4. ENVIRONMENTAL CONSEQUENCES AND MITIGATION MEASURES
4.1. Proposed Action
4.1.1. Geology and Mineral Resources
4.1.1.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Expose people or structures to major geologic hazards; or
- Substantially restrict the future ability to utilize mineral resources.
4.1.1.2. Impacts of the Proposed Action
Slope Stability and Seismic Effects:
Seismic review of regional faults (active and potentially active) has indicated
maximum credible earthquake magnitudes of 5.8 to 7.5 (see Table 4.1). However, because of the distance
from each of these faults to the Project mine and process area; the nature
of the underlying geologic units; and the depth to ground water; regional
seismicity is not expected to cause substantial horizontal accelerations
or extensive ground shaking within the Project area.
The proposed slope configurations for the leach pad ore heap (2H:1V, including
benches) are similar to those used at nearby mining operations, at which
no substantial slumping or slope failure has occurred. Stability analyses
completed for the planned heaps and waste rock stockpiles (WESTEC, Inc.
1996b) also indicate that the proposed slope of the heap and waste rock
stockpiles would be stable and unlikely to produce substantial failures,
including landslides, either under normal operating conditions or from ground
shaking during regional seismic events.
Preliminary pit slope recommendations prepared for the East Pit and West
Pit contained slope angles ranging from 40E to 55E, with circular failure
and/or non-daylighting wedge failure potential within the pits controlling
most of the slope angles (WESTEC, Inc. 1997). Experience at nearby mines
indicates that the proposed final pit wall slope of 1H:1.2V (50 degrees),
constructed in cemented alluvium/gravels and metamorphic rock, would provide
the required factor of safety for long-term slope stability, including the
vibrations from blasting and ground shaking from anticipated seismic events
in the region. The proposed pit wall design includes safety benches at regular
vertical intervals to contain minor rock falls. The waste rock stockpile
slope configurations would also be similar to those used at the Picacho
Mine. No substantial slumping or slope failure is anticipated; however,
the preliminary pit slope report recommended re-evaluation once mining operations
commenced and more data was available.
Table 4.1
| Fault or Fault Zone |
Distance and Direction
from Project Area
(miles/direction) |
Maximum Probable Magnitude |
Effects at Project Area |
| Maximum Probable Peak Acceleration (g)a |
Duration of Strong Ground Shaking (seconds) |
| East Mesa |
29/West |
6.0 |
0.17 |
18 |
| East Highline Canal Lineament |
32/West |
6.0 |
0.09 |
18 |
| Imperial/Brawley |
42/Southwest |
6.8 |
0.07 |
24 |
| Brawley Seismic Zone |
44/West |
5.8 |
0.04 |
18 |
| Superstition Hills |
55/West |
7.0 |
0.05 |
30 |
| San Andreas |
63/Northwest |
7.5 |
0.04 |
36 |
| Elsinore |
77/Southwest |
7.0 |
0.03 |
30 |
aSource: Joyner and Fumal 1986 (In: Environmental Solutions,
Inc. 1993b.)
Because of the great depth to ground water, and the design of the heap
leach pad, which prevents the accumulation of standing water within the
heap, there is very little potential for any liquifaction, and no significant
effects are anticipated.
Project structures would be designed and constructed subject to the current
Uniform Building Code (UBC) Seismic Zone 4 standards, which are
the most stringent in the UBC. Implementation of Seismic Zone 4 standards
would conform to the current Building Code Requirements of the Imperial
County Planning/Building Department, and prevent catastrophic failure of
facilities which could endanger human life during seismic events. Therefore,
impacts to Project facilities from remote seismic events would not be significant.
No surface ruptures are anticipated from seismic activity because there
are no known or currently identified active faults within the Project area.
Mining of the proposed pits would not be expected to affect either the physical
geology of known faults in the region or regional seismicity. No significant
effects are anticipated.
Subsidence:
No land surface subsidence due to the extraction of ground water from the
ground water production wells is expected. Generally, land surface subsidence
related to ground water extraction occurs only when the drawdown of the
ground water table is large or results
in a substantial pressure reduction in a confined aquifer;
or a substantial percentage of the earth materials forming the aquifer are fine-grained (silts or clays); or the
depth from the surface of the land to the water
table is small. Because the amount of ground water the Project proposes
to extract is not large compared to the size of the aquifer
or the amount of water in storage (see Section 4.1.3.2.2); because
the sediments in the ground water production area are relatively coarse
alluvial materials; and because the depth to ground water is greater than
500 feet below ground surface (bgs), measurable
subsidence is not expected to occur as a result of the production of ground
water. If subsidence were to occur, it would be localized and not adversely
affect any Project facilities or natural or other man-made features. The
wells, water pipeline, and electrical transmission and distribution lines
can each tolerate localized subsidence. There are also no other existing
or planned developments or natural features in the immediate vicinity of
the ground water production wells which could be adversely affected by localized
subsidence. Thus, the impact of any subsidence which may occur would be
below the level of significance.
Naturally Occurring Radioactive Materials:
Materials to be mined by the Project have not been analyzed for naturally
occurring radioactive materials (NORM). However, some analyses from the
general area for radon gas and uranium and thorium in soils have been conducted
and can be used as an indication of the relative amount of NORM in the Project
mine and process area. In 1990 the California Department of Health Services
(CDHS) conducted an initial phase radon survey by placing short-term radon
detectors in approximately 2,858 randomly selected homes (CDHS 1990).
Two samples were collected from homes in the Brawley area of Imperial Valley,
the results of which indicated radon isotope-222 levels of 1.8 and
1.1 picocuries per liter (pCi/l) of air. These values are substantially
below the USEPA recommended level of 4.0 pCi/l at which action should
be taken to reduce radon levels. The mining of the proposed West Pit, Singer
Pit, and East Pit is not expected to substantially increase the release
of naturally occurring radon gas into the atmosphere.
Within an approximately fifteen (15)-mile radius of the Project mine
and process area, approximately 37 soil samples were collected as part
of the national uranium resource evaluation (NURE) (Hoffman, et al. 1991).
The uranium values from these soil samples range from 2.2 to 4.4 ppm,
and average 3.0 ppm. The average crustal abundance of uranium is 2.5 ppm
(Rose, et al. 1979). The thorium values from the same soil samples range
from 4.0 to 21.0 ppm, and average 10.67 ppm. The average
crustal abundance of thorium is 10 ppm. In the immediate vicinity of
the Project area, two (2) soil samples were collected. The uranium
values from these two (2) soil samples are 2.2 and 3.0 ppm,
which produce an average of 2.6 ppm. The thorium values from the same
two (2) soil samples were 5.0 and 16.0 ppm, which produces
an average of 10.5 ppm. Using the radon values in comparison to the
USEPA recommended action level, and the uranium and thorium values in comparison
to the average crustal abundance of those elements, neither the Project
area nor the vicinity appears to have elevated levels of radioactive elements
and, therefore, elevated NORM levels would not likely be expected to be
produced by operations within the Project mine and process area. These impacts
would be below the level of significance.
Loss of Mineral Potential:
Condemnation drilling by Glamis Imperial geologists has been used to determine
the limits of the gold ore bodies within the Project mine and process area.
The results of this drilling, to date, indicate that valuable mineral resources
common to the Project mine and process area do not exist in the areas of
the proposed heap pad, waste rock stockpiles, and the process and ancillary
facilities. Therefore, no potentially valuable mineralization would be buried
by the placement of these facilities in these areas.
Backfilling of the West Pit would result in the burial, and thus likely
loss, of some mineral resources since there is some mineralization at the
bottom of the West Pit which would not be mined under the Proposed Action.
However, as shown in Figure 3.2, this mineralization is dipping
steeply to the west, and any mining would produce substantially greater
quantities of waste rock per ton of ore than is currently economic under
the Proposed Action. Thus, mining of this mineralization is very unlikely
to ever be economic, and its loss would not be significant.
Some mineralization would also be left in some locations at the bottom of
the East Pit following the completion of mining under the Proposed Action.
Since the East Pit would only be partially backfilled, if necessary, to
the level needed to raise the floor to the predicted level of any pit lake,
the costs of mining this mineralization below the current limits of the
Proposed Action under some future Plan of Operations would increase only
slightly over that of leaving the East Pit completely open. This decrease
in the economic value of the mineralization in the East Pit from partially
backfilling would not be significant.
4.1.1.3. Measures Incorporated by Project Design
and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.1-1: Heap leach pad and waste rock stockpile slopes shall be constructed
at overall slopes no steeper than 2H:1V.
- 4.1.1-2: Mine pit slopes shall be constructed at overall slopes no
steeper than 1H:1.2V (50 degrees) unless mining conditions and geotechnical
factors demonstrate through engineering analysis that steeper slopes would
be safe, and such steeper slopes shall be approved by the BLM.
Slopes shall not be steeper than is safe considering actual rock strength
and structural conditions encountered. Pit slope angles in the West Pit
and East Pit shall be re-evaluated after one (1) year of mining of that
pit.
- 4.1.1-3: Approximately 40-foot wide benches shall be constructed at
approximately 80-foot high intervals on mine pit slopes to catch loose
rocks. Approval shall be obtained from the BLM
prior to construction of mine pit benches which differ substantially from
these specifications.
- 4.1.1-4: To avoid any substantial slumping or slope failure of the
heap and waste rock stockpile slopes, the recommendations of the slope
stability analyses of these facilities shall be followed during the construction
of these facilities.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.1-5: Project structures subject to the Uniform Building Code shall
be designed and constructed consistent with the standards of Seismic Zone 4.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
No mitigation measures are proposed or recommended.
4.1.1.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
There would be no unavoidable adverse effects to geology from implementation
of the Proposed Action. The goal of the Proposed Action is to mine precious
metal mineral resources for beneficial use.
The effects of the Proposed Action on geology or mineral resources would
be below levels of significance.
4.1.2. Soil Resources
4.1.2.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Cause substantial erosion.
4.1.2.2. Impacts of the Proposed Action
Approximately 1,302 acres would be disturbed within the Project
mine and process area, 38 acres within the Project ancillary area,
and 22 acres within the overbuilt 92 kV/34.5 kV transmission
line corridor as part of the Proposed Action. Soils within the Project mine
and process area are poorly-developed gravelly sands, and only a thin covering
of soil is present for Project reclamation and revegetation. Approximately
112,200 cubic yards of soil would be salvaged from all washes and areas
where sufficient soil development is noted. Soils would be salvaged to the
greatest depth practicable (generally 12 to 18 inches) and stockpiled
for later use during reclamation activities. Soils would be stockpiled at
two (2) proposed sites within the Project mine and process area (see
Figure 2.2). The soil stockpiles would be clearly identified
with signs to assure that the material was not misidentified as waste rock
material. The gravelly nature of the soils would minimize erosion by wind
and rain.
Many of the soils in the Project area, and many of the Project facilities
themselves (such as the soil stockpiles, waste rock stockpiles, and heap,
etc.), may be subject to erosion, either from precipitation falling directly
within the Project area or from flow events in the ephemeral washes. To
minimize erosion, Glamis Imperial has indicated that all Project facilities
(including the heap leach facility, waste rock stockpiles, soil stockpiles,
and roads) would be designed and constructed with erosion control features
engineered to meet the performance standards at 14 CCR 3706 (see
Section 2.1.11.2.3). The Project would also be required to be
constructed and operated in accordance with a Storm Water Pollution Prevention
Plan (SWPPP), which requires the use of Best Management Practices for erosion
control, in accordance with the California Storm Water National Pollution
Discharge Elimination System (Storm Water NPDES) permit program (California
Water Code Section 13000 et seq.).
Surface runoff and drainage from disturbed areas within the Project mine
and process area would be controlled, collected, conveyed to sediment basins,
and infiltrated (or consumed in the mining or heap leach process). Any areas
which might be susceptible to erosion from surface flows would be protected
through the use of berms, sediment ponds, rip rap, check dams composed of
sand bags, silt fences, or other techniques to prevent erosion and potential
damage. These erosion control features would be in areas currently proposed
for disturbance. Erosion control methods would be designed to handle at
least a 20-year/1-hour intensity storm event, in accordance with standards
established by 14 CCR 3706(d) (SMARA regulations). Modifications
to the erosion control methods would be made as necessary over the life
of the Project. As a result, substantial erosion would not be created and
the impacts of erosion would not be significant.
Several ephemeral drainages would be permanently diverted around the Project
facilities within the Project mine and process area. Rip rap would be placed
along the channel banks to prevent erosion. Each diversion would channel
the flow into the same major wash, or into another existing wash which was
tributary to the same major wash, thus putting all flow back into the same
drainage system. Diversion channels would also be built to approximate the
original drainage system in both gradient and channel geometry, and would
be designed to convey all runoff flows from the 100-year 24-hour, 100-year
6-hour, and 500-year 24-hour precipitation events. This would minimize changes
in the hydraulic characteristics of the channel and minimize the potential
to increase any erosion from the diversion of the wash. Erosion impacts
from the diversion of the ephemeral stream channels would not be significant.
Because the washes which flow through the Project mine and process area
continue downgradient to the southwest until each eventually ends in individual
areas of infiltration on the eastern edge of the Algodones Sand Dunes (see Figure 3.18),
there would be no impacts from erosion, sedimentation, or diversion of ephemeral
stream channels on any areas outside of the "Indian Wash Drainage Basin,"
including the Fort Yuma Indian Reservation or the "Picacho Wash Drainage
Basin" in which the Fort Yuma Indian Reservation sits.
Because of the minimal amount, depth, and length of time of the surface
disturbance associated with activities to be conducted within the Project
ancillary area and the overbuilt 92 kV/34.5 kV transmission line
corridor, there is little chance of any substantial erosion. This would
be a less-than-significant effect.
4.1.2.3. Measures Incorporated by Project Design
and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.2-1: Surface disturbance shall be kept to the minimum that is required
to construct and operate the project.
- 4.1.2-2: Soils shall be salvaged from all areas where sufficient soil
development is noted in conformance with the approved Reclamation Plan.
Soils shall be salvaged to the greatest depth practicable and placed in
stockpiles clearly delineated with signs to assure the material is not
mistaken as waste rock. Soil stockpiles shall be located away from washes
and other areas prone to erosion and consolidated as appropriate to reduce
disturbance to undisturbed areas within the Project mine and process area.
Stockpiles shall be kept shallow and dry, if not to be used within one
(1) year of initial placement, to protect seeds.
- 4.1.2-3: All mine facilities shall be designed and constructed with
erosion control features engineered to meet the performance standards of
14 CCR 3706, including the control of runoff and protection of
areas susceptible to erosion from surface flows.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.2-4: A Storm Water Pollution Prevention Plan, incorporating the
use of Best Management Practices for erosion control, shall be developed
and implemented in accordance with the California Storm Water NPDES permit
program.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
No other mitigation measures are proposed or recommended.
4.1.2.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
Implementation of the Proposed Action would result in the unavoidable
loss of those minor amounts of soils which cannot be salvaged during construction.
