of significance. The Complete
Pit Backfill Alternative would also have similar impact on public services
as the Proposed Action (see Section 4.1.11.3.2). These impacts
would be below the level of significance.
4.4.11.2. Mitigation Measures
Mitigation measures incorporated into the Complete Pit Backfill Alternative
design and incorporated by regulation which eliminate potentially significant
effects on roads, utilities and public services would be the same as those
measures identified for the Proposed Action (see Section 4.1.11.1.3,
Section 4.1.11.2.3, and Section 4.1.11.3.3). No
other measures would be necessary to reduce impacts of the Complete Pit
Backfill Alternative below the level of significance. The effects of the
Complete Pit Backfill Alternative on roads, utilities and public services
would remain below the level of significance.
4.4.12. Emergency Services and Public Safety
4.4.12.1. Impacts of the Complete Pit Backfill
Alternative
The Complete Pit Backfill Alternative would have similar impacts on emergency
services and public safety as the Proposed Action (see Section 4.1.12.2).
Because the East Pit would be completely backfilled, the potential public
safety concerns from the open East Pit would be eliminated. The effects
of the Complete Pit Backfill Alternative on emergency services and public
safety would be less than significant.
4.4.12.2. Mitigation Measures
Mitigation measures incorporated into the Complete Pit Backfill Alternative
design and incorporated by regulation which eliminate potentially significant
effects on emergency services and public safety would be the same as those
measures identified for the Proposed Action (see Section 4.1.12.3),
except that no measures would be necessary to barricade any open pits. No
other measures would be necessary to reduce impacts of the Complete Pit
Backfill Alternative below the level of significance. The effects of the
Complete Pit Backfill Alternative on emergency services and public safety
would be below the level of significance.
4.4.13. Other Resources
4.4.13.1. Impacts of the Complete Pit Backfill
Alternative
The Complete Pit Backfill Alternative would have essentially identical
impacts on other resources as would the Proposed Action (see Section 4.1.13).
The effects of the Complete Pit Backfill Alternative on other resources
would be less than significant.
4.4.13.2. Mitigation Measures
No mitigation measures are proposed or recommended.
4.5. No Action Alternative
Under the No Action Alternative, the Proposed Action would not be constructed,
and precious metals within the Project mine and process area not be mined
under the submitted Plan of Operations. As discussed in Section 2.2.4,
if the No Action Alternative is adopted, the Project area would remain as
it currently is, and existing dispersed recreational and other uses of the
Project area would continue.
4.5.1. Geology and Mineral Resources
No adverse impacts on geology or mineral resources would result from
the No Action Alternative, and the identified precious mineral resources
would remain in place pending other proposals for development.
4.5.2. Soil Resources
No adverse impacts on soil resources in the Project area would result
from implementation of the No Action Alternative.
4.5.3. Hydrologic Resources
No adverse impacts on surface water or ground water resources would result
from implementation of the No Action Alternative.
4.5.4. Air Resources
Local exceedences of the CAAQS for PM10
have occured in the past, and may continue in the future, during periods
of high winds, even with implementation of the No Action Alternative. This
would be a cumulatively significant effect.
4.5.5. Biological Resources
No adverse impacts on biological resources would result from implementation
of the No Action Alternative.
4.5.6. Cultural and Paleontological Resources
No adverse impacts on cultural or paleontological resources would result
from implementation of the No Action Alternative.
4.5.7. Visual Resources
No adverse impacts on visual resources would result from implementation
of the No Action Alternative.
4.5.8. Noise
No adverse noise impacts would result from implementation of the No Action
Alternative.
4.5.9. Land Use
The existing land use within, and in the vicinity of, the Project area
would likely continue under the No Action Alternative.
4.5.10. Socioeconomics
The No Action Alternative would not create the 120 job opportunities,
nor the estimated $7 million in annual payroll, from the Proposed Action.
The No Action Alternative would result in the loss of the $48 million
initial capital expenditures, $1.7 million annual capital expenditures,
and the $26 million per year non-capital expenditures and associated
taxes and benefits to the local economy projected by the Project.
4.5.11. Roads and Public Services
No adverse impacts on roads, utilities, or public services from implementation
of the No Action Alternative.
4.5.12. Emergency Services and Public Safety
No adverse impacts on emergency services or public safety would result
from implementation of the No Action Alternative.
|