BLM RMP Planning Schedule

Ongoing Resource Management Plans (RMP) and Environmental Impact Statements (EIS)

Resource Management Plan/Environmental Impact Statement

Notice of Intent

Scoping Report

DEIS
Notice of Availability

Comment Period end

FEIS Notice of Availability

Record of Decision

Eastern Interior RMP (Combines 40-Mile RMP, Steese National Recreation Area RMP, White Mountains National Conservation Area RMP, Upper Black River Area)February 29, 2008December 2008TBD *TBDTBDTBD
National Petroleum Reserve - Alaska (NPR-A) Integrated Activity PlanJuly 28, 2010November, 20102012TBDTBD2012
East Alaska RMP/EIS Delta River EA AmendmentApril 10, 2008December 2008March 2010May 2010N/AN/A
Ring of Fire RMP/EIS Haines Block Supplemental EIS AmendmentMarch 2009September 2009TBDTBDTBDTBD
Ring of Fire RMP/EIS Campbell Tract EA AmendmentFebruary 19, 2010TBDN/ATBDN/AN/A
Kobuk-Seward Peninsula RMP/EIS Squirrel River EA AmendmentMay 13, 2010TBDN/ATBDN/AN/A

 * The Draft Eastern Interior RMP/EIS is currently being reviewed by the BLM's Washington Office. It will be released for public comment when internal review is completed.


Acronyms
DEIS --- Draft Environmental Impact Statement
FEIS --- Final Environmental Impact Statement
N/A ---Not Applicable
NPR-A - National Petroleum Reserve-Alaska
RMP --- Resource Management Plan
TBD -- - To Be Determined