Based upon regulatory requirements and mitigation measures that have been
incorporated into the Project design, effects of the Proposed Action on
soil resources would be below level of significance.
4.1.3. Hydrologic Resources
4.1.3.1. Surface Waters
4.1.3.1.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Substantially degrade water quality;
- Contaminate a public water supply;
- Cause substantial flooding or siltation; or
- Substantially alter surface flow conditions, patterns, or rates.
4.1.3.1.2. Impacts of the Proposed Action
In addition to other changes, this section has been modified from the
November 1996 Draft EIR in response to comments to: include a discussion
of flood zones; and add a new delineation of "waters of the United
States" impacted by the Proposed Action.
Stream Flow Alterations:
The Proposed Action would include the diversion of segments of five (5)
existing ephemeral watercourses, and the permanent filling or excavation
of tributaries of these watercourses. All diversions divert water entering
the Project mine and process area to other segments of these same washes,
which then flow naturally through or around the Project mine and process
area (see Figure 2.9).
Although these diversions result in a substantial alteration to surface
water drainage patterns within the Project mine and process area, each diversion
would channel the flow directly into another existing wash which was tributary
to the same major watercourse. All other storm water surface flows entering
the Project mine and process area which would not otherwise impact Project
facilities would flow through the Project mine and process area. Each of
the diversion channels has been designed to safely convey all runoff flows
from the 100-year, 6-hour precipitation event, which satisfies the siting
requirements for mining waste management units (23 CCR 2572(b))
and exceeds the recommended design values for diversions and drainage facilities
around mining waste management units as prescribed in 23 CCR 2572(h)(1)(C).
Because there is some potential for flash flooding from thunder storms,
the diversion channels have also been designed with an additional "flood
bench" area immediately adjacent to the main channel so that the channel
and "flood bench" together can easily accommodate the 500-year,
24-hour storm flow (see Figure 2.10). Each of the diverted channels
directs flows around the mining facilities and back into the same major
drainage system from which it was diverted (see Figure 2.9).
Thus, all flows would continue in the same channels outside of the Project
mine and process area, and there would be no substantial alteration of stream
flows or patterns outside of the Project mine and process area. The impacts
resulting from these alterations are below the level of significance
Precipitation falling on undisturbed portions of the Project mine and process
area would be allowed to collect and flow through the area as before construction
of the Project. Precipitation falling within the open pit boundaries would
collect on, or infiltrate through, pit floors, thus reducing potential storm
water runoff from the Project compared to the existing desert floor. Precipitation
falling on the heap leach pad or within the pregnant or barren ponds would
also remain within this closed hydrologic system. Depending on the porosity
and permeability of the mine facility and the intensity of the precipitation,
storm water runoff may be delayed (such as from rain falling on the porous
waste rock stockpiles) or accelerated (such as from the relatively impervious
roads). Regardless of the effect, because the Project mine and process area
facilities which may accelerate, delay, or "capture" precipitation
are such a minor percentage of the overall surface area of the drainage
basins in which they are located, only a very minor delay, acceleration,
or reduction in storm water flow in the major washes downstream of the Project
mine and process area would result from the Project activities. Minor, ephemeral
tributaries which are truncated by certain Project facilities (such as the
heap leach pad) would have a reduction on runoff flow, although this flow
reduction is not considered substantial and therefore would not be significant.
Surface runoff and drainage resulting from precipitation falling on the
waste rock stockpiles, soil stockpiles, or on project roads and other disturbed
areas within the Project mine and process area would be controlled using
a number of Best Management Practices (BMPs).
Among the methods of control would be collection and detention in sediment
basins. Evaporation and infiltration would occur in the sediment basins,
further reducing the potential for downstream sedimentation. If excess water
is captured, it may be utilized in the mining, dust control, or heap leach
processes. Based on experience at the Picacho Mine, it is expected that
insignificant quantities of storm water would leave the Project mine and
process area. The specific details of storm water management would be documented
in a SWPPP, which would be prepared after approval of the Project mine,
and implemented when the facility begins operations. This SWPPP would be
a public document maintained on the Project mine and process area. Storm
water flows would not result in a significant impact.
Stream Sedimentation and Quality Degradation:
The principal throughgoing stream channels appear to be undergoing very
little geomorphic change (EMA 1996a). There is a potential for the erosion
of materials from the Project soil stockpiles, waste rock stockpiles, and
other Project facilities into the washes due to overland storm flow or from
erosion by flows in the washes themselves during major precipitation events.
Substantial erosion of Project facilities could result in substantial discharge
of sediment into the watercourses, which could lead to the deposition of
substantial sediment in these watercourses downstream of the Project mine
and process area, and which could damage or bury the vegetation in the washes.
Areas most susceptible to erosion, and thus, the production of sediment,
would be steep, loose, waste rock or soil stockpile slopes adjacent to the
major throughgoing watercourses; the outside banks of major turns in the
washes, and the "at grade" haul and maintenance road crossings
of the major stream channels within the Project mine and process area (and
the two (2) "at grade" crossings of the western-most wash
adjacent to the Project mine and process area by the relocated Indian Pass
Road).
Best management practices to reduce the potential for erosion have been
incorporated into the Proposed Action (see Section 2.1.11.2.3
and Section 4.1.2.3) which would also substantially reduce the
potential for sedimentation in the ephemeral stream channels. These include
placing rip rap on the outside bends of diverted stream channels, providing
setbacks of facilities (such as the waste rock stockpiles) from the banks
of throughgoing washes, placing berms around facilities as appropriate,
and installing sediment basins around the facility designed to capture run
off from the 100-year, 24-hour storm event for the entire Project mine and
process area. In addition, the heap benches and berms would be constructed
to provide for 100 percent containment of the precipitation from the
1-hour probable maximum precipitation (PMP) design storm event. Since the
Project would use process solutions that could potentially be harmful to
human health and the environment during the 20-year proposed operating life,
the use of the PMP design was selected as the most stringent, prudent and
reasonable value, compared to the 100-year/24-hour event or other smaller
precipitation event). The PMP was calculated to be 4.65" by averaging
the PMP values for Yuma, Arizona and El Centro, California. A conservative
value of 5" was used in the design. Utilizing this approach would,
under probable conditions, provide maximum protection to the environment
from the escape of fluids from the heap leach facilities. Erosion control
methods around facilities other than the heap leach would be designed to
manage not less than a 20-year, 1-hour intensity storm event, in accordance
with standards established by 14 CCR 3706(d) (SMARA regulations).
The Proposed Action also includes compliance with the conditions of the
Storm Water NPDES General Permit applicable to the Project, and preparation
and compliance with the requirements of a Storm Water Pollution Prevention
Plan (SWPPP) to control drainage and erosion. As a result, the Proposed
Action is not anticipated to result in significant sedimentation.
Substantial quantities of various chemicals would be stored and used within
the Project mine and process area (see Section 2.1.9.4), and
substantial quantities of regulated waste (such as waste oil) would be generated
(see Section 2.1.9.5). These materials could be released into
the watercourses which flow through the Project area, either through spills
directly into the washes or from overland flow of either the spilled material
or contaminated soil. Minor spills of chemicals and regulated wastes may
occur during the life of the Project, but would not result in any substantial
degradation of surface water quality if promptly contained and collected
and properly disposed of. Measures to reduce the potential for spills of
chemicals or regulated waste have been included in the Proposed Action,
which also includes sediment traps designed for the 100-year, 24-hour storm
event to ensure no spilled material leaves the Project mine and process
area, and measures to reduce erosion and sedimentation which may transport
spilled materials or wastes to the watercourses. Together, these measures
would reduce the potential for any surface water degradation to insignificance.
The heap leach pad system (heap, pad, ponds, etc.) would be designed to
provide for 100-percent containment of the precipitation from the maximum
probable one (1)-hour storm event occurring simultaneously with a 24-hour
power outage while still maintaining a two-foot freeboard in the process
and overflow ponds (see Section 2.1.8). This would reduce the potential
for failure of the process facilities to contain all process solutions during
high precipitation events, which might otherwise result in a discharge of
process solution and sediment to the natural drainage channels. In addition,
the waste characterization studies (EMA 1995; EMA 1996b) conducted on samples
of waste rock and leached ore concludes that these materials are all properly
classified as non-acid generating wastes, and that the leachates which may
be formed from precipitation moving through the waste rock or leached ore
would have very low concentrations of metals, which would not degrade the
quality of surface waters. These effects would also be below the level of
significance.
There is no evidence that implementation of the Proposed Action would result
in any violations of any applicable state water quality standard, nor violate
any applicable toxic effluent standard or prohibition.
Floodplain Encroachment
Pursuant to Sections 74400 through 74402 of Division 4 of Title 7
of the codified ordinances of Imperial County, a development permit is required
to be obtained from the Flood Administrator before construction or developments
begins within any area of special flood hazard (such as FEMA Zone A,
but not Zone C). Sections 74500 through 74501 of Division 4
of Title 7 of the codified ordinances of Imperial County proscribe
the standards of construction and standards for utilities which are to be
followed when constructing structures within these special hazard areas.
Based upon a review of the FEMA FIRM map for the Project area, none of the
facilities located within the Project mine and process area would encroach
upon any areas designated Zone A, and only a small portion of the buried
water pipeline in the Project ancillary area is proposed to be constructed
through an area designated Zone A (that in the portion of Zone A
which crosses Indian Pass Road) [see Figure 3.8]. Construction
in this Zone A section would be subject to these Imperial County standards
and would require authorization from the Imperial County Flood Administrator.
This would not be a significant effect.
Compliance with Executive Order 11988 would require the BLM
(and other federal agencies granting applicable rights) to reference in
the granted right those uses, if any, that are restricted under identified
federal, state or local floodplain regulations in any floodplain. This is
not a significant effect.
Ground Water Inflows:
The West Pit and East Pit are predicted to intercept the local ground water
table at elevations of 211 feet and 88 feet AMSL,
respectively. Thus, the projected final pit floor elevation of both the
East Pit and the West Pit would intersect ground water within the bedrock
aquifer. Because of the low permeability
and porosity of the bedrock below the ground water table, little ground
water is expected to enter the pits. Hydrologic investigations conducted
within the area of the proposed pits indicate that hydraulic conductivity
in the bedrock is very low (WESTEC, Inc. 1996a); however; these data were
calculated from falling head and slug tests and, as such, are of limited
value in accurately determining aquifer parameters.
Furthermore, information collected to date indicates that the flow of substantial
amounts of ground water from the alluvium bedrock contact into the open
pits is highly unlikely. This is supported by the fact that approximately
60 percent of the exploration holes drilled in and around the proposed
pits have been drilled using dry methods, and only a trace of water has
been detected at the alluvium/bedrock contacts (see also Figure 3.11
and Figure 3.12). Should ground water be encountered in the pits
during mining operations, it would be utilized in dust control operations,
or collected and used in process operations, thus reducing the amount of
ground water which would need to be produced from the ground water wells
and consumed.
After the cessation of mining activities, it is possible that ground water
seepage, surface runon or direct precipitation may accumulate in the bottom
of either the East Pit. Calculations based on projected ground water inflow
to the pit, annual precipitation, and annual evaporation for the East Pit
indicate that the estimated annual evaporation rate is approximately 170 times
the annual estimated ground water and precipitation inflow rate (WESTEC,
Inc. 1996a). Because the project pit inflow estimates are based on limited
data, additional calculations using hydraulic conductivity values ten (10
times higher were made to evaluate possible higher inflows to the pit. These
calculations indicated that even in the event that inflow rates an order
of magnitude greater than those expected based on existing data, annual
evaporation would still exceed annual inflow (Personal Communication, John Heggeness,
WESTEC, 1996). Thus, the formation of a pit lake in the bottom of the East
Pit after the cessation of mining activities is not likely. The Proposed
Action also proposes to conduct an assessment at the end of mining and to
backfill the East Pit with waste rock to
an elevation which would ensure that no standing water would remain in the
pit bottom if the assessment indicates that there is a reasonable potential
for a pit lake to form. This reduces the potential for the formation of
a pit lake in the East Pit even further. (See also Section 4.1.3.2.2
for a discussion of the potential for the degradation of ground water quality
as a result of evaporation and/or leaching of minerals from a pit lake,
should it form.) The effects of any pit lake on ground water hydrology are
less than significant. However, see Section 4.1.5.3.2 for a
discussion of the potential adverse effects of a pit lake on wildlife.
The formation of localized moist areas, seasonal seeps, or ephemeral, localized
ponds from ground water inflow, precipitation, or surface water runon, remains
a possibility in the East Pit. The effects of these seeps on ground water
hydrology are below the level of significance. However, see Section 4.1.5.2
for a discussion of the potential adverse effects of these seeps, etc. on
vegetation and plant habitat.
Both the West Pit and the Singer Pit are proposed to be completely backfilled
under the Proposed Action. However, if mining is suspended or terminated
prior to backfilling of the West Pit above the ground water level, it is
possible, but not probable, that a pit lake could form in the West Pit.
Also, if mining is suspended or terminated prior to the complete backfilling
of either the West Pit or the Singer Pit, formation of localized moist areas,
seasonal seeps, or ephemeral, localized ponds from ground water inflow (for
the West Pit only), precipitation, or surface water runon remains a possibility.
These effects on ground water hydrology are below the level of significance.
However, see Section 4.1.5.2 for a discussion of the potential
adverse effects of these seeps, etc. on vegetation and plant habitat, and
see Section 4.1.5.3.2 for a discussion of the potential adverse
effects of a pit lake on wildlife.
"Waters of the United States":
The delineation of "waters of the United States" conducted for
the Project (see Section 3.3.1.4) determined that there were
approximately 114.5 acres of jurisdictional "waters of the United
States" within the Project mine and process area. An assessment of
the acreage of "waters of the United States" which would be affected
by discharges of dredged or fill material (that is, altered by excavation
or the addition of material) by Project activities within the Project mine
and process area has been completed (LSA Associates, Inc. 1997b [see Appendix N
to this EIS/EIR]). By comparing the layout of the Project facilities within
the Project mine and process area to the delineated "waters of the
United States," it is estimated that approximately 77.4 acres
of "waters of the United States" would be directly affected through
the permanent filling or excavation of these "waters of the United
States" within the Project mine and process (see Figure 4.1).
Indirect impacts to other "waters of the United States" would
also occur, both within and immediately adjacent to the Project mine and
process area, principally through the isolating or de-watering of a given
reach of drainage course by excavating or filling upstream areas. However,
such indirect impacts would be restricted to short reaches of tributary
stream channels immediately down-gradient of the filled or excavated areas,
since all of the major stream channels have been diverted to maintain throughgoing
flows.
