BLM RMP Planning Schedule

Ongoing Resource Management Plans (RMP) and Environmental Impact Statements (EIS)

Resource Management Plan/Environmental Impact StatementNotice of IntentScoping ReportDEIS
Notice of Availability
Comment Period FEIS Notice of AvailabilityRecord of Decision
East Alaska RMP/EISMarch 18, 2003June 2003April 29, 2005Ended on
July 28, 2005
July 3, 2006September 7, 2007
Ring of Fire RMP/EISMarch 19, 2003June 2005September 30, 2005Ended on
December 29, 2005
August 25, 2006March 21, 2008
Kobuk-Seward Peninsula RMP/EISJanuary 30, 2004August 24,  2004May 5, 2006Ended on September 15, 2006September 28, 2007September 4, 2008
Bay RMP/EISDecember 6, 2004June 2005September 29, 2006Ended on
January 5, 2007
December 14, 2007Fall 2008
Northeast NPR-A Supplemental IAP/EIS

December 4, 2006

 N/AAugust 24, 2007Ended on November 6, 2007May 16, 2008July 16, 2008

East Interior RMP (Combines 40-Mile RMP; Steese National Recreation Area RMP; White Mountains National Conservation Area RMP; Black River Area)

February 29, 2008September 2008May 2009July 2009April 2010September 30, 2010

Upcoming Resource Management Plans (RMP)

 Resource Management Plan

Start DateFinish Date
Bering Sea - Western Interior RMPTBDTBD
Utility Corridor RMP RevisionTBDTBD
Central Yukon RMP RevisionTBDTBD


Acronyms
DEIS --- Draft Environmental Impact Statement
FEIS --- Final Environmental Impact Statement
NPR-A - National Petroleum Reserve-Alaska
RMP --- Resource Management Plan
TBD -- - To Be Determined