The draft alternatives analysis prepared under Section 401(b)(1) of
the Clean Water Act (LSA 1997b) concludes that the Proposed Action is the
least environmentally damaging practicable alternative. In addition, Section 3.3.1
of this EIS/EIR describes the hydrologic function, and Section 3.5
describes the ecosystem values, of the "waters of the United States"
located within the Project mine and process area. Section 4.1.2.3,
Section 4.1.3.1.3, and Section 4.1.5.4 of this EIS/EIR
discuss the appropriate and practicable steps which should be taken to minimize
potential adverse impacts of the discharge on these hydrologic functions
and aquatic ecosystem values. Alternatives to the proposed discharge to
or fill of "waters of the United States" within the Project mine
and process area are discussed in Section 2.2 of this EIS/EIR;
this analysis supports the conclusion that there are no practicable alternatives
to the proposed discharge which would have less adverse impact on the aquatic
ecosystem. Section 4.1.3.1.2 concludes that the discharges would
not cause or contribute to violations of any applicable state water quality
standard, violate any applicable toxic effluent standard or prohibition,
or cause or contributed to substantial degradation of the "waters of
the United States". Section 4.1.5.3.3 concludes that the
mitigated effects of the Proposed Action on the only effected endangered
species (desert tortoise) would be below the level of significance, and
the Biological Assessment submitted by the BLM
to the USFWS for the USFWS Biological Opinion concludes that, with mitigation,
the Proposed Action would not jeopardize the continued existence of the
desert tortoise. It is also anticipated that, pursuant to 33 CFR 325.4,
the ACOE would consider all of the mitigation
measures proposed within this EIS/EIR which may be imposed as conditions
of approval by the BLM, County of Imperial, and
other federal, state, and local agencies which would achieve the objectives
of the ACOE Section 404 program, and especially
the conditions of approval proposed in the Stream Alteration Agreement between
Glamis Imperial and the CDFG. Accordingly, the effects of the Proposed Action
on "waters of the United States" is below the threshold of significance.
4.1.3.1.3. Measures Incorporated by Project
Design and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
See also those measures described in Section 4.1.2.3 designed
to mitigate erosion and Section 4.1.5.4 designed to mitigate
wildlife impacts.
- 4.1.3.1-1: Major watercourses shall be diverted only to the extent
necessary to protect Project facilities, and shall be diverted back into
the same wash system after as short a diversion as practical. Permanent
diversion channels shall be built to approximate the original drainage
system in both gradient and channel geometry, and shall be engineered to
adequately contain and deliver stream flows resulting from the 100-year/24-hour
precipitation event. The diversion system shall also be designed to adequately
contain and deliver stream flows predicted from the 500-year, 24-hour precipitation
event.
- 4.1.3.1-2: All chemicals shall be stored in conformance with applicable
local, state and federal regulations. All non-mining wastes shall be stored
in secondary containment areas, as required, and disposed of off-site in
an approved landfill. Regulated wastes shall be recycled or disposed of
in conformance with all applicable local, state and federal laws and regulations,
and in a manner approved by the responsible regulatory agencies.
- 4.1.3.1-3: Major maintenance of equipment shall be conducted within
the concrete-paved and bermed areas of the maintenance yard to the extent
possible to minimize accidental discharges of waste lubricants and other
materials to the ground.
- 4.1.3.1-4: Each phase of the heap leach pad system (heap, pad, ponds,
etc.) shall be designed to provide for 100-percent containment of the precipitation
from the maximum probable one (1)-hour storm event occurring simultaneously
with a 24-hour power outage while still maintaining a two-foot freeboard
in the process and overflow ponds, and shall be consistent with the requirements
of the CRWQCB .
- 4.1.3.1-5: Diversion channels shall be designed to prevent the abrupt
diversion of flows from their natural courses, and shall provide sufficient
natural protective materials at the points of diversions where necessary
to protect the diversion works. All designs for the diversion channels
shall be signed and stamped by an engineer registered to practice in California
and submitted to the Imperial County Public Works Department for approval
prior to commencement of construction.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
See also those measures described in Section 4.1.2.3 designed
to mitigate erosion and Section 4.1.5.4 designed to mitigate
wildlife impacts.
- 4.1.3.1-6: Project facilities shall not be constructed within special
flood hazard zones (Zone A) as noted on Federal Emergency Management
Agency (FEMA) National Flood Insurance Program Flood Insurance Rate Map
(FIRM) for Imperial County, California (Unincorporated Areas), Panel 700
of 1175, Community-Panel Number 060065 0700 B, Effective
Date: March 15, 1984, except as may be authorized by a Development
Permit approved by the Imperial County Flood Administrator pursuant to
Division 4 of Title 7 of the codified ordinances of Imperial
County and, if applicable, restrictions contained in the approvals of the
appropriate federal authorizing agencies.
- 4.1.3.1-7: Applicant shall acquire and comply with the necessary approvals
from the U.S. Army Corps of Engineers for all jurisdiction "waters
of the United States" under Section 404 of the Clean Water Act
which may be dredged or filled through Project actions.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
See also those measures described in Section 4.1.5.4 designed
to mitigate wildlife impacts and those measures described in Section 4.1.5.2
designed to mitigate adverse effects on vegetation and plant habitat.
No mitigation measures are proposed or recommended.
4.1.3.1.4. Unavoidable Adverse Effects and
Level of Significance After Mitigation
Implementation of the Proposed Action would result in unavoidable, although
not significant, adverse effects to surface water flows within the Project
mine and process area as a result of the permanent diversion of portions
of the ephemeral stream channels within the Project mine and process area.
4.1.3.2. Ground Waters
4.1.3.2.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Substantially degrade water quality;
- Contaminate a public water supply;
- Substantially degrade or deplete ground water resources; or
- Interfere substantially with ground water recharge.
4.1.3.2.2. Impacts of the Proposed Action
In addition to other changes, this section has been modified from the
November 1996 Draft EIR in response to comments to: clarify the relationship
of the ground waters in the Project area to the Colorado River aquifer; add a discussion of the absence of impacts
to seeps and shallow water wells located in the vicinity of the Project
ground water well field area; reduce the estimated quantity of water seeping
from All American Canal to the Amos-Ogilby-East Mesa Basin; include a discussion
of Imperial County's Ground Water Management Ordinance and requirement for
permit; and discuss the relationship between the ground waters in Picacho
Wash Basin and the Project mine and process area.
Ground Water Production:
Ground water would be produced to supply water for heap leach processing
and other service water requirements. An annual maximum of 1,200 afy of ground water would be supplied from up to
four (4) wells drilled in the Project ground water well field area
within the Project ancillary area southwest of the Project mine and process
area. Imperial County's "Ground Water Management Ordinance" requires
that a Ground Water Extraction Permit be obtained prior to commencing the
drilling of ground water production wells. The Imperial County Public Works
Director is required to determine whether sufficient ground water is available
for the proposed use based on the projected use of ground water by the Project
in accordance with Section 56614.01(b) of the ordinance. Exemptions
from obtaining a permit are allowed for the drilling of production exploration
wells.
The projected drawdown of ground water levels in the vicinity of the Project
ground water well(s) as a function of time was calculated using data collected
during the test of ground water exploration well PW-1, which was drilled
under the Ground Water Management Ordinance permit exemption for production
exploration wells (WESTEC, Inc. 1996a; see Table 4.2).
These calculations assumed an individual ground water supply well, located
in the vicinity of ground water exploration well PW-1, would produce approximately
725 gpm, or 1,170 afy, for 20 years.
An average hydraulic conductivity of 16 ft/day (5.6 x 10-3
cm/sec) was assumed for all calculations. Several different drawdown scenarios
were calculated using a range of aquifer
parameters. The calculations were performed using an aquifer
thickness of 300 feet to 600 feet, and a storage coefficient ranging
from 0.02 to 0.002. The calculations show that drawdowns ranging from 1.5 feet
to 6.4 feet are projected to occur at distances of approximately 50,000 feet
(approximately nine and one-half (9.5) miles) from the pumping well
after 20 years of continuous pumping (WESTEC, Inc. 1996a). Maximum
predicted drawdown at a distance of only 1,000 feet from the modeled
water supply well is 19.2 to 24.4 feet. These results would likely
be conservative because they assume: no recharge of the ground water basin
(previously estimated at 30,000 afy); all
wells would be located in the same aquifer
as the production well; and conservative thicknesses for the aquifer
(thicknesses of 1,000 feet have actually been measured).
Table 4.2
Pumping Rate
(gpm) |
Aquifer Thickness
(ft) |
Transmissivity
(ft2/day) |
Storage Coefficient |
Distance to Drawdown Contour in feet |
1,000 |
10,000 |
20,000 |
50,000 |
| 7251 |
300 |
4,800 |
0.02 |
19.2 |
8.6 |
5.4 |
1.8 |
| 725 |
400 |
6,400 |
0.02 |
14.9 |
6.9 |
4.5 |
1.7 |
| 725 |
500 |
8,000 |
0.02 |
12.2 |
5.8 |
4.0 |
1.6 |
| 725 |
600 |
9,600 |
0.02 |
10.4 |
5.1 |
3.4 |
1.5 |
| 725 |
300 |
4,800 |
0.002 |
24.4 |
13.8 |
10.6 |
6.4 |
| 725 |
400 |
6,400 |
0.002 |
18.8 |
10.8 |
8.5 |
5.3 |
| 725 |
500 |
8,000 |
0.002 |
15.4 |
9.0 |
7.1 |
4.6 |
| 725 |
600 |
9,600 |
0.002 |
13.0 |
7.7 |
6.1 |
4.0 |
1This pumping rate is equivalent to approximately 1,200 afy.
Source: WESTEC, Inc. 1996a
Conservative ground water level drawdowns were also calculated for three (3)
specific wells located in the vicinity of the Project: the Gold Rock Ranch
well, located approximately four and one-half (4.5) miles south-southwest
of well PW-1; the Mesquite Mine well GF-3A, located approximately eight (8) miles
northwest of well PW-1; and the American Girl Mine well 26-2, located
approximately eight (8) miles south of well PW-1 (WESTEC, Inc.
1996a; see Table 4.3). For an aquifer
with a thickness of 500 feet (a saturated thickness of 500 feet was
used for the alluvial aquifer to account
for the thickening of the aquifer to the
southwest (Dutcher, et. al. 1972)) and a storativity value of 0.02, a Project
well pumping at a rate 725 gpm (approximately 1,200 afy)
over a period of 20 years was predicted to result in a drawdown of
3.7 feet in the Gold Rock Ranch well, and a drawdown of 1.8 feet
in both the Mesquite Mine well and the American Girl Mine well (WESTEC,
Inc. 1996a). These conservative drawdowns represent a three (3) percent,
one-half (0.5) percent, and one and one-half (1.5) percent drawdown
of the depth of the Gold Rock Ranch, Mesquite Mine, and American Girl Mine
ground water wells, respectively, over the life of the Project. These drawdowns,
and their effects on the projects and the ground water aquifer,
are below the level of significance.
Table 4.3
Pumping
Rate
(gpm) |
Aquifer
Thickness
(ft) |
Transmissivity
(ft2/day) |
Storage
Coefficient |
Gold Rock
Ranch Well
(126 ft. water column)
4 miles from well |
Mesquite Mine Well
(470 ft. water column)
8 miles from well |
American Girl Mine Well 26-2
(110 ft. water column)
9 miles from well |
| (ft of drawdown) |
| 725 |
500 |
8,000 |
0.02 |
3.7 |
1.8 |
1.8 |
Source: WESTEC, Inc. 1996a
Wells for the production of ground water for wildlife (guzzler wells,
or "extraction devices"), which are powered by windmills, have
been drilled within the Algodones Sand Dunes north of Highway 78 and
west of the Southern Pacific railroad tracks by the U.S. Bureau of Reclamation
(Personal Communication, Randy Rister, ICFGC, June 26, 1997). The wells
were drilled to depths of only 75 to 150 feet below ground surface,
or approximately 200 feet AMSL. As static
ground water levels in the Project ground water production area are greater
than 500 feet below ground surface, or approximately 0 feet AMSL, and the guzzler wells are all located further
than 20 miles northwest of the Project ground water well field, ground
water production for the Project should have no effect on the water available
to the guzzler wells.
Several small water seeps are located northwest to southwest of the Project
ground water well field area in the vicinity of and adjacent to the eastern
side of the Algodones Sand Dunes (Personal Communication, Randy Rister,
ICFGC, June 26, 1997). The source of the water for the seeps has not
been identified in any area hydrologic studies; however, because the depth
to ground water in the ground water well field area is several hundred feet,
it is believed that the seeps result from near surface flows of water as
sub-flow in ephemeral stream channels, or the surface outflow of precipitation
which flows through the sand dunes. In either case, ground water production
from the Project ground water well field area, produced from depths of greater
than 500 feet below ground surface and at least five (5) miles
distant, would not impact the shallow source of the seeps. Furthermore,
two (2) production wells, one (1) at the Gold Rock Ranch and one (1)
at the Mesquite Mine are both closer to the seeps than the Project ground
water well field. No known effects to the seeps from the pumping of these
two (2) wells have been observed.
It is unlikely that the Project's ground water production would affect ground
water located in the Picacho Wash Basin. A number of published hydrogeologic
studies have placed a ground water divide between the Amos-Ogilby-East Mesa
Basin and the Picacho Wash Basin, that is, between the Cargo Muchacho Mountains
and Picacho Peak (see Figure 3.10), such that ground water would
flow away from, rather than toward or across, this divide (Bedinger, et
al. 1983; Loeltz, et. al. 1975; and Dutcher, et al. 1972). Furthermore,
bedrock depth in the surface water divide between the "Picacho Wash
Drainage Basin" and the "Indian Wash Drainage Basin" (at
an elevation of approximately 960 feet) is assumed to be shallow, no
deeper than several hundred feet, since this surface water divide is bounded
by the exposed bedrock on the northeast and west-southwest. The depth to
bedrock in the Project mine and process area is zero (0) to 300 feet
below ground surface (860 to 560 feet AMSL).
Exploration drilling to the southeast of the Project mine and process area
has also encountered bedrock at relatively shallow depths (Personal Communication,
Dan Purvance, Chemgold, 1996) (see Figure 3.12). Thus, while
bedrock is not exposed at the surface of the surface water divide between
the "Indian Wash Drainage Basin" and the "Picacho Wash Drainage
Basin," and no data (gravity, etc.) has been made available to judge
the depth to bedrock in this area, it is very likely that a subsurface bedrock
barrier to ground water flow between the Amos-Ogilby-East Mesa and the Picacho
Wash ground water basins exists in the same location as the surface divide.
Any effect to ground water in the Picacho Wash Basin, were it to occur,
would be below the level of significance.
Comparing the amount of water projected to be extracted during the life
of the Project to the estimated usable and recoverable stored water and
estimated recharge, the Project should not substantially impact the alluvial
ground water resources of the area. The Project's maximum annual extraction
rate of 1,200 afy represents about four (4)
percent of the annual 30,000 acre-feet recharge of the entire Amos-Ogilby-East
Mesa Basin. Over the 20-year projected life of the Project, the Project
would use an estimated 24,000 acre-feet of water, which represents
approximately 0.01 percent of the estimated 230,000,000 acre-feet
of useable and recoverable water in the Amos-Ogilby-East
Mesa Basin (WESTEC, Inc. 1996a), or approximately 0.02 percent
of the estimated 126,000,000 acre-feet of useable and recoverable water
in the Amos-Ogilby Basin alone. These effects are below the level of significance.
Ground water inflows into open pits are predicted to be very small, only
1.5 gpm (2.4 afy) for the West Pit
and 0.7 gpm (1.1 afy) for the East
Pit. This rate of ground water inflow would have a negligible effect on
ground water levels in the vicinity of the pits or beyond. Ground water
entering either of these pits during mining operations would be utilized
in dust control operations, or collected and used in process operations.
No ground water is anticipated to be encountered in the Singer Pit. The
impacts from ground water inflow into the pits to the surrounding aquifer is below the level of significance.
Ground Water Quality:
Given the depth to ground water in the Project mine and process area, there
is little potential for degradation of ground water quality from accidental
spills or leakage of chemicals or regulated wastes from containment areas
or from the leach pad facility. Minor spills of chemicals and regulated
wastes may occur during the life of the Project, but should not result in
any substantial degradation of ground water quality if promptly contained
and collected and properly disposed of. The Proposed Action also includes
measures to reduce the potential for spills of chemicals or regulated waste
to below the level of significance.
Based upon the high acid neutralization potential reported for the samples
of waste rock and leached ore in the Waste Characterization Study (see Appendix C-1),
water from rainfall moving through waste rock or neutralized leached ore
would not be likely to generate acidic waters which could degrade ground
water quality. In addition, the results of the SPLP extractions conducted
on the same rock materials indicate that waters from rainfall would not
be likely to leach substantial quantities of metals from these rock materials,
and ground water quality would not be degraded. This impact would not be
significant.
The heap leach pad has been designed with a dual liner system to decrease
the potential for any leakage of leach solution. The first portion of the
leach pad would be constructed with a liner consisting of a composite of
40-mil polyvinyl chloride (PVC) primary and 20-mil PVC secondary geomembrane
liners placed directly on a minimum of four (4) inches of compacted,
fine-grained, bedding material. Similar liners were approved by the CRWQCB and constructed by others at the nearby
American Girl mine in 1995. The USEPA is reported to have recognized the
acceptability (for seamabilty, punctureability and installability) of 20-mil
PVC liners for landfills (Peggs 1992), and the United States Bureau of Reclamation
(USBR), which has installed over 40 million square feet of PVC in canal
linings since 1968, has specified 20-mil thicknesses since the early 1980's
(Comer, et al. 1996). The pad is also designed to drain by gravity into
the solution collection system and solution ponds so that there is only
a minimum layer of saturated drain rock (typically less than one (1)
foot) above the liner, thus reducing the hydraulic head across the liner.
Monitoring of both the vadose zone and
ground water for evidence of leakage of leach solution would be conducted
under the Proposed Action. The vadose zone monitoring system would be placed
under only approximately 25 percent of the leach pad liner and process
ponds, but would be located directly under the lowest points of each cell
of the heap leach pad and the process ponds. Because of its placement, this
vadose monitoring system should be capable of detecting any substantial
leak through the double liner system of the heap leach pad and process ponds.
The CRWQCB would typically require monthly
sampling of both the vadose zone and
ground water monitoring points and analysis for the constituents of concern
(those constituents of the process solution, such as cyanide and select
metals, which if detected in the vadose zone
or ground water monitoring points would likely indicate a leak). Results
would be required to be reported monthly, more rapidly if evidence of a
leak is detected. Detected leaks under the pad would be evaluated and corrected
under the supervision of the CRWQCB , either
through excavation of the heaped material and repair of the liner, if the
height of the heap at the time of detection of the leak is not too great,
or through reducing or eliminating the application of leach solution to
that portion of the heap located over the leak. Leaks under the process
ponds would be repaired after emptying the appropriate pond. Leaks are not
common place and are usually detected while still small. Remediation of
leaked solution is typically not required because the weak cyanide solution
degrades rapidly as the pH drops and it is oxidized in the air, and the
soil and rock material above the ground water can attenuate the concentrations
of the metals. Taken together, these measures reduce the potential for any
ground water quality degradation from the heap leach pad and process ponds
to insignificance.
It is also unlikely that any degradation of ground water in the Picacho
Wash Basin would result from any accidental spills or leakage of chemicals
or regulated wastes from Project containment areas or from the leach pad
facility. In addition to the presumed bedrock ground water barrier located
between the Indian Wash portion of the Amos-Ogilby-East
Mesa Basin and the Picacho Wash Basin, the ground water gradient established
by the data presented in Appendix E-1 and Appendix E-2 clearly
trends down to the southwest, away from the Project mine and process area
toward the area of the Project production well field (near well PW-1),
and away from the divide between the Indian Wash portion of the Amos-Ogilby-East Mesa Basin and
the Picacho Wash Basin. Thus, impacts to the ground water of the Picacho
Wash Basin would be below the level of significance.
Pit Water Quality:
As discussed in Section 4.1.3.1.2, the formation of a pit lake
in the bottom of the East Pit following the completion of pit mining is
not likely to occur, and the Proposed Action includes backfilling the pit
with waste rock material to an elevation that is above the predicted level
of any pit lake should a study reasonably determine that a pit lake may
form (see Section 2.1.3). Based upon the high acid neutralization
potential reported for the samples of waste rock and leached ore in the
Waste Characterization Study (see Appendix C-1), ground water moving
through backfilled waste rock in either the West Pit or East Pit would not
be likely to generate acidic waters. In addition, the results of the SPLP
extractions conducted on the same rock materials indicate that the ground
waters would not be likely to leach substantial quantities of metals from
these rock materials, and the ground water quality would likely remain relatively
unchanged.
To further assess the potential interactions which may occur between the
waste rock which may be backfilled into either the West Pit or East Pit
and the ground water which may enter either pit, an additional geochemical
investigation was conducted (see Appendix C-2) to supplement the Waste
Characterization Study. Samples of each of the rock types which may be backfilled
into either the West Pit or East Pit were processed by several standard
USEPA chemical-extraction techniques to conservatively simulate what constituents
may be leached from the rock if exposed to ground waters entering a backfilled
pit. Modeling was then conducted using analyses of the extracted constituents,
analyses of the ground water, and the mineral phases of the rock to evaluate
impacts to the ground water after equilibration.
Representative composite samples of each of the principal rock types to
be mined (sericite gneiss, biotite gneiss, and gravels) (see Section 3.1.1)
were first extracted using USEPA Method 1312, which is designed to
determine the mobility of both organic and inorganic constituents in liquids,
soils and wastes. It uses a 60/40 weight percent of sulfuric acid/nitric
acid diluted with deionized water to a pH of 5.0 added to the solid sample,
which is then agitated for 18 hours. The resultant liquid (leachate)
is then filtered and analyzed. The analytical results from each of the three (3)
samples show that the extracted constituents are in low concentrations,
in most cases at or below the respective concentrations in the ground water
currently in the undeveloped pits, and are below current California water
quality standards except the primary selenium maximum contaminant limit
(MCL) and the secondary manganese MCL (see Appendix C-2).
Six (6) additional representative composite samples of four (4)
rock types (sericite gneiss, biotite gneiss, volcanics, and gravels) (see
Section 3.1.1) were also collected from the locations of both
the East Pit and West Pit and extracted using USEPA Method 1320, the
Multiple Extraction Procedure, which is "designed to simulate the leaching
that a waste would undergo from repetitive precipitation of acid rain on
an improperly designed sanitary landfill. The repetitive extractions reveal
the highest concentration of each constituent that is likely to leach in
a natural environment." (USEPA 1986). As such, this test is very conservative
for the types of geologic materials and the environment anticipated within
the backfilled Project pits.
The first Method 1320 extraction uses USEPA Method 1310 (Extraction
Procedure (EP) Toxicity Test Method) to leach constituents from the solid
by agitating for 24 hours with deionized water which is maintained
at a pH of 5.0 with acetic acid. The resulting leachate is then filtered
and analyzed. Nine (9) subsequent extractions are then sequentially
undertaken on the solid residual using a 60/40 weight percent of sulfuric
acid/nitric acid diluted with deionized water to a pH of 3.0, each agitated
for 24 hours. The resultant leachate from each extraction is filtered
and analyzed.
The analytical results from the six (6) samples used in the USEPA Method 1320
extraction show that the concentration of the constituents in the first
extraction are much higher than in subsequent extractions (see Appendix C-2).
TDS and alkalinity concentrations were uniformly higher than in the ground
water in the first extraction for all rock types, as were the concentrations
of aluminum, calcium, and manganese. The pH was also uniformly lower than
the ground water, reflecting the acidic extraction fluid. Concentrations
of copper, lead, potassium, strontium, titanium, zinc, barium, chromium,
thallium, beryllium, magnesium, cadmium, arsenic, or silver in the first
extractions of some samples also slightly exceeded the respective constituent
concentrations in the ground water. Constituent concentrations in extractions 2
through 10 were typically lower than concentrations in either the ground
water or extraction 1, although iron concentrations increased in nearly
all samples in the later extractions, reflecting the artificially low pH
in the extraction fluid (see Section 2.1.4) and the lack of
alkalinity remaining in the sample.
The analytical results of the Method 1320 extractions show that high
concentrations of calcium and available alkalinity may leach from the backfilled
material, probably due to the rigorous leaching procedure and the dissolution
of calcite (CaCO3) which is present as a secondary mineral phase
in the rocks. The relatively high manganese concentrations in the Method 1320
extraction leachates are also due to the rigorous leaching method and the
dissolution of secondary manganese minerals (oxyhydroxides) in the rock.
Geochemical models were also run to test the effects of the ground water
flowing into the pits and equilibrating with the backfilled material under
earth surface conditions. The results of these geochemical models were then
evaluated relative to existing (background) ground water quality and to
the potential impacts to ground water quality downgradient from the pits.
Because calcite (CaCO3) is the most reactive mineral phase present
in the rocks, the models assumed that inflowing ground water would equilibrate
with calcite and with atmospheric carbon dioxide (CO2). The model
inputs were derived from the analytical results of the ground water samples
collected in the areas of the pits, the Method 1312 extractions, and
the Method 1320 extractions. The results of all of the geochemical
models predict that the dissolved constituent concentrations present in
the ground water which has equilibrated with the backfilled material in
the pits would be at, or below, the current concentrations present in the
ground water. Therefore, no impacts to ground water quality are expected
to occur from the complete or partial backfilling of any of the Project
pits.
4.1.3.2.3. Measures Incorporated by Project
Design and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
See also those measures described in Section 4.1.3.1.3 designed
to mitigate water quality degradation from chemical spills and use, Section 4.1.12.3
designed to respond to and remediate any chemical spills, and Section 4.1.5.4
designed to eliminate the possibility of a pit lake to mitigate potential
impacts to wildlife.
- 4.1.3.2-1: To prevent excessive drawdown or possible damage to the
well or pumping system, ground water production from well PW-1 shall
be limited to a maximum average of 550 gpm unless a higher pumping
rate, supported by reasonable proof of increased well efficiency, is approved
by the ICPWD. The maximum average production rate from each additional
production well drilled shall be limited to that rate which prevents excessive
drawdown or possible damage to the well or pumping system.
- 4.1.3.2-2: The total annual ground water production rate shall not
exceed 1,200 afy.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.3.2-3: Ground water production and monitoring wells shall be plugged
and abandoned in conformance with applicable regulatory requirements, including
14 CCR 3713(a).
- 4.1.3.2-4: The heap leach pad shall be designed, constructed and operated
in conformance with the specifications, requirements and prohibitions of
Waste Discharge Requirements issued by the CRWQCB
.
- 4.1.3.2-5: The heap leach pad shall be monitored in conformance with
the requirements of the Monitoring and Reporting Program issued by the
CRWQCB . This would include collection of
groundwater quality baseline data prior to mine development.
- 4.1.3.2-6: Applicant shall obtain approval from the ICPWD of a "Ground
Water Management Ordinance" permit prior to drilling any ground water
production well intended for continued use. Production of ground water
from the Project ground water well field shall be monitored and reported
to the ICPWD consistent with the requirements of this permit.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
No other mitigation measures are proposed or recommended.
4.1.3.2.4. Unavoidable Adverse Impacts and
Level of Significance After Mitigation
Implementation of the Proposed Action would result in the unavoidable,
but not significant, loss of ground water produced from the ground water
well field, and may result in the unavoidable loss of minor quantities of
ground water if exposed as seeps in the walls of the open pit after the
cessation of mining.
Effects of the Proposed Action to ground water resources would be below
levels of significance.
4.1.4. Air Resources
4.1.4.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
The Proposed Action would normally have a significant effect on the environment
if it would:
- Violate any regulatory requirement of the ICAPCD; or
- Violate any ambient air quality standard; or
- Contribute substantially to an existing or projected air quality violation;
or
- Expose sensitive receptors to substantial pollutant concentrations.
4.1.4.2. Impacts of the Proposed Action
In addition to other changes, this section has been substantially modified
from the November 1996 Draft EIR in response to comments to: recalculate
fugitive emissions for travel on unpaved roads (and other revisions to reflect
changes in the Proposed Action); and add additional cumulative analysis
for air quality requested (cumulative analysis extended).
Air Pollutant Emission Sources and Emissions:
The Proposed Action consists of many activities and operations, each of
which may have the potential to emit air pollutants. Rule 101 (Definitions)
of the Rules and Regulations of the ICAPCD (Rules) defines a "source"
as "a specific device, article, or piece of equipment from which air
contaminants are emitted, or the distinct place (such as with fires or other
chemical activity) from which air pollutants are emitted." Rule 207B.
(New and Modified Stationary Source Review-Definitions) goes further to
define "emissions unit" as "an identifiable operation or
piece of process equipment such as an article, machine, or other contrivance
which emits, has the potential to emit, or results in the emissions of any
affected pollutant directly or as fugitive emissions." Rule 101
goes on to define "fugitive emissions" as "those emissions
which cannot reasonably pass through a stack, chimney, vent or other functionally
equivalent opening." A comprehensive list of each of the identified
individual potential sources of Project air pollutant emissions ("emission
units"), organized into "emission groups" of similar activities
(such as mining, heap leaching, etc.), are presented in Table 4.4.
Table 4.4
| LIST OF POTENTIAL EMISSION SOURCES AND TYPE FOR THE PROPOSED
ACTION |
| Emission Unit |
Emission Unit Description |
Emission "Source" Type |
| Point |
Fugitive |
Mobile |
Other |
| Emission Unit Group 1: Mining Activity |
| 1.001 |
Drilling - Waste Rock |
|
X |
|
|
| 1.002 |
Drilling - Ore |
|
X |
|
|
| 1.003 |
Blasting - Waste Rock |
|
X |
|
|
| 1.004 |
Explosives Detonation - Waste Rock Blasting |
|
X |
|
|
| 1.005 |
Blasting - Ore |
|
X |
|
|
| 1.006 |
Explosives Detonation - Ore Blasting |
|
X |
|
|
| 1.007 |
Waste Rock Loading |
|
X |
|
|
| 1.008 |
Ore Loading |
|
X |
|
|
| 1.009 |
Waste Rock Dumping |
|
X |
|
|
| 1.010 |
Ore Dumping |
|
X |
|
|
| 1.011 |
Waste Rock Dozing |
|
X |
|
|
| 1.012 |
Waste Rock Hauling |
|
X |
|
|
| 1.013 |
Ore Hauling |
|
X |
|
|
| 1.014 |
Ammonium Nitrate Prill Silo Loading |
X |
|
|
|
| 1.015 |
Ammonium Nitrate Prill Silo Unloading |
X |
|
|
|
| 1.016 |
Wind Erosion (Waste Rock Stockpile) |
|
X |
|
|
| 1.017 |
Wind Erosion (Soil Stockpiles) |
|
X |
|
|
| 1.018 |
Haul Truck (Combustion) |
|
|
X |
|
| 1.019 |
Mine Dozer (Combustion) |
|
|
X |
|
| 1.020 |
Drill Rig (Combustion) |
|
|
X |
|
| 1.021 |
Loader (Combustion) |
|
|
X |
|
| 1.022 |
Clean-Up Loader (Combustion) |
|
|
X |
|
| Emission Unit Group 2: Heap Leaching Activity |
| 2.001 |
Portable R-O-M Lime Silo Loading |
X |
|
|
|
| 2.002 |
Portable R-O-M Lime Hopper Loading |
X |
|
|
|
| 2.003 |
Lime Application to Ore |
|
X |
|
|
| 2.004 |
Ore Ripping/Spreading/Dozing |
|
X |
|
|
| 2.005 |
Heap Leach Dozer (Combustion) |
|
|
X |
|
| 2.006 |
Cyanide Application and Leaching |
|
X |
|
|
| 2.007 |
Pregnant Solution Pond |
|
X |
|
|
| 2.008 |
Barren Solution Pond |
|
X |
|
|
| 2.009 |
Wind Erosion (Heap Leach Pad) - Non-Leach |
|
X |
|
|
| 2.010 |
Wind Erosion (Heap Leach Pad) - Leach |
|
X |
|
|
| Emission Unit Group 3: Process Plant |
| 3.001 |
Carbon Adsorption Tank 1 |
|
X |
|
|
| 3.002 |
Carbon Adsorption Tank 2 |
|
X |
|
|
| 3.003 |
Carbon Adsorption Tank 3 |
|
X |
|
|
| 3.004 |
Carbon Adsorption Tank 4 |
|
X |
|
|
| 3.005 |
Carbon Adsorption Tank 5 |
|
X |
|
|
| 3.006 |
Acid Wash Tank |
|
X |
|
X |
| 3.007 |
Cyanide Make-up Tank |
|
X |
|
|
| 3.008 |
Strip Tank |
|
X |
|
|
| 3.009 |
Electrowinning Cell |
|
X |
|
X |
| Emission Unit Group 4: Refining |
| 4.001 |
Mercury Retort Furnace (Electric) |
X |
|
|
|
| Emission Unit Group 5: Laboratory |
| 5.001 |
Jaw Crusher |
X |
|
|
|
| 5.002 |
Pulverizer |
X |
|
|
|
| 5.003 |
Fume Hood |
X |
|
|
|
| 5.004 |
Waste Acid Tank |
|
X |
|
|
| Emission Unit Group 6: Shop Area |
| 6.001 |
Main Diesel Tank 1 |
|
|
|
X |
| 6.002 |
Street Diesel Tank |
|
|
|
X |
| 6.003 |
Unleaded Gasoline Tank |
|
|
|
X |
| 6.004 |
Coolant Tank |
|
|
|
X |
| Emission Unit Group 7: Mine & Process Area Support Activities |
| 7.001 |
Water Truck (Combustion) |
|
|
X |
|
| 7.002 |
Water Truck Traffic |
|
X |
|
|
| 7.003 |
Backup Diesel-Fueled Generator |
X |
|
|
|
| 7.004 |
Mobile Light Plant - Pit #1 |
|
|
X |
|
| 7.005 |
Mobile Light Plant - Pit #2 |
|
|
X |
|
| 7.006 |
Mobile Light Plant - Heap |
|
|
X |
|
| 7.007 |
Mobile Light Plant - WRS |
|
|
X |
|
| 7.008 |
Cable Reel Machine |
|
|
X |
|
| 7.009 |
Grading of Road Surface |
|
X |
|
|
| 7.010 |
Grader (Combustion) |
|
|
X |
|
| Emission Unit Group 8: Other Mobile Emission Units |
| 8.001 |
On-Site Delivery Truck Traffic |
|
X |
|
|
| 8.002 |
On-Site Light Vehicle Traffic |
|
X |
|
|
| 8.003 |
Off-Site Delivery Truck Traffic |
|
X |
|
|
| 8.004 |
Off-Site Light Vehicle Traffic |
|
X |
|
|
| 8.005 |
On-Site Delivery Truck (Combustion) |
|
|
X |
|
| 8.006 |
On-Site Light Vehicle (Combustion) |
|
|
X |
|
In addition to being organized into emission groups, these emission units
can also be characterized by the "type" of emission unit. For
the sake of this analysis, four (4) different "types" of
emission units were identified which are applicable to the Project: stationary
"point" sources (e.g., the diesel-fuel emergency electric generator);
"fugitive" sources (i.e., those which do not emit pollutants from
single points, but from diffuse areas (e.g., dust generated by vehicles
moving on unpaved roads or windblown dust)); mobile combustion sources (e.g.,
the "tailpipe" emissions from haul trucks, dozers, etc.); and
"other" sources (e.g., vapor emissions from the storage of fuel
in storage tanks). Table 4.4 also lists the
emission "type" of each of the Project emission sources.
Estimates of the annual emissions of each applicable criteria air pollutant
from each emission unit during full operation of the Project were prepared
using generally available emission estimating techniques and operational
parameters for each of the emission units as provided by Glamis Imperial,
assuming the implementation of the "emission control" techniques
proposed to be implemented as a part of the Proposed Action to reduce emissions
(such as the watering of roads) [see Appendix O of this EIS/EIR]. Table 4.5 provides a summary of the maximum estimated
daily (in pounds per day) and annual (in tons per year) regulated (criteria)
air pollutant emissions expected from the Project during full operations.
During the periods of Project construction, and post-Project reclamation,
emissions from the Project would be limited to emissions of fugitive particulate
matter from loading, hauling, dumping, dozing, and vehicular traffic in
the Project area as well as combustion emissions from mobile sources.
Table 4.5
| SUMMARY OF TOTAL CALCULATED EMISSION OF REGULATED AIR POLLUTANTS |
| Emission Unit No. |
Emission Unit Description |
Regulated Air Pollutants |
| TSP |
PM10 |
SOx |
NOx |
CO |
VOCs /ROGs |
(lbs/day) |
(tons/yr) |
(lbs/day) |
(tons/yr) |
(lbs/day) |
(tons/yr) |
(lbs/day) |
(tons/yr) |
(lbs/day) |
(tons/yr) |
(lbs/day) |
(tons/yr) |
| Emission Unit Group 1: Mining Activity |
| 1.001 |
Drilling - Waste Rock |
7.15 |
0.93 |
3.58 |
0.47 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.002 |
Drilling - Ore |
3.58 |
0.47 |
1.79 |
0.23 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.003 |
Blasting - Waste Rock |
149.00 |
13.00 |
74.70 |
6.51 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.004 |
Explosives Detonation - WR Blasting |
0.00 |
0.00 |
0.00 |
0.00 |
45.40 |
3.96 |
386.00 |
33.60 |
1,530.00 |
133.00 |
0.00 |
0.00 |
| 1.005 |
Blasting - Ore |
0.00 |
6.51 |
0.00 |
3.25 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.006 |
Explosives Detonation - Ore Blasting |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
1.98 |
0.00 |
16.80 |
0.00 |
66.60 |
0.00 |
0.00 |
| 1.007 |
Waste Rock Loading |
69.50 |
8.24 |
32.90 |
3.90 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.008 |
Ore Loading |
34.70 |
4.12 |
16.40 |
1.95 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.009 |
Waste Rock Dumping |
171.00 |
20.30 |
80.90 |
9.60 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.010 |
Ore Dumping |
85.50 |
10.10 |
40.50 |
4.80 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.011 |
Waste Rock Dozing |
33.70 |
6.15 |
4.31 |
0.79 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.012 |
Waste Rock Hauling |
338.00 |
39.30 |
152.00 |
17.70 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.013 |
Ore Hauling |
169.00 |
19.60 |
76.10 |
8.84 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.014 |
Ammonium Nitrate Prill Silo Loading |
0.50 |
0.06 |
0.25 |
0.03 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.015 |
Ammonium Nitrate Prill Silo Unloading |
0.45 |
0.06 |
0.23 |
0.03 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.016 |
Wind Erosion (Waste Rock Stockpiles) |
17.90 |
3.20 |
8.97 |
1.60 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.017 |
Wind Erosion (Soil Stockpiles) |
4.49 |
0.80 |
2.24 |
0.40 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 1.018 |
Haul Truck (Combustion) |
120.00 |
21.90 |
62.50 |
11.40 |
266.00 |
48.50 |
2,440.00 |
445.00 |
1,050.00 |
192.00 |
116.00 |
21.10 |
| 1.019 |
WRS Dozer (Combustion) |
6.34 |
1.16 |
3.30 |
0.60 |
13.40 |
2.44 |
123.00 |
22.40 |
52.90 |
9.65 |
5.83 |
1.06 |
| 1.020 |
Drill Rig (Combustion) |
38.30 |
7.69 |
19.90 |
4.00 |
18.60 |
3.74 |
284.00 |
56.90 |
61.10 |
12.20 |
22.50 |
4.51 |
| 1.021 |
Loader (Combustion) |
15.80 |
2.88 |
8.21 |
1.50 |
16.80 |
3.07 |
183.00 |
33.40 |
53.10 |
9.70 |
23.20 |
4.24 |
| 1.022 |
Clean-up Loader (Combustion) |
4.18 |
0.76 |
2.18 |
0.40 |
4.46 |
0.81 |
48.50 |
8.86 |
14.10 |
2.57 |
6.16 |
1.12 |
| SUBTOTAL - EMISSION UNIT GROUP 1 |
1,270.00 |
167.00 |
591.00 |
78.00 |
364.00 |
64.50 |
3,460.00 |
617.00 |
2,760.00 |
426.00 |
174.00 |
32.10 |
| Emission Unit Group 2: Heap Leaching Activity |
| 2.001 |
Portable R-O-M Lime Silo Loading |
0.14 |
0.02 |
0.07 |
0.01 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 2.002 |
Portable R-O-M Lime Hopper Loading |
1.00 |
0.12 |
1.00 |
0.12 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 2.003 |
Lime Application to Ore |
0.12 |
0.01 |
0.06 |
0.01 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 2.004 |
Ore Ripping/Spreading/Dozing |
29.70 |
5.42 |
3.68 |
0.67 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 2.005 |
Heap Leach Dozer (Combustion) |
6.34 |
1.16 |
3.30 |
0.60 |
13.40 |
2.44 |
123.00 |
22.40 |
52.90 |
9.65 |
5.83 |
1.06 |
| 2.006 |
Cyanide Application and Leaching |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 2.007 |
Pregnant Solution Pond |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 2.008 |
Barren Solution Pond |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 2.009 |
Wind Erosion (Heap) - Non-Leach |
8.23 |
1.47 |
4.12 |
0.74 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 2.010 |
Wind Erosion (Heap) - Leach |
0.41 |
0.07 |
0.21 |
0.04 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| SUBTOTAL - EMISSION UNIT GROUP 2 |
46.00 |
8.27 |
12.40 |
2.18 |
13.40 |
2.44 |
123.00 |
22.40 |
52.90 |
9.65 |
5.83 |
1.06 |
| Emission Unit Group 3: Process Plant |
| 3.001 |
Carbon Adsorption Tank 1 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 3.002 |
Carbon Adsorption Tank 2 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 3.003 |
Carbon Adsorption Tank 3 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 3.004 |
Carbon Adsorption Tank 4 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 3.005 |
Carbon Adsorption Tank 5 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 3.006 |
Acid Wash Tank |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 3.007 |
Cyanide Make-up Tank |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 3.008 |
Strip Tank |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 3.009 |
Electrowinning Cell |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| SUBTOTAL - EMISSION UNIT GROUP 3 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| Emission Unit Group 4: Refining |
| 4.001 |
Mercury Retort Furnace (Electric) |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| SUBTOTAL - EMISSION UNIT GROUP 4 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| Emission Unit Group 5: Laboratory |
| 5.001 |
Jaw Crusher |
1.02 |
0.19 |
0.07 |
0.01 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 5.002 |
Pulverizer |
1.02 |
0.19 |
0.07 |
0.01 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 5.003 |
Fume Hood |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 5.004 |
Waste Acid Tank |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| SUBTOTAL - EMISSION UNIT GROUP 5 |
2.04 |
0.37 |
0.15 |
0.03 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| Emission Unit Group 6: Shop Area |
| 6.001 |
Main Diesel Tank 1 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.19 |
0.04 |
| 6.002 |
Street Diesel Tank |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.01 |
0.00 |
| 6.003 |
Unleaded Gasoline Tank |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
3.26 |
0.60 |
| 6.004 |
Coolant Tank |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| SUBTOTAL - EMISSION UNIT GROUP 6 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
3.46 |
0.63 |
| Emission Unit Group 7: Mine & Process Area Support Activities |
| 7.001 |
Water Truck (Combustion) |
6.72 |
1.23 |
3.50 |
0.64 |
11.90 |
2.16 |
109.00 |
19.80 |
46.90 |
8.56 |
5.17 |
0.94 |
| 7.002 |
Water Truck Traffic |
0.23 |
0.04 |
0.10 |
0.02 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 7.003 |
Backup Diesel Generator |
0.00 |
0.01 |
0.00 |
0.01 |
0.00 |
0.01 |
0.00 |
0.38 |
0.00 |
0.10 |
0.00 |
0.01 |
| 7.004 |
Mobile Light Plant - Pit #1 |
1.02 |
0.19 |
0.48 |
0.09 |
0.45 |
0.08 |
6.82 |
1.24 |
1.47 |
0.27 |
0.55 |
0.10 |
| 7.005 |
Mobile Light Plant - Pit #2 |
1.02 |
0.19 |
0.48 |
0.09 |
0.45 |
0.08 |
6.82 |
1.24 |
1.47 |
0.27 |
0.55 |
0.10 |
| 7.006 |
Mobile Light Plant - Heap |
1.02 |
0.19 |
0.48 |
0.09 |
0.45 |
0.08 |
6.82 |
1.24 |
1.47 |
0.27 |
0.55 |
0.10 |
| 7.007 |
Mobile Light Plant - WRS |
1.02 |
0.19 |
0.48 |
0.09 |
0.45 |
0.08 |
6.82 |
1.24 |
1.47 |
0.27 |
0.55 |
0.10 |
| 7.008 |
Cable Reel Machine |
2.67 |
0.49 |
1.36 |
0.25 |
15.50 |
2.83 |
96.70 |
17.60 |
142.00 |
25.90 |
16.70 |
3.04 |
| 7.009 |
Grading of Road Surface |
1.40 |
0.26 |
4.11 |
0.75 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 7.010 |
Grader (Combustion) |
4.08 |
0.74 |
2.12 |
0.39 |
5.73 |
1.05 |
46.60 |
8.51 |
10.00 |
1.83 |
2.34 |
0.43 |
| SUBTOTAL - EMISSION UNIT GROUP 7 |
19.20 |
3.50 |
13.10 |
2.40 |
34.90 |
6.37 |
279.00 |
51.30 |
204.00 |
37.40 |
26.40 |
4.83 |
| Emission Unit Group 8: Other Mobile Emission Units |
| 8.001 |
On-Site Delivery Truck Traffic |
0.38 |
0.07 |
0.17 |
0.03 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 8.002 |
On-Site Delivery Truck (Combustion) |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.01 |
0.00 |
0.03 |
0.01 |
0.00 |
0.00 |
| 8.003 |
On-Site Light Vehicle Traffic |
3.77 |
0.67 |
1.70 |
0.30 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 8.004 |
On-Site Light Vehicle (Combustion) |
0.20 |
0.04 |
0.10 |
0.02 |
0.05 |
0.01 |
0.49 |
0.09 |
1.65 |
0.30 |
0.20 |
0.04 |
| 8.005 |
Off-Site Delivery Truck Traffic |
19.50 |
3.48 |
8.77 |
1.57 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| 8.006 |
Off-Site Light Vehicle Traffic |
274.00 |
49.00 |
124.00 |
22.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
| SUBTOTAL - EMISSION UNIT GROUP 8 |
298.00 |
53.30 |
134.00 |
24.00 |
1.68 |
0.31 |
0.06 |
0.01 |
0.50 |
0.09 |
0.20 |
0.04 |
| TOTAL - ALL EMISSION GROUPS |
1,640.00 |
233.00 |
751.00 |
107.00 |
413.00 |
73.30 |
3,860.00 |
691.00 |
3,020.00 |
473.31 |
209.00 |
38.60 |
The largest proportion of the emission units are the fugitive emission
sources, especially emitters of fugitive particulate matter (TSP and PM10).
Mining and heap leaching activities, such as blasting, loading, dumping
and dozing, release fugitive particulate matter into the air through the
physical movement of the ore or waste rock. Ore and waste rock hauling,
and truck and vehicle traffic, all generate fugitive particulate matter
emissions by traveling on unpaved roads. Finally, wind erosion of both the
waste rock stockpiles and ore heap can generate fugitive particulate matter
emissions.
Mobile sources, the next largest category of sources, are principally associated
with the mining and heap leaching process. They consist almost exclusively
of large diesel engines which power the haul trucks, dozers, graders, and
water trucks. Because of the high percentages of use (many would operate
nearly 24 hours per day), these mobile sources would produce substantial
quantities of "tailpipe" combustion emissions, such as NOx,
SOx, and CO.
Most of the mobile sources fall into the category of "non-road engines,"
generally defined under 40 CFR '89 as internal combustion engines
which are in or propel a vehicle which is not a "road" vehicle,
or are portable or transportable, but which do not remain in a fixed location
for more than a year. These federal regulations require that "non-road"
engines must be manufactured to meet specific emission standards for criteria
pollutants, based on the size (hp rating) of the engine and date of
manufacture, according to a specific timetable commencing on January 1,
1996. Table 4.6 lists the identified Project
"non-road" engines, the size (kW rating) of each, whether the
engine would be purchased (in 1998) "new" or "used,"
and whether the engine would be subject to these new federal emission limitations.
Table 4.6
Engine |
Engine Rating |
Year of Manufacture |
Applicability of 40 CFR 89 |
| Haul Trucks (8) |
2,500 hp |
1998 |
No |
| Dozers (2) |
375 hp |
1998 |
Yes |
| Drill Rigs (2) |
550 hp |
1998 |
Yes |
| Loader (1) |
1,250 hp |
1998 |
No |
| Light Plants (4) |
35 hp |
1998 |
No |
| Cable Reel Machine (1) |
350 hp |
<1996 |
No |
| Clean-up Loader (1) |
690 hp |
<1996 |
No |
| Water Trucks (2) |
1,050 hp |
<1996 |
No |
| Grader (1) |
275 hp |
1998 |
Yes |
| Back-Up Generator (1) |
750 hp |
1998 |
Yes |
Based on the Project engine size ratings and their assumed date of manufacture
(based on the purchase date), less than half of the Project "non-road"
engines would be required to be manufactured to met the new federal emission
standards. However, many engine manufacturers are already meeting or exceeding
the new emission standards.
Although the Project has a number of stationary point sources, these sources
are individually and collectively minor sources of criteria air pollutant
emissions. About one-half (2) of the stationary point sources are combustion
sources, which as a class emit substantially more gaseous combustion pollutants
(NOx, SOx, and CO) than particulate matter.
Finally, the "other" category of criteria pollutant emission sources
consist exclusively of the diesel, gasoline and other volatile organic compound
storage and dispensing tanks. However, the total quantities of these materials
emitted by the Project to the atmosphere are small.
Federal PSD Regulations:
Federal Prevention of Significant Deterioration (PSD) regulations are
applicable only to major stationary sources which are either specific types
of facilities which emit, or have the potential to emit, 100 tons per
year or more of a criteria pollutant, or any facility which emits, or has
the potential to emit, 250 tons per year or more of any criteria pollutant.
Most fugitive emissions, however, are not included as applicable
emissions under the federal PSD program. Since the few stationary emission
units under the Proposed Action emit collectively substantially less than
1 ton per year of any criteria pollutant, the Project is not subject
to federal PSD regulations.
Title V of the CAAA:
The CAAA included Title V, which established
a very detailed and extensive operating permit system for "major sources"
of regulated air pollutants. The ICAPCD has adopted Rule 900 to implement
Title V within the District, and USEPA's delegation of authority to
implement Title V through Rule 900 became effective on June 2,
1995. Rule 900 is applicable only to a "major" source of
air pollutants, which is defined as "a stationary source which has
the potential to emit a regulated air pollutant or a hazardous air pollutant
(HAP) in quantities equal to or exceeding the lesser of any of the following
thresholds:"
"100 tons per year (tpy) of any regulated air pollutant;"
"10 tpy of one HAP or 25 tpy of two or more HAP's; or"
"Any lesser quantity threshold promulgated by the U.S. EPA."
At present, no lower quantity threshold has been set by the USEPA.
To determine the applicability of Title V (Rule 900) to the Project,
an inventory of the annual potential to emit for each of the applicable
emission units was conducted for the Proposed Action (see Appendix O).
Since Title V (Rule 900) specifically excludes "fugitive"
and "mobile" (road and non-road engine) sources of regulated air
pollutants, it is basically applicable only to stationary ("point"
and "other") sources of criteria (regulated) air pollutants (and
certain HAPs). As such, few of the Project's emission units are included
in the Title V applicability for criteria pollutants. The largest applicable
annual emission rate for a single criteria pollutant for the Proposed Action
is 0.64 tons per year of volatile organic compounds/reactive organic
gases (VOCs /ROGs); all of this emitted from
the fuel and other organic liquid storage and dispensing facilities.
HAPs are specifically listed hazardous air pollutants, some of which can
be found in many of the natural earth materials which would be mined by
the Project; in the fuels used and stored by the Project; and in the solution
used to leach the precious metals from the ore. Current USEPA and ICAPCD
guidance provides that reasonably quantifiable HAP emissions from fugitive
sources, as well as from stationary sources, must be counted to determine
the applicability of Title V for HAPs. The potential HAPs component
of the emitted Project particulates has been conservatively estimated by
assuming that all of the HAPs contained in the fugitive particulate matter
are subject to Title V (Rule 900). Based upon analyses of ore
and waste rock samples collected during exploration drilling (see Section 2.1.4),
and using the calculated total annual TSP emission estimates (see Table 4.5), the total annual emission of particulate-based
HAPs has been estimated at less than 0.01 tons (see Appendix O).
HAPs released as a result of the combustion of diesel fuel and gasoline
in mobile engines are not subject to Title V (Rule 900). In addition,
the HAPs released from most uses of the leaching solution (principally HCN)
are not subject to Rule 900 because they cannot be reasonably quantified.
Due to its limited use, combustion HAPs from the diesel-fueled emergency
generator total less than one (1) pound (0.0002 ton) per year.
The total annual emission of all potentially applicable HAPs from the Project,
including reasonably quantifiable fugitive HCN emissions, is approximately
0.5 tons, substantially below both the 25 ton project-wide Title V
threshold and the 10 ton individual HAP Title V threshold (see
Appendix O).
New Source Review and Emission Offsets:
Rule 207 of the ICAPCD regulations requires the preconstruction review
of new or modified stationary sources to ensure that a project would not
interfere with the attainment or maintenance of ambient air quality standards.
This rule also states that no net increase in emissions to the air basin
would be allowed from new permitted stationary sources with the potential
to emit 137 pounds per day (equivalent to 25 tons per year) or
more of any nonattainment pollutant or its precursors. Rule 207 also
requires that emissions in excess of the 137 pound per day threshold
be "offset" with an actual reductions of the same pollutant or
its precursors. These offsets can be obtained from another source at the
same location, and offset at a ratio of 1:1; or from another source up to
50 miles away at a ratio of 1.2:1. Based upon the emission estimates
for permitted stationary sources as presented in Appendix O, which
are maximum, not anticipated, emission levels, the Proposed Action would
not emit more than 25 tons per year of any nonattainment pollutant
or its precursors, and would be in compliance with Rule 207.
Conformity to the State Implementation Plan
Section 176 of the Clean Air Act (CAA), as amended (42 USC 7401
et seq.), and regulations under 40 CFR Part 51, Subpart W,
apply to projects within non-attainment areas with respect to the conformity
of general federal actions to the applicable State implementation plan (SIP).
Under those authorities, "no department, agency or instrumentality
of the Federal Government shall engage in, support in any way or provide
financial assistance for, license or permit, or approve any activity which
does not conform to an applicable implementation plan." Under CAA 176©
and 40 CFR Part 51, Subpart W, a federal agency must make
a determination that a federal action conforms to the applicable SIP before
the action is taken. The emission reduction measures contained in the Proposed
Action conform to the requirements of the SIP.
As required by the CAA and the CAAA,
the ICAPCD in 1992 issued its final air quality attainment plan (AQAP) outlining
how the basin would conform to the requirements of the state implementation
plan (SIP). The ICAPCD AQAP requires emission offsets of nonattainment air
pollutants to produce net emission reductions within the basin. This is
implemented by ICAPCD Rule 207, which requires that emissions of nonattainment
air pollutants in excess of 137 pounds per day (25 tons per year)
from stationary sources be "offset" with actual net reductions
of the same air pollutant or its precursors in excess of the emissions from
the project. Based upon the analysis of compliance with Rule 207 presented
above, the Proposed Action would not emit more than 25 tons per year
of any nonattainment pollutant or its precursors covered by Rule 207,
and thus would be in compliance with Rule 207 and conform to the State
Implementation Plan.
Best Available Control Technology/Reasonably Achievable Control Measures:
Rule 207 of the ICAPCD regulations also requires the application of
Best Available Control Technology (BACT) to
any new (stationary) emission unit which has the potential to emit 25 pounds
per day (approximately 4.5 tons per year) of any nonattainment pollutant
or its precursors. The Project contains no applicable emission unit which
produces more than 1 ton per year, and thus is not subject to BACT requirements.
ICAPCD Regulation VIII (Fugitive Dust Requirements for Control of Fine
Particulate Matter) requires the implementation of Reasonably Available
Control Measures (RACM) to reduce the amount of PM10 entrained
in the ambient air as a result of emissions generated from anthropogenic
(man-made) fugitive dust sources generated from within Imperial County.
RACM must be applied to any active operation, except as specifically exempted
in the regulations. Because the silt content of both the Project ore and
waste rock is less than five (5) percent, and most other Project activities
which would generate fugitive PM10 are specifically exempted
from Regulation VIII, only the use of internal roads for traffic and
hauling; the discharge of the lime to the ore trucks; and the soil stockpiles
are subject to RACM for PM10. For each of these activities, the
Proposed Action already contains one (1) or more of those measures
required as RACM: the haul and maintenance roads are watered at least once
per day; the lime discharge to the ore trucks is controlled by water sprays;
and emissions from the soil stockpiles are controlled through the application
of vegetation. Therefore, there is no regulatory requirement for the implementation
of any additional measures to reduce emissions of fugitive PM10.
California Air Toxics "Hot Spots" Information and Assessment Act
(AB2588):
The Air Toxics "Hot Spots" Information and Assessment Act (AB2588) ("Hot Spots" Act) was
enacted in September 1987, and subsequently amended in 1992 and again in
1997. The goal of the "Hot Spots" Act is to collect emission data
indicative of routine, predictable releases of toxic substances to the air;
to identify facilities having localized impacts from these releases; to
evaluate health risks from exposure to these emissions; to notify nearby
residents of significant risks; and reduce risk below the determined level
of significance.
The "Hot Spots" Act requires CARB to compile and maintain a list
of substances posing chronic or acute health threats when present in the
air. The Air Toxics "Hot Spots" Act currently identifies by reference
over 600 substances which are required to be subject to the program,
a portion of which must be quantified. Under Section 4432 of the California
Health & Safety Code, AB2588 applies
to the following:
A(a) Any facility which manufactures, formulates, uses, or releases any
of the substances listed pursuant to Section 44321 or any other substance
which reacts to form a substance listed in Section 44321 and which
releases or has the potential to release total organic gases, particulates,
or oxides of nitrogen or sulfur in the amounts specified in Section 44322.
"(b) Except as provided in Section 44323, any facility which is
listed in any current toxics use or toxics air emission survey, inventory,
or report released or compiled by a district. A district may, with the concurrence
of the state board, waive the application of this part pursuant to this
subdivision for any facility which the district determines will not release
any substance listed pursuant to Section 44321 due to a shutdown or a process
change."
Of the 600 substances listed under the "Hot Spots" Act, a large
portion of them are also listed as HAPs under Title V of the federal CAA.
Of those listed as "Substances Which Must Be Quantified" under
AB2588, the Proposed Action is not
expected to emit any substances which were not already identified as a HAP
under Title V of the Clean Air Act. The Proposed Action would use several
chemicals listed as "Substances For Which Production, Use, or Other
Presence Must be Reported." Given the use and presence of these chemicals,
Glamis Imperial would be expected to prepare and submit to the ICAPCD an
AB2588 Emission Inventory Plan (EIP)
as specified in California Health & Safety Code Sections 44300 et seq.
This plan must meet the requirements of the Emission Inventory Criteria
and Guidelines Regulation, California Code of Regulations Subchapter 7.6,
Sections 93300 through 93347, and outline "a comprehensive characterization
of the full range of hazardous materials that are released, or that may
be released, to the surrounding air from the facility." Once the EIP
is approved by the ICAPCD, a complete Emission Inventory would be prepared
in accordance with the requirements of AB2588.
Given the limited quantities of applicable emissions as discussed above,
and the remote location of the Project, exposure of sensitive populations
to significant concentrations of air toxics from the Proposed Action is
very unlikely. Any impacts would be below the level of significance.
Compliance with Ambient Air Quality Standards:
The principal pollutant of concern emitted by the Project is PM10
because of the relatively large quantity of PM10 emitted by the
Project, the relatively low ambient air quality standard for PM10,
and the fact that nearly all of the Project PM10 emissions are
from fugitive and mobile sources which are emitted throughout the Project
mine and process area. (The newly adopted PM2.5 standard is not
yet applicable and, because of the lack of baseline ambient measurements,
determinations of attainment for any area cannot yet be made. In addition,
the techniques necessary to estimate a project's PM2.5 emissions
have not yet been fully developed, and thus an evaluation of a project's
potential impacts and compliance with the new standard cannot be made.)
In order to estimate the ambient air concentrations of PM10 which
may result from Project emissions, computer-aided dispersion modeling for
the Project PM10 emissions was conducted (see Appendix O).
The modeling was conducted with the USEPA Industrial Source Complex -
Short Term (ISCST3R) dispersion model, which utilized the Trinity Consultants,
Inc. Breeze "graphical front end" (IBM-PC Version 3.00, dated 96113).
Using USEPA's regulatory default model options and rural dispersion parameters
with elevated terrain, emissions from Project were modeled based on hourly
emission rates calculated in Appendix O and summarized in Table 4.5 for all sources (fugitive, point, mobile
and other) of PM10 within the Project mine and process area.
Surface meteorological data for the year 1989 from the National Weather
Surface (NWS)-operated Yuma Air Station, combined with upper-air data from
the NWS-operated Tucson Upper Air Station, was used, as it provided the
most readily and reasonably available meteorological data set for the modeling.
One (1) set of discrete receptors and four (4) Cartesian receptor
grids were used for the modeling the emissions from the Proposed Action.
Two (2) coarse Cartesian receptor screening grids were used: a 24 x 21,
1,000-meter receptor grid, centered on the Project mine and process area,
which extended out over five (5) miles from the Project mine and
process area boundary (and included the wilderness areas located in the
vicinity of the Project mine and process area); and a 21 x 21,
250-meter receptor grid, also centered on the Project mine and process area,
which extended out over one-half (0.5) mile from the Project mine
and process area boundary. The single discrete receptor set consisted to
two (2) groups: a set of receptors placed at approximate 50-meter intervals
along the fenced Project mine and process area boundary; and individual
receptor points located in areas of potential public concern outside of
those areas modeled under the Cartesian receptor grids (these receptor points,
and their respective locations, are listed in Table 4.7).
In addition, two (2) densely spaced Cartesian receptor grids were modeled
in those areas on the Project mine and process area boundary near pollutant
"highs" identified by the coarser modeling.
Table 4.7
| Receptor Point |
Location (UTM) |
| Northing |
Easting |
| Bard, California |
3630500 |
729000 |
| Fort Yuma Reservation Boundary - Wash |
3635200 |
720000 |
| Fort Yuma Reservation Boundary - NW Corner |
3634850 |
711750 |
| Picacho State Recreation Area |
3656000 |
723000 |
| American Girl Mine |
3637300 |
707200 |
| Glamis, California |
3652500 |
680000 |
| Gold Rock Ranch |
3640000 |
700000 |
| Picacho Mine |
3649500 |
720200 |
| Mesquite Regional Landfill |
3655943 |
685581 |
| Mesquite Mine |
3658556 |
688788 |
Modeling was conducted for each of the four (4) modelable criteria pollutants
(PM10, NOx, SO2, and CO) emitted by the
Project using the applicable regulatory averaging times for each pollutant.
A complete discussion of the modeling conducted, including the parameters
used in the model runs and a discussion of the meteorological data, is contained
in Appendix O to this EIS/EIR.
The computer-calculated maximum ambient 24-hour PM10 concentration
located at any point on or outside of the Project mine and process area
perimeter fence was 30.73 Fg/m3, located on the perimeter
fence near the northwest corner of the Project mine and process area. Calculated
maximum annual PM10 concentrations were 5.7 Fg/m3,
also located on the perimeter fence at a point near the northwest corner
of the Project mine and process area. Both of these values are below the
applicable CAAQS and NAAQS (see Table 3.7),
although close to the CAAQS when the background
(annual) PM10 concentration (either 19.0 Fg/m3
(arithmetic mean) or 17.5Fg/m3 (geometric mean)) calculated from
the nearest monitored location, Gold Rock Ranch, is added. Calculated Project-generated
ambient concentrations at distances greater than 3,750 meters (2.3 miles)
from the Project mine and process area boundary were universally below 5 Fg/m3.
Maximum ambient concentrations at receptor points on the northern boundary
of the Ft. Yuma Indian Reservation, a distance of 12,000 meters
(7.5 miles) from the southern boundary of the Project mine and process
area, were well below 1.0 Fg/m3 (both 24-hr and annual concentrations)
and would be impossible to distinguish from background ambient concentrations.
Impacts from the Project at the other discrete receptors placed at points
of potential public concern were universally modeled at below 2 Fg/m3,
and would likewise be impossible to distinguish from background concentrations.
These impacts would be below the level of significance. However, monitoring
is proposed to be required to verify that the project does not exceed the
ambient air quality standards.
One-hour and annual average concentrations were modeled from the Project's
estimated emissions of NOX. However, as indicated in Table 3.7, both the CAAQS
and NAAQS are for concentrations of the NO2 portion of NOX.
In order to reasonably predict the Project's compliance with the CAAQS and NAAQSs for NO2, the NO2 fraction
of ambient NOX was estimated utilizing the USEPA's "Ozone
Limiting Method." Using this method, the highest estimated 1-hr concentration
of NO2 from the Project at any point on or outside of the perimeter
fence was 0.24 ppmv, less than the CAAQS
of 0.25 ppmv (250 ppbv). The highest annual average ambient NO2
concentration resulting from the Proposed Action was 0.0116 ppmv, much
less than the NAAQS of 0.053 ppmv (53 ppbv), this at a point well
within the fenced boundary of the Project mine and process area. Ambient
concentrations modeled at the other discrete receptors placed at points
of potential public concern were universally at or below 0.01 ppmv
(10 ppbv). These impacts would be below the level of significance. A complete
discussion of the "Ozone Limiting Method," as well as the results
of the NOX modeling conducted, is included in Appendix O.
The highest modeled 1-hour SO2 concentration, at a point near
the center of the Project mine and process area, was 494 µg/m3,
well below the CAAQS of 655 µg/m3.
All modeled concentrations at points accessible to the public, at or beyond
the boundary of the Project mine and process area, were universally less
than 150 µg/m3. The modeled
3-hour high, at a point near the center of the Project mine and process
area, was 264 µg/m3, well
below the secondary NAAQS of 1,300 µg/m3.
All modeled SO2 concentrations at points accessible to the public
were universally below 100 µg/m3,
well below the secondary NAAQS. The modeled 24-hour SO2 high,
at a point near the center of the Project mine and process area, was 61 µg/m3, below both the CAAQS and NAAQS. Calculated 24-hour SO2
ambient concentrations at distances greater than 3,750 meters (2.3 miles)
from the Project mine and process area boundary were universally below 10 µg/m3. The highest modeled annual
average, at a point again near the center of the Project mine and process
area, was less than 22 µg/m3,
well below the annual NAAQS. These impacts would be below the level of significance.
A complete discussion of the modeling conducted for SO2 emissions
from the Project is contained in Appendix O.
The results of the CO model indicate a maximum 1-hour high, at a point near
the center of the Project mine and process area, of 2,501 µg/m3, well below both the 24-hour NAAQS
and CAAQS . In addition, all calculated 1-hour
ambient concentrations beyond the Project mine and process area boundary
were universally below 1,500 µg/m3.
The results of the 8-hr average model shows a maximum modeled high, at a
point again near the center of the Project mine and process area, of 993 µg/m3, well below both the annual
NAAQS and CAAQS for CO. All modeled concentrations
at points accessible to the public, beyond the Project mine and process
area boundary, were universally below 500 µg/m3,
well below both the annual NAAQS and CAAQS
for CO. These impacts would be below the level of significance. A complete
discussion of the modeling conducted for CO emissions from the Project is
contained in Appendix O.
Deposition and Depletion of Suspended Particulate Matter
Deposition of lofted particulate matter from Project operations is expected
to occur on and around the Project area. The rate at which particulate matter
settles out from the atmosphere is a function of its gravitational settling
velocity. Larger particles (those greater than 30 microns in diameter) have
sufficient mass to overcome turbulent eddies, and as such settle out much
more quickly than smaller particles. In order to evaluate the quantity of
material potentially deposited on nearby surface and flora in the area,
the emissions of total suspended particulates were modeled using the ISCST3
model. The EPA model has algorithms which simulates the effects of dry and
wet deposition of particulates on the surface due to the processes of gravitational
settling and turbulent diffusion. The depositional velocity is a function
of the meteorology and surface conditions near the source, but is independent
of the distance from the source.
In modeling the deposition of particulate matter, model settings identical
to those used for the criteria pollutant modeling were used: EPA's regulatory
default model options, rural dispersion parameters, elevated terrain, etc.
In addition, the dry deposition option was enabled. Also, consistent with
earlier runs, the Yuma/Tucson meteorological data set was used. A radial
receptor grid, consisting of eight (8) radii with 30 rings spaced
at 100-meter intervals, roughly centered on the Project mine and process
area, and extending approximately 2.0 kilometers beyond the Project mine
and process area boundary, was used. Given the high gravitational settling
velocity of particulate matter greater than 30 microns, only suspendable
particulate matter (those less than 30 microns in diameter, or TSP) were
modeled using the same model source parameters as were used in the modeling
performed for impacts from PM10, and using calculated annual
average emissions of TSP. In addition, the model conservatively assumed
that no wet deposition occurred, that no depletion or removal of mass from
the plume occurred, and that deposited particulate matter was not re-suspended
as a result of additional turbulence or eddies.
The modeled annual average deposition values calculated at all points beyond
the Project mine and process area boundary were less that six (6.0) grams
per square meter (g/m2). At all points greater than 0.5 kilometers
from the Project mine and process area boundary, the annual average deposition
was less than 2.0 g/m2. The highest amount of deposition (24.1 g/m2)
occurred at a receptor point located near the center of the Project mine
and process area, and the amount of deposited material decreased rapidly
as the distance from the source increased. A complete discussion of the
deposition modeling conducted for the Project is contained in Appendix O.
These impacts are not considered significant in regards to their air quality
impacts (see above); the effects on vegetation are discussed in Section 4.1.5.2.
Exposure of Sensitive Populations:
Project air pollutant emissions would produce modest increases in the annual
average ambient concentrations of both criteria air pollutants and HAPs
in the immediate vicinity of the Project mine and process area, well below
any applicable threshold for exposure of sensitive populations. In addition,
the Project mine and process area is far removed from any resident population,
sensitive or otherwise, which could be exposed to any significant, long-term
increase in the ambient concentrations of either criteria air pollutants
or HAPs. Transient populations (i.e., recreational visitors) could be temporarily
exposed to slightly higher level concentrations, although again these ambient
air concentrations would be well below any appropriate threshold exposure
level.
Other Air Quality Related Health Concerns:
Coccidioidomycosis ("valley fever" or "desert fever")
is caused by an infection from the fungus Coccidiodes immitis. Spores
of this fungus are endemic in the uppermost few inches of the soil of those
areas where the disease occurs (CDHS No Date). Spores are carried into the
air on dust, particularly during dust storms, and infection is caused by
inhalation of dust carrying the spores. The California Department of Health
Services (CDHS) indicates that:
"Nearly everyone living for many years in areas where coccidioidomycosis
occurs becomes exposed to and infected by the fungus that causes the disease...
most people never get sick, and ... only two out of every 1,000 individuals
infected develop severe illness.... Even the mildest >attack= of coccidioidomycosis
confers lifelong immunity." (CDHS No Date)
Although much of Arizona (including Yuma), portions of San Diego County,
and northern Mexico have been established as endemic areas for the disease,
Imperial Valley has not been designated as an endemic area for coccidioidomycosis.
The Imperial County Department of Health Services, Division of Environmental
Health (ICDHS-DEH) has indicated that there are no recorded cases of valley
fever in Imperial County (Personal Communication, Thomas Wolf, ICDHS-DEH,
May 5, 1997).
Assuming that the area of
the Proposed Action is endemic for the disease, only the top few inches
of soil would be expected to contain the spores (Personal Communication,
Dr. C. Talbert, Kern County Health Department, June 6, 1997).
This layer of soil would be removed or buried during the first days of construction
activity in any particular area, so that any exposure to dust-containing
spores would be limited to those times when construction in new areas was
initiated. Although this is not expected to result in a significant effect,
a mitigation measure is proposed to reduce the effect further.
4.1.4.3. Measures Incorporated by Project Design
and Regulation and Mitigation Measures
Although the assessment of impacts assumes the implementation of those
measures incorporated into the project design or required by regulation
which avoid or reduce potentially significant impacts, these measures are
expressly identified below to facilitate review and implementation. Mitigation
measures, if any, which are proposed to avoid or reduce potentially significant
effects are separately identified.
Measures Incorporated by Project Design Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.4-1: Chemical dust suppressant treatments, in combination with
water sprays, shall be applied to the haul and maintenance roads within
the Project mine and process area to minimize the generation of fugitive
PM10. Only chemical dust suppressants acceptable to all appropriate
agencies shall be applied, and the application rates and frequencies, for
both the dust suppressant and water, shall be consistent with the guidance
of the manufacturer to achieve optimal suppression of dust. Dust suppressant
and/or water shall be applied no less than twice per day on days without
precipitation unless road surface moisture is documented as sufficient
to achieve maximum suppression of fugitive dust emissions without the additional
dust suppressant or water.
- 4.1.4-2: Project employees, contractors, and visitors shall be advised
of the need to adhere to speed limits to minimize the generation of fugitive
dust. Applicant shall develop and implement appropriate measures to strengthen
compliance with posted speed limits to prevent the generation of fugitive
dust.
- 4.1.4-3: Shrouding of the lime discharge to the ore trucks, or equivalent
RACM for these fugitive PM10 emissions, shall be implemented
and maintained.
- 4.1.4-4: Water sprays or dust suppressants (chemical treatments acceptable
to all appropriate agencies) shall be applied to Indian Pass Road from
its intersection with Ogilby Road to the boundary of the Project mine and
process area with sufficient frequency to minimize the emissions of fugitive
PM10 from Project traffic on Indian Pass Road.
- 4.1.4-5: All disturbed surfaces no longer needed for project activities
shall be reclaimed as soon as practical to minimize fugitive PM10
emissions from wind erosion.
Measures Incorporated by Regulation Which Avoid or Reduce Potentially
Significant Impacts:
- 4.1.4-6: All permits required by the ICAPCD shall be obtained, and
all operations conducted in compliance with the conditions of these permits.
- 4.1.4-7: All fuels used at the Project shall conform to the CARB low-sulfur
requirements in order to minimize SOx emissions from Project-related vehicular
activities.
Mitigation Measures Proposed to Avoid or Reduce Potentially Significant
Impacts:
No mitigation measures are proposed or recommended.
Other Mitigation Measures (These are measures which may further reduce
the impacts of certain effects which are below the level of significance
without mitigation):
- 4.1.4-8: Appropriate measures, such as water sprays, dust suppressants
(chemical treatments acceptable to all appropriate agencies), or reduced
operating speeds, shall be applied to all activities which disturb the
top foot of soil in any areas during construction and reclamation activities
to minimize emissions of fugitive PM10 which may contain Coccidiodes
immitis spores. Project employees, contractors, and visitors shall
be advised to use appropriate precautions regarding the inhalation of dust
while in the Project area during the initial construction/reclamation phases
to minimize exposure to Coccidiodes immitis spores.
- 4.1.4-9: Applicant shall, in consultation with the ICAPCD, establish
and maintain one (1) meteorological monitoring station (for wind speed
and wind direction) and two (2) PM10 monitoring stations
(6-day high volume samplers) to monitor project the ambient concentrations
of PM10 which may be generated by Project activities. It shall
be the intent of the two (2) PM10 monitors to be located
in generally an upwind and downwind arrangement and operated simultaneously
to provide information on the Project's effects on ambient PM10
concentrations. Should the monitoring show that Project operations may
be contributing to a significant increase in ambient PM10 concentrations,
then the Applicant shall review its procedures for reducing PM10
emissions and recommend to the ICAPCD methods which could be applied to
reduce these emissions sufficiently to eliminate the significant increase.
4.1.4.4. Unavoidable Adverse Effects and Level
of Significance After Mitigation
Project emissions of criteria air pollutants and HAPs would produce increases
in the ambient concentrations of both these air pollutants in the immediate
vicinity of the Project mine and process area during the life of the Proposed
Action. Application of the measures proposed as part of the Proposed Action
would prevent impacts to air resources from reaching or exceeding the level
of significance.
4.1.5. Biological Resources
This assessment of the effects of the Project on biological resources
is based on the findings described in several biological technical investigation
reports of the area of the
Proposed Action which are appended to this EIS/EIR as Appendices F,
G, H, I, J, and K. A summary of the findings of the biological surveys is
provided in Section 3.5.6.2. In addition, the findings of the
Biological Assessment of the anticipated effects of the Project on the federal
and state listed and proposed biological resources in the Project area,
prepared on behalf of the BLM (Rado 1997) and
submitted to the USFWS, have been summarized in this assessment, and the
recommended mitigation measures provided in the Biological Assessment have
been integrated into measures provided in this EIS/EIR.
4.1.5.1. Assumptions and Assessment Guidelines
The assessment of impacts assumes the implementation of those measures
incorporated into the project design or required by regulation which avoid
or reduce potentially significant impacts.
To determine the potential significance of the effects of the Proposed Action
on biological resources, it is necessary to consider the relative importance
of the identified biological resources in the vicinity of the area of the
Proposed Action and the degree of potential Proposed Action-related impacts
on these respective resources. As discussed in the regulatory framework
for biological resources section of this EIS/EIR (Section 3.5.1),
factors utilized to determine the relative importance of the biological
resources in the vicinity of the Proposed Action are, in part, based on
species and habitats afforded protection under both the federal Endangered
Species Act (ESA) and the California Endangered Species Act (CESA), as well
as BLM sensitive
species , and other species of concern, collectively referred to as
special-interest species for the purposes of this assessment (see Section 3.5.1).
Based upon NEPA and CEQA guidelines, and commonly accepted criteria, a project
would normally be considered to have a significant effect on biological
resources if it could:
- Substantially affect a rare or endangered species of animal or plant
or the habitat of the species;
- Interfere substantially with the movement of any resident or migratory
fish or wildlife species; or
- Substantially diminish habitat for fish, wildlife, or plants.
4.1.5.2. Impacts of the Proposed Action on Vegetation
and Plant Habitat
In addition to other changes, this section has been modified from the
November 1996 Draft EIR in response to comments to assess the effects of
Project dust which may settle on vegetation.
The Project would impact vegetation and plant habitat primarily through
direct destruction of plants by surface disturbance during construction
of the mine and ancillary facilities. An estimated 1,362 acres of surface
disturbance would result from the Proposed Action from the development of
the mine pits, heap leach pad, waste rock stockpiles, soil stockpiles, process
ponds, haul roads and access road realignment, drainage diversions, ground
water well field and pipeline, electrical power lines, and other ancillary
facilities. The surface locations of these facilities are identified on
Figure 2.1 and Figure 2.2, and the surface acreage
disturbed by these activities is listed in Table 2.2.
Surface disturbance would occur incrementally throughout the early life
of the Project as individual pits are mined and waste rock stockpiles, soil
stockpiles, and process facilities are expanded. Plant habitat would be
lost as result of: initial surface blading of vegetation, stockpiling of
soil and waste rock, and construction of surface facilities and access corridors;
crushing or damage to vegetation as a result of heavy equipment use and
vehicle use and parking; periodic geological survey activities; and the
use of heavy equipment during reclamation activities. Vegetation existing
in the areas of surface disturbance would be destroyed or damaged as a result
of removal, crushing, entombment, soil compaction, or root damage.
A total 1,302 acres of surface disturbance would occur within the Project
mine and process area, of which an estimated 1,215 acres of the sparse,
widely-distributed shrub/scrub vegetation habitat, dominated by creosote
bush, characteristic of the upland areas within the Project mine and process
area, would be affected. The remaining area of surface disturbance, approximately
87 acres, would impact the shrub/tree vegetation (i.e., microphyll
woodland vegetation) habitat characteristic of the primary and secondary
washes within the Project mine and process area. As discussed in Section 3.5.6,
approximately 2 acres microphyll woodland vegetation habitat within
the Project ancillary area and approximately 1 acre of microphyll woodland
vegetation habitat in the overbuilt 92 kV/34.5 kV transmission
line corridor would be subject to surface disturbance.
Vegetation and plant habitat recovery is a function of the type and degree
of soil disturbance. Disturbed or compacted soils associated with construction
or human activity may take longer to recover than soils disturbed by natural
disturbances (i.e., such as flooding), in part because seeds, and perhaps
related symbionts (e.g., rhizobial bacteria), may no longer be present (Virginia
and Bainbridge 1987). Revegetation strategies would be implemented to reduce
the time involved for natural plant establishment on land disturbed by the
Proposed Action. Examples of strategies in desert revegetation include soil
preparation (scarification and topsoil restoration), reseeding, transplantation,
and plant protection (see Section 2.1.11, or Appendix A,
Reclamation Plan). Application of these strategies within the Project area
would continue during the life of the revegetation program under the Proposed
Action.
As discussed in the Reclamation Plan, the revegetation program has been
developed based upon experience gained from revegetation efforts at the
Picacho Mine and information provided by qualified experts on desert flora
and revegetation. When the measures discussed in the Reclamation Plan are
successfully implemented, the effects of surface disturbance from mine construction
and operations on the vegetation and plant habitat within the area of the
Proposed Action would be below the level of significance.
Project mining activities and vehicular traffic would affect vegetation
and plant habitat within the immediate vicinity of the Project area by increasing
the amount of airborne particulate deposition onto vegetation surfaces (see
Section 4.1.4.2). Experiments currently underway in other parts
of the California desert have demonstrated that the short-term effects of
dusting may cause lowered primary production in desert plants due to reduced
photosynthesis and decreased water-use efficiency. No long-term effects
were detected in creosote bushes that were exposed to periodic acute heavy
dust deposition along an unpaved road. Dusted creosote recovered its normal
canopy by shedding dusted leaves and producing new shoots in response to
seasonal rainfall (Personal Communication, S. Ahmann, U.S. Army National
Training Center, June 6, 1997). The projected average annual particulate
deposition onto vegetation outside the boundaries of the Project mine and
process area would be less than 6.0 g/m2 and would not exceed
4.0 g/m2 in areas further than 0.5 km from the Project mine
and process area boundary. Further, the potential effects on vegetation
from dust would be reduced by natural occurrences of wind and infrequent
precipitation which would remove some of the accumulated dust. With the
implementation of the fugitive dust reduction measures contained in the
Proposed Action, the effect of dust from the Proposed Action on vegetation
and plant habitat would be below the level of significance.
Moisture available from watering of roads and other traffic areas for dust
suppression during construction and mining activities could result in a
temporary increase in some opportunistic plant species immediately adjacent
to active roadways or other watered surface areas. Similarly, new low spots
or drainage areas where water could pond or accumulate within the active
portions of the Project mine and process area could result in the introduction
of salt cedar, introduced species or other noxious weeds. Salt cedar could
also invade moist pit areas following the completion of active mining activities
where water may accumulate; however, these conditions are not expected to
exist following the completion of mining (see Section 4.1.3.2.2).
Seasonally moist areas within the remnant East Pit (or West Pit, if mining
is terminated prior to the commencement of backfilling) could result in
small areas (estimated at less than 1 to 2 acres of pit bottom) in which
salt cedar growth might be supported (Personal Communication, Samuel A.
Bamberg, Ph.D., Bamberg and Associates, April 25, 1996). The Proposed
Action includes measures to actively control introduced plant species during
and following active operations. The resulting impacts would be below the
level of significance.
There would be a potential for impacts on vegetation and plant habitat due
to the transport of hazardous chemicals to the Project area via public highways
and access roads. The probability of hazardous chemical spillage occurring
due to a transport accident is considered low, but the potential for occurrence
cannot be entirely eliminated. The preventative and corrective measures
discussed in Section 4.1.12.3 would reduce the effects of the
potential risk to vegetation and plant habitat resulting from spills of
hazardous chemicals being transported to the Project area to below the level
of significance.
Up to 1,200 afy of ground water would be
produced from the Project ground water well field for use in mining operations.
The static elevation of the ground water in the alluvial production reservoir
has been measured at 540 feet below ground surface (WESTEC, Inc. 1996a).
The water table is far below the depth
that surface vegetation could be utilizing the ground water; therefore,
anticipated drawdown and lowering of the ground water elevation as a result
of the proposed ground water production would not impact surface vegetation
or plant habitat.
Microphyll vegetation habitat exists in the wash systems down topographic
gradient of the Project mine and process area (see Figure 3.16).
Concern exists that diversions of the ephemeral drainages around the mine
facilities would change the flow of water through the drainages feeding
this vegetation habitat in the downgradient wash systems. There is also
concern that these hydrologic changes to ephemeral drainages would increase
erosion or affect fluvial processes in the washes, resulting in increased
sedimentation or changes in the quality of water flowing through the Project
area. Construction of facilities within the Project mine and process area
would also eliminate the uppermost portions of some small drainages, reducing
the amount of runoff which may flow down the remaining channel and, thus,
be available to the channel vegetation immediately downstream.
Under the Proposed Action, storm waters in the major ephemeral drainages
would either be allowed to flow naturally through the Project area, or would
be diverted into channels around the Project facilities and returned to
the same natural watercourse downgradient of the Project mine and process
area. Each of the diversion channels would be designed to channel the surface
flow back into the same major downstream ephemeral drainages from which
the flow originated (see Section 2.1.9.7). The diversion channels
through the Project mine and process area would be built to approximate
the original drainage system in both gradient and channel geometry to prevent
erosion, and would be revegetated with microphyll vegetation to establish
the same type plant habitat. Major Project facilities have been located
to minimize the number and amount of small, ephemeral tributaries which
may have their upper reaches eliminated. These Project design measures would
minimize the effects on downstream vegetation and plant habitat from any
potential changes in ephemeral stream flow and fluvial processes to below
the level of significance.
4.1.5.2.1. Impacts to Threatened or Endangered
Plant Species
No federal or California listed, proposed, or special status plant species
were observed during the botanical surveys of the Project area or overbuilt
92 kV/34.5 kV transmission line corridor. Based on the findings
of the surveys and prior database records, no listed, proposed, rare or
special status plants would be affected by this Proposed Action.
4.1.5.2.2. Impacts to BLM Sensitive Plant
Species and Habitat
One BLM sensitive plant species, fairy duster,
was observed along the edges and banks of the smaller (2- to 8-foot wide)
ephemeral drainages within the Project mine and process area and in ephemeral
drainages throughout the vicinity of the Project area. Individual fairy
duster plants would be destroyed and their seed bank potentially lost (i.e.,
the dormant seeds left by previous years= plants would be buried) as a result
of the proposed grading and development activities within the Project mine
and process area. Fairy duster occurs over a large geographic area, including
the Colorado, eastern Mojave, and Sonoran Deserts. Based on surveys, an
estimated 500+ individual plants occur within the Project mine and process
area. Since most of the smaller ephemeral drainages in the Project mine
and process area would be disturbed as a result of Project construction,
all of this habitat, and essentially all of these fairy duster plants, would
be lost. However, the species is locally common, and can and would recolonize
in washes previously disturbed by mining operations (Environmental Solutions
1987). Native seeds, including fairy duster, would be collected from wash
soils for use during reseeding during reclamation activities (see Section 2.1.11.1),
thus replacing the communities lost during Project construction. The impact
resulting from the loss of individual fairy duster plants, and fairy duster
habitat, within the Project area is considered to be below the level of
significance.
4.1.5.2.3. Impacts to CNPS List 4 Species
and Habitat
One CNPS List 4 ("watch" list) species, the winged cryptantha,
was observed within the Project area. This species was reported to exist
in low numbers along the banks of the larger ephemeral drainages. Fewer
than 60 individual plants were estimated to exist within the Project
mine and process area (Rado 1997). These plants would be destroyed and their
localized seed bank and habitat within the Project mine and process area
would be potentially lost as a result of surface disturbance during mine
construction. This species is widespread in distribution, ranging from the
southeastern desert in California into Arizona and Nevada, but it is typically
encountered in low densities and numbers of individual plants. The CNPS
List 4 status indicates that these plants are not "rare"
but are sufficiently uncommon that their status should be monitored. Native
seeds, including the winged cryptantha, would be collected from wash soils
for use during reseeding during reclamation activities (see Section 2.1.11.1),
thus replacing the communities lost during Project construction. Given the
current status and the distribution of the winged cryptantha, the impact
from the loss of the observed plants and habitat within the Project area
would be below the level of significance.